🧱 CFC 241Emitters: underfloor heating and radiatorsChapter 4 of 10 in the section

Managing the temperature rise: stages, logging and refusing to accelerate

This chapter details the thermal management of the initial heating-up of an underfloor heating system. You will be able to programme the progressive flow-temperature stages, log daily the water values measured at the manifold, formally refuse requests to speed up the schedule and hand over an unchallengeable thermal file to the floor-covering installer.

Key takeaways

  • A gradual temperature rise protects the heating element and prevents cracking of the mineral substrate.
  • The daily reading of flow and return temperatures secures the traceability of the installation.
  • Any demand to accelerate the schedule requires a formal risk notice sent in writing to the site management.
  • The completed and signed heating-up protocol is a condition for the subsequent intervention of the floor-covering contractor.

Programming the temperature stages and daily logging of parameters

The first heating-up of an underfloor heating circuit is not intended to dry out a structure prematurely by force, but to release the mechanical stresses in the pipe coils and their surrounding screed without causing thermal shock. As the heating installer, you are responsible for the control: the temperature rise must be carried out continuously, either linearly or in strict stages, using a mobile electric boiler or the final heat generator switched to commissioning mode.

  1. Initial stabilisation at low temperatureStart the circulation pump with a flow-water setpoint of no more than 25 °C, or the ambient temperature plus 5 °C if the room is very cold. Keep this water temperature stable for at least three consecutive days without interruption.
  2. Daily increments in regular stagesRaise the flow-water temperature by 5 °C per 24 hours until the project's maximum design temperature is reached, generally set between 45 °C and 50 °C according to the thermal calculation notes.
  3. Holding at the maximum design temperatureMaintain the maximum design temperature without variation for a minimum of four full days, while ensuring a constant flow rate in all loops of the manifold.
  4. Controlled cool-down to standby temperatureLower the flow-water temperature by 5 °C per day to return to a value between 15 °C and 20 °C, the standby temperature required before any further work on the floor.
Typical example of a heating-up thermal cycle (complete 14-day cycle)
Cycle dayFlow water setpoint (°C)Measured flow temperature (°C)Return temperature (°C)Circuit pressure (bar)
Day 1 to 32524.821.51.8
Day 43030.125.21.8
Day 53534.929.41.7
Day 64040.234.11.7
Day 74544.838.51.7
Day 8 to 114545.039.21.6
Day 123535.330.81.6
Day 132525.122.01.6
Day 142020.219.11.6

The reading cannot be automated on the mere promise of an unverified electronic sensor. The team leader or fitter goes to the manifold every working day to log the temperature shown on the flow thermometer, the overall return temperature, the static filling pressure and the state of the flow indicators on the flow meters. Any power cut or thermal safety shutdown of the heat pump must be recorded immediately, stating its exact duration.

Formal refusal to accelerate the schedule and handover to the floor-covering installer

Under pressure from the site management or the general contractor trying to make up for a delay on the construction site so that a glued parquet can be laid early, the heating installer is frequently ordered to shorten the heating-up period or to double the daily temperature increments. Giving in to such an order directly exposes the system to abrupt deformation of the pipes, thermal debonding and destructive cracking of the screed surrounding the circuit.

Under art. 365 CO, the contractor has a duty to inform the client without reservation as soon as a circumstance jeopardises the proper execution of the work. Forcing an accelerated heating-up constitutes a technically flawed instruction. The registered letter or official warning email must state that the abrupt rise in temperature creates an immediate risk of shearing at the expansion joints and compromises the mechanical integrity of the structure. If the management maintains its order despite the warning, art. 369 CO releases the contractor from liability if the defect results from the formal orders given by the client despite the contrary notices served.

  • Categorically refuse to sign a commitment document providing for setpoint increases of more than 5 °C per 24 hours.
  • Notify in writing the refusal to accept the consequences of cracks caused by a shortened cycle at the client's request.
  • Document with photographs the setpoint settings and flow thermometers at the time the acceleration order is received.
  • Keep a complete copy of the heating-up records in the company's technical file for the ten-year warranty.

At the end of the cool-down and circuit stabilisation, the complete initial heating-up protocol must be formally handed over to the person in charge of the site management and to the craftsman responsible for laying the parquet or tiles. This official handover certifies that the hydraulic installation has operated at its maximum design temperature without load failure and that the system is now regulated at the prescribed laying temperature, thereby releasing access to the premises for the next trade.

Control of temperature ramps and daily hydraulic traceability

The commissioning heating of an underfloor heating system is not intended to heat the building for the finishing work, but to bring about, in a controlled manner, the thermal expansion of the embedding body before it is locked in by the final covering. The heating installer intervenes once the minimum curing time of the binder has been observed by the screed contractor. For a conventional cement screed, the progressive temperature rise begins only after a waiting period of at least 21 days after pouring, compared with 7 days for a calcium sulphate flowing screed.

The temperature rise is carried out in strict increments on the regulating valve or the electronic module of the heat pump. Start-up takes place with flow water set at 25 °C, or at the room's ambient temperature if that is lower, but never below 20 °C. This initial setpoint remains locked for 3 consecutive days in order to avoid any thermal shock in the mass. The setpoint is then raised by 5 °C per 24-hour period up to the project's maximum design temperature, commonly set at 45 °C or 50 °C according to the thermal calculation notes. This maximum stage is maintained continuously for at least 4 days, then the cool-down begins at the same gradient of 5 °C per day until the temperature returns to 20 °C.

Standard thermal protocol of an underfloor heating system (cement screed basis)
Operating phaseFlow setpoint stagesMinimum durationParameters monitored at the manifold
Phase 1: Initial start-up25 °C constant3 daysBalanced flow in each loop, no air, flow-return delta T below 7 K
Phase 2: Ascending rampIncrease of 5 °C per 24 h period4 to 5 daysProgressive actuation of the mixing valve, operation of the circulation pump
Phase 3: Test at maximum temperatureProject setpoint (e.g. 45 °C)4 full daysOverheating control by manually reset safety aquastat (cut-off at 55 °C)
Phase 4: Descending rampDecrease of 5 °C per 24 h period4 to 5 daysStabilisation of hydraulic pressure between 1.5 and 2.0 bar, temperature readings
Phase 5: Service hold20 °C to 22 °CUntil layingStable surface temperature allowing the floor layer's moisture measurements

The daily logging of temperatures is the technical proof that the programme was carried out regularly. Each working day, the fitter or team leader reads the actual temperature on the flow thermometer of the distributor, the manifold return temperature, the static pressure of the network on the pressure gauge and the ambient air temperature in the reference zone. Any power supply failure, any HVAC shutdown or any circulation anomaly must be logged with the exact time and the corrective action taken. If a technical interruption of the heating exceeds 24 hours during the temperature rise, the protocol does not resume where it stopped: it restarts at the lower stage so as not to subject the structure to sudden stress.

Order to shorten the schedule and adversarial handover of the file

In the finishing phase, pressure exerted by the site management or the client to speed up the laying of a glued parquet is recurrent. A compressed schedule often leads the site management to demand that steps be skipped, water at 45 °C be injected directly from the second day, or the total heating time be reduced to less than a week. Applying such a forced regime creates excessive differential thermal gradients between the base and the surface of the mineral substrate, triggering destructive cracking, flatness defects and future bond failures of the wooden floor covering.

Faced with a service order imposing an accelerated temperature rise that does not comply with the recognised rules of the art, the heating installer must immediately give written notice of refusal. The document makes clear that the requested rate of temperature increase exceeds the mechanical adaptability of the materials and contravenes the physical principles of heat distribution. Under art. 369 CO, the client's rights in respect of defects of the work are excluded where the defective execution is personally attributable to the client, in particular because of orders given contrary to the contractor's formal notices. The registered letter or meeting minutes expressly record that the company disclaims any warranty on the behaviour of the emitter assembly and its finishes if the order is maintained against its formal advice.

When the complete prescribed cycle ends without incident, the heating installer draws up the official heating-up protocol. This contractual document summarises the start-up dates, the complete history of the temperatures recorded each day, the operating pressures and the signature of the responsible technician. It is officially transmitted to the site management and handed over in person to the floor-covering installer before the latter begins preparing the substrate. This handover releases the heating installer from the interface: the parquet layer then has the data needed to proceed, under their own trade responsibility, with marking the measurement points and carrying out the dryness checks required before final laying.

Handling execution disagreements and handing over the protocol

On the construction site, schedule pressure frequently leads the site management to demand a reduction of the heating cycle in order to allow early laying of floor coverings. The heating installer must on no account modify the ramps programmed on the control of the heat pump or the temporary boiler to satisfy this request. A temperature rise that is too abrupt causes internal mechanical stresses and shearing of the screed. In the event of a formal order to shorten the heating, the heating installer issues a written notice pointing out the risks of damage to the work, in accordance with the Code of Obligations (CO) and the rules of the SIA 118 standard.

  1. Logging of actual parametersThe installer reads the flow temperature, return temperature and operating pressure daily at the underfloor heating distributor. These data are entered on the recording sheet fixed to the distribution cabinet.
  2. Refusal to sign an addendum to the protocolThe company refuses to sign any document certifying a completed heating-up if the nominal stages have not been fully run through in accordance with the technical specifications of the heating plant.
  3. Adversarial handover to the floor-covering installerThe completed and signed heating-up protocol is handed over against receipt to the parquet layer or tiler before the start of their work. This document certifies only the thermal history delivered by the hydraulic network.

The heating installer sticks strictly to their role as thermal operator of the heat-transfer fluid. They take no calcium carbide samples and give no opinion on the screed's suitability to receive timber, these tasks belonging to the field of floor coverings. As soon as the initialled temperature record has been handed over, the installation is switched to its normal weather-compensated curve or left on standby setpoint according to the written instructions of the site management.

Frequently asked questions

What should be done if the site management demands that temperature stages be skipped?

The installer sends a written notice formalising the refusal to modify the heating programme. This document recalls the risks of cracking of the substrate through thermal shock and releases the heating installer from liability for the resulting material damage. If a mandatory order is confirmed in writing, the company applies the imposed instructions only after having notified the forfeiture of warranty rights for the mechanical behaviour of the heated floor.

How should temperatures be logged if there is no automatic control?

In the absence of a digital controller with an automatic heating-up function, the heating installer manually controls the motorised mixing valve or adjusts the flow setpoint of the generator. The technician takes a daily reading from the thermometers fitted on the flow and return manifolds. Each value read is entered manually in the construction site logbook with the date, the exact time and the fitter's signature.

Must the heating installer check the screed moisture before handover?

No. The role of the CFC 241 heating installer is limited to producing and distributing thermal energy according to the prescribed curves, then handing over the traceability of the water flow temperatures. Measuring residual moisture with a carbide bomb is the exclusive responsibility of the screed layer or the parquet layer under the rules of their trade, before authorisation to apply their own glued finish.

At what precise moment must the heating-up protocol be handed over to the other trades?

The summary document is transmitted once the progressive cooling phase is complete, before the parquet layer starts setting out. The handover takes place by adversarial transmission against signature with the site management and the floor-covering craftsman. This transmission certifies that the hydraulic circuit has reached its design temperature and has returned to a surface temperature compatible with bonding the floor covering.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work
  • CO art. 369Exclusion of the client's rights for defects of the work where the defective execution is personally attributable to the client (orders given contrary to the contractor's formal notices or any other cause)