🧱 CFC 241Commissioning, control and acceptanceChapter 2 of 10 in the section

The outdoor sensor: façade, sun, exhaust air and the consequences of a poor choice

This chapter gives you the method for correctly positioning an outdoor heating sensor and making its measurement reliable. You will learn how to determine the right façade, how to respect the heights and thermal safety distances from windows or exhaust air outlets, and how to check that the temperature matches on the controller before acceptance.

Key takeaways

  • Positioning on a north or north-west façade protects the measurement from low morning sun radiation.
  • The sensor is fixed at two thirds of the building height, at least two metres above the ground.
  • A minimum clearance of two metres from windows and exhaust air outlets avoids any false thermal signal.
  • The ohmic check at the controller terminals validates the accuracy of the recorded outdoor temperature.

Positioning on the building envelope: orientation, height and thermal pitfalls of the façade

The position of the outdoor sensor directly determines the calculation of the flow temperature by the heating curve. A positioning error distorts the weather-compensated flow curve of the installation, leading to complaints about lack of comfort or significant overconsumption. The typical case occurs in the depth of winter, in February: a sensor mounted on an east-facing façade picks up the first rays of the sun from seven o'clock in the morning. While the outdoor ambient air remains below zero, the sensor housing heats up by direct radiation and sends the controller an erroneous value that is eight to ten degrees too high. The control system immediately lowers the water flow temperature, or even shuts off circulation to the heat pump or boiler, leaving the building without heating at the exact time of the occupants' peak demand.

To guarantee stable control, the basic rule requires mounting on a north or north-north-west façade. If the architectural layout rules out access to the north, the west façade may be an acceptable alternative, provided that the sensor is fitted with a ventilated sun shield. South and east façades are strictly to be avoided for controlling the main heat generator.

Minimum positioning distances for the outdoor sensor
Disturbing elementMinimum clearance distancePhysical effect on control
Tilt-and-turn window or door2.0 m to the side and aboveInput of warm indoor air during morning ventilation.
Ventilation exhaust air (CFC 244)3.0 m in all directionsLukewarm stale air flow distorting the outdoor temperature.
Chimney outlet or gas balanced-flue terminal2.5 m above and to the sideHot combustion gases altering the heating curve.
Natural ground or outdoor terrace2.0 m above the groundRadiation from the ground and disturbances caused by snowdrifts.

As regards mounting height, the sensor is generally placed at two thirds of the building height for a detached house or a small apartment building, i.e. between two metres and two and a half metres above the ground. This arrangement keeps the sensor out of reach of vandalism while avoiding the influence of heat rising from the ground or of cold air layers stagnating at ground level during night frost. On tall buildings, the upper storeys exposed to excessive prevailing winds are avoided; fixing at first- or second-floor level, on a blank section of façade, is preferred.

Connection, ohmic check and validation of the value read by the controller

Once the physical location has been validated, the mechanical mounting and the electrical connection must preserve the integrity of the measurement. The sealed housing is mounted on the surface of the render using suitable plugs, without creating an excessive thermal bridge in an external insulation system. The cable entry must face downwards to form a drip loop, preventing any moisture from penetrating towards the cable gland. Sealing the cable passage through the wall also prevents warm, humid air from inside the boiler room or the dwelling from entering the sensor housing, which would distort the measurement and condense on the sensing element.

  1. Visual check of the immediate surroundingsInspect the façade to check that there are no recent thermal obstacles (air-conditioning cabinet, powerful new outdoor light fitting, roof overhang blocking the natural ventilation of the sensor).
  2. Reference measurement on siteTake the exact ambient air temperature in the immediate vicinity of the outdoor sensor using a calibrated thermometer, in the shade of the façade.
  3. Disconnection and ohmic checkIn the boiler room, disconnect the two sensor wires from the control terminal block. Measure the electrical resistance with a multimeter and compare the value with the manufacturer's characteristic curve (Pt1000, Ni1000 or NTC sensor).
  4. Comparison on the controller displayReconnect the sensor and read the value displayed in the controller's commissioning menu. The difference between the reference thermometer and the reading on the device must not exceed half a degree.

If a significant difference appears between the physical measurement and the value read, the installer checks the line resistance of the wiring. An excessive cable length combined with too small a cross-section creates a parasitic resistance that artificially shifts the measurement on Pt100 or resistive sensors. Where the existing wiring cannot be replaced, most modern heating controllers allow a correction offset to be applied in the configuration parameters. At the end of commissioning, the record documents the exact orientation of the sensor, the mounting height, the reference temperature found and the value validated on the thermal controller, thereby formalising acceptance in accordance with the rules of the trade.

Impact of solar radiation and clearance distances on the façade

Inadequate positioning of the outdoor sensor distorts the whole heating curve from the very start of the cold season. The most damaging error on installations in the lowlands or at medium altitude is to mount the housing on an east or north-east facing façade. In February, from seven o'clock in the morning, low sun strikes the plastic housing or the adjacent masonry directly. The temperature perceived by the sensing element then rises by several kelvins within a few tens of minutes, artificially going from −2 °C to +8 °C. The control system reacts at once by lowering the water flow temperature, or even by switching off the zone circulation pump, at the precise moment when the users call for thermal comfort.

The recommended façade orientation remains the north to north-north-west quadrant. This sector ensures that the measuring cell receives no direct radiation, while remaining representative of the outdoor ambient air temperature experienced by the heat-losing walls of the building. Where the layout of the site requires mounting towards the west or north-west, fitting a ventilated sun shield supplied by the manufacturer is essential to neutralise late-afternoon radiation.

Positioning constraints of the outdoor sensor according to façade elements
Disturbing elementRecommended minimum distanceDirect consequence on control
Window or French window2.0 m to the side or 1.5 m belowOpening the sashes causes a puff of warm air and a premature shutdown of the heating.
Exhaust air outlet (ventilation or dryer)2.5 m to 3.0 m away from the exhaust coneThe residual warm air flow induces a continuous drop in the water flow temperature.
Outdoor unit of a heat pump3.0 m outside the cold discharge flowThe ice-cold air blown out by the evaporator causes the living spaces to overheat.
Natural ground or roof terrace2.0 m to 2.5 m of clear heightReflection from snow or heating of the bitumen distorts the climate data acquisition.

The mounting height determines how representative the signal is. In the case of a detached house or a small rental building, the sensor is generally installed at a height of between 2.0 m and 2.5 m above the finished ground level. This dimension keeps the device out of reach of mechanical impacts, mud or rainwater splashes, and avoids the layer of snow accumulated on the ground. On a multi-storey apartment building, the usual practice is to fix the sensor at mid-height of the heated living zone, commonly on the second or third floor, on the two thirds of the north façade, so as to take into account the vertical thermal gradient of the building.

On-site check protocol and metrological validation in the controller

When commissioning a heat generator, checking the value read by the boiler room controller is an essential self-inspection step under the SIA 118 standard. The installer cannot be satisfied with a mere display without a comparative physical check. The measurement is taken with a calibrated thermometer placed a few centimetres from the wall-mounted housing, sheltered from direct wind and radiation, after thermal stabilisation of the measuring enclosure for at least ten minutes.

  1. Ohmic reading at the foot of the façadeOpen the sealed housing, disconnect one of the two conductors from the terminal block and measure the ohmic resistance with a calibrated digital multimeter. Compare the measured value with the nominal curve of the thermistor (for example NTC or PTC sensor) as a function of the temperature measured by the reference thermometer.
  2. Loop check in the boiler room panelReconnect the sensor on the façade, then measure the overall resistance at the controller input terminals. This test validates the integrity of the connecting line, the absence of a short circuit, the absence of oxidation and the absence of excessive parasitic resistance caused by a cable of insufficient cross-section or too great a length.
  3. Comparison between displayed value and actual temperatureConsult the diagnostic menu of the control panel. The difference between the outdoor temperature shown on the screen and the temperature measured on site by the service thermometer must not exceed 0.5 K. Beyond that, a fault search on the line or the sensor is required.
  4. Adjustment of the correction offsetIf a minor, constant discrepancy persists after checking the wiring, set the software offset available in the controller so that the displayed value matches the actual physical value before starting the heating cycles.

The passage of the sensor cable through the insulated building envelope requires rigorous attention to sealing. Any conduit opening into the sensor base without being closed off with sealing mastic creates a chimney effect: tempered, humid air from the indoor technical rooms escapes to the outside and continuously flows over the measuring resistor. This parasitic flow produces a reading that is too warm in winter and causes internal condensation on the electronic component, leading in the short term to irreversible ohmic drift. Sealing the conduit on both the inside and the outside guarantees the durability of the climate reading.

Correcting positioning errors and eliminating thermal drift

An outdoor sensor exposed to the rising sun distorts the climate analysis from the first hours of operation. In February, direct radiation at seven o'clock in the morning raises the temperature of the housing several degrees above the real ambient temperature. The controller immediately lowers the water flow set point according to the heating curve, causing a premature shutdown of the heat pump or boiler while the building is experiencing its maximum heat losses. If the plan imposed this defective location, art. 365 para. 3 CO applies: the contractor must immediately inform the client of any circumstance compromising the proper execution of the work.

  1. Physical repositioning of the housingMove the sensor to the north or north-west façade, sheltered from any direct radiation. Respect a mounting height at two thirds of the façade for a building of two to three storeys, or at least 2.5 metres above the ground.
  2. Insulation and sealing checkPass through the envelope with a sealed conduit to avoid internal thermal bridges. Use a cable gland facing downwards to prevent run-off water from penetrating into the connection housing.
  3. Comparative metrological checkMeasure the temperature in immediate contact with the housing using a calibrated thermometer. Compare the measurement with the value displayed on the heating controller; correct the residual offset in the control parameters.

Electronic corrections of slope or sensor inertia never durably compensate for a sensor bathed in morning rays or licked by an air extraction flow. Physically moving the sensing element remains the only method in accordance with the rules of the trade to guarantee the contractual heating curve and prevent discomfort for the users.

Frequently asked questions

Why does morning sun on an east-facing façade disturb the control at seven o'clock?

Low solar radiation strikes the housing from dawn and warms its sensor by conduction and radiation. The controller interprets a fictitious rise in the outdoor air while the building is experiencing the morning cold peak. By applying the weather-compensated flow curve, the control system reduces the flow temperature or shuts down the generators, causing a sharp drop in indoor comfort at the moment when heating needs are highest.

What clearance distance should be applied from windows and exhaust air outlets?

The sensor must be kept at least two metres away from any façade opening, window, door or transom light through which indoor heat may escape. The same minimum distance of two metres applies without exception to mechanical ventilation exhaust outlets, kitchen extractor hoods or flue outlets. This clearance avoids the creation of a warm microclimate that would permanently distort the signal sent to the controller.

What should be done if the north façade of the building is completely inaccessible for cabling?

When the north façade is inaccessible, the north-west orientation is the recommended fallback solution. If no shaded wall can receive the cable, mounting on a west façade remains possible provided that a ventilated sun shield is installed around the sensor. Using an industrial radio-frequency sensor of a suitable class also makes it possible to reach the north façade without major through-wall cabling work.

What measurement difference is tolerated between the value displayed on the controller and a reference thermometer?

At commissioning, the permissible difference between the value measured by a reference thermometer placed against the housing and the value read on the controller must not exceed 0.5 kelvin. A larger discrepancy generally indicates an abnormal line resistance, poor tightening on the terminal block, an unsuitable conductor cross-section or ohmic drift of the thermosensitive element, requiring recalibration by offset or replacement of the component.

Texts and standards cited

  • CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he must immediately inform the client, failing which he bears the consequences (para. 3).