Key takeaways
- An indelible mechanical marking identifies each loop at the flow and return on the manifold.
- The layout plan and the flow rate table must be fixed inside the cabinet door.
- Hydraulic balancing is carried out with the circulator running at forced speed, adjusting the graduation of each rotameter.
- The cabinet must always remain accessible without the need to dismantle fixed fittings or joinery.
Loop identification, permanent labelling and handover file
As soon as the coils of cross-linked polyethylene or polybutylene pipe are unrolled, each loop must be identified unambiguously. Too many construction sites end up with markings in grease pencil or on strips of masking tape stuck hastily onto the valves. After a few months, under the effect of temperature variations and condensation, these markings become completely illegible. For a heating installer carrying out maintenance or repairs, an anonymous manifold makes any methodical diagnosis impossible in the event of overheating or a cold room.
- The precise name of the room served according to the architect's room allocation plan (e.g. South Living Room, Bedroom 1, Upper-floor Bathroom).
- The loop sequence number corresponding exactly to the layout diagram and to the thermal calculation report.
- The active length of the unrolled pipe, expressed in linear metres excluding connecting runs.
- The design mass flow rate calculated by the design office, written in litres per minute on the label.
- Check during pullingMark both ends of the pipe with an indelible marker as soon as it is cut, before feeding the pipe through the floor penetration or into the supply duct.
- Fitting the rigid clipsFix the permanent marker rings on the flow and return connections below the Eurocone fittings, before the water pressure test.
- Completing the cabinet sheetFill in the cardboard summary sheet supplied with the manifold, using the final room designations.
- Laminating and fixingInsert the completed document into a transparent self-adhesive pocket firmly pressed against the inside face of the metal door.
The as-built plan is an essential element of the handover file given to site management and the client. This as-built plan must record the exact routes, the areas treated, the laying pitch adopted for each zone and the location of the expansion joints crossed, with protective sleeving. Supplying clear technical documentation is part of the contractor's general duties of performance under the Code of Obligations (CO), and avoids later disputes during alterations or floor penetrations.
Balancing with the flowmeter and rules for positioning the cabinet
Flow rates are never set by guesswork or by the number of turns of the handwheel. Modern manifolds incorporate on each flow a float flowmeter (rotameter), generally graduated from 0.5 to 5 l/min. The water flowing in the transparent body pushes a float whose visible level corresponds to the instantaneous flow of the fluid. Without this balancing, hot water systematically takes the shortest loops, creating a hydraulic short circuit that starves distant rooms such as the bathroom or the living room.
| Room use | Indicative length | Nominal temperature difference | Indicative flow rate |
|---|---|---|---|
| Bedroom | 60 to 75 m | 5 K | 0.8 to 1.2 l/min |
| Bathroom | 45 to 60 m | 4 K | 1.2 to 1.8 l/min |
| Living room / lounge | 80 to 100 m | 5 K | 1.5 to 2.2 l/min |
| Kitchen | 50 to 70 m | 5 K | 1.0 to 1.4 l/min |
To carry out the balancing, the main distribution circulator must run at its operating head, with all thermostatic valves 100% open and the actuators removed or forced into manual position. The fitter unlocks the locking ring of the rotameter, then screws or unscrews the stem until the float's meniscus is aligned with the target graduation. This operation must be repeated twice over the whole bank: changing the flow in one circuit immediately causes a change in differential pressure on the neighbouring circuits.
The installation height of the flush-mounted or surface-mounted cabinet is generally set at 15 or 20 cm above the finished floor, measured under the bottom frame, so as to leave a suitable bending radius for the pipes entering from below. At the acceptance of the work, the actual values measured on the float are recorded on the commissioning sheet. This traceability ensures that, in the event of a later complaint about insufficient comfort, the installer can prove the hydraulic conformity of the installation against the forecasts of the heat balance.
Balancing protocol with flowmeters and recording at the manifold
Hydraulic balancing of an underfloor heating network relies on the rigorous adjustment of the volume flow of each loop to overcome the most unfavourable pressure loss and guarantee the calculated heat output. During commissioning by the heating installer, the circulators of the mixing unit run at constant speed or at proportional differential pressure according to the design requirements. All adjustments are made with the room regulation valves fully open and the electrothermal actuators removed or mechanically locked in the upper position. Without immediate identification of the circuits when connecting the multilayer or cross-linked polyethylene pipes, any action on the micrometric ring of a flowmeter is blind and compromises heat distribution between day rooms and bedrooms.
- Venting check and pressure stabilisationCheck that the manifold is completely vented through the automatic float air vents. Establish the cold static operating pressure required by the installation, generally between 1.5 and 2.0 bar, before starting the secondary circulation pump.
- Adjusting the flow on the flow rotametersTurn the adjustment ring or the transparent body of the flowmeter graduated in litres per minute. Position the visual marker (ball or float disc) exactly on the set value from the thermal calculation report for each room.
- Checking hydraulic interactionsGo through all the flows again after setting the last loop. Since opening or closing a circuit changes the differential pressure available at the manifold, readjust the first circuits if a flow drift appears.
- Mechanical locking and physical readingClip on the red locking caps or tighten the locking lock-nuts to fix the position of the throttle valve. Write the flow rate read on the marking label and transfer the value to the inspection sheet.
| Loop no. | Room designation | Pipe length (m) | Set flow rate (l/min) | Measured flow rate (l/min) |
|---|---|---|---|---|
| 01 | Living room - Glazed bay | 88 | 2.1 | 2.1 |
| 02 | Living room - Inner zone | 76 | 1.8 | 1.8 |
| 03 | Kitchen | 62 | 1.5 | 1.4 |
| 04 | Master bedroom | 94 | 1.6 | 1.6 |
| 05 | Bathroom | 48 | 1.9 | 1.9 |
| 06 | Study / Bedroom 2 | 71 | 1.3 | 1.3 |
Cabinet location, service access and work file
The location of the distribution cabinet must be validated with site management as early as the structural work phase. Whether flush-mounted in a technical partition or exposed in a secondary room (laundry, store, utility cupboard), the distribution box must under no circumstances end up blocked behind a fixed kitchen unit, a washing machine or non-removable joinery panelling. A free frontal clearance of at least 70 cm must be maintained at all times in front of the hinged or removable door. This distance allows spanners to be inserted to retighten the compression fittings, the graduated tubes of the flowmeters to be read at eye level and work to be done on the electrothermal heads without bending the supply cables.
Handing over the installation requires the as-built plan to be included in the technical work file given to the client. This as-built plan details the exact geometric route of each loop, the laying spacing (pitch of 10, 15 or 20 cm), the precise location of the expansion joints crossed with protective sleeving, and the actual developed length in metres of each coil. These measurements allow the building manager or the heating installer carrying out maintenance to recalculate the pressure losses in the event of a future replacement of the circulator or adjustment of the heating curves of the heat pump.
Distribution non-conformities and inaccessible cabinets: handling balancing disputes
On construction sites in French-speaking Switzerland, complaints about underfloor heating mostly come from rooms that are overheated or underheated following sloppy balancing, or from manifolds walled in behind fixed fittings. When an installer works on an installation without labelling and without a record of flow rates, he cannot guarantee the contractual temperature regime. The absence of clear identification of each loop is a clear defect in execution that blocks fine commissioning.
In the event of reversed or missing identification of the coils under the screed, the correction method requires shutting off all the flows at the manifold. The technician bleeds the circuits, then opens a single loop while injecting fluid at 35 °C and observing the surfaces with a thermal camera to trace the actual route. This time-consuming intervention, charged on a time-and-materials basis to the defaulting trade if the temporary marking was erased by a third party, makes it possible to reconstruct the distribution diagram.
To close the work file, the flow rates read on the flowmeter in l/min must correspond to the values in the hydrodynamic calculation report with a maximum deviation of 10%. The signed balancing report, the as-built plan showing the actual layout and the engraved labelling on the inner sheet metal of the cabinet relieve the heating company of liability. Without these three handover documents supplied at the acceptance of the work under standard SIA 118, thermal comfort defects remain attributable to the fitter.
Frequently asked questions
How do you identify an unlabelled loop on a manifold in service?
Close all the flow and return valves at the manifold. Open a single loop at maximum flow, then inject water at a minimum of 35 °C. Using a thermal camera, follow the heating-up of the floor to locate the exact room. Note the estimated length and the observed flow rate, immediately fit an engraved ring on the PE-Xa or PEX pipe, then repeat the operation for each circuit.
What should you do if a flowmeter stays stuck at zero despite the valve being open?
The main cause is residual air forming a pocket, or a mechanical blockage of the float due to hemp residues or sludge. Isolate the loop at the manifold, connect a flushing pump to the drain valve and purge the air with clean water at 2 to 3 bar. If the float remains stuck, unscrew the micrometric ring to free the stem.
Who is responsible for the accessibility of the distribution cabinet after the finishing work?
The heating installer must position his cabinet according to the coordination plans validated by site management. If a kitchen fitter, joiner or plasterer builds a partition or a fixed unit in front of the hatch without the engineer's authorisation, he creates a non-conformity. The heating installer issues a formal notice in the site diary to demand that access be fully cleared.
Which setting documents must be kept in the cabinet?
Inside the cabinet door, stick a laminated sheet stating for each flow: the name of the room served, the pipe length, the inside diameter and the set flow rate in l/min. Add the numerical marker corresponding to the engraved rings fixed on each flow and return. This data must be strictly identical to that in the technical handover file.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).
- norme SIA 118General conditions for the execution of construction work