Hydraulic distribution and balancing: the execution reference
Intended for heating team leaders and foremen, this section brings together the methods for calculating, setting and checking hydraulic distribution. From the boiler room to the last emitter, it covers the sizing of closed networks, circulator control, water quality and methodical balancing to guarantee the design flow rate at every floor in accordance with SIA 384/1 and the Suissetec guidelines.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
0.5 to 1.0 m/s
Recommended flow velocity in main risers
1.3 times
Minimum hydraulic test pressure relative to the operating pressure
< 100 Pa/m
Target linear pressure loss to limit noise and pumping power
0.5 bar
Absolute minimum pressure at the highest point of the installation
Technical scope of the hydraulic network and construction site interfaces
Hydraulic distribution is the backbone of every thermal installation. It covers the transport of heat energy from the production unit to the emission terminals through a closed-circuit network. For the heating fitter, the operational objective is to deliver the heat-transfer fluid at a precise flow rate, with controlled pressure loss and no noise nuisance whatsoever, while proving the conformity of the installation at acceptance.
Respecting the interfaces guarantees the overall quality of the works and limits disputes at handover. Under art. 364 CO, the contractor is responsible for the proper and faithful execution of the work entrusted to them. On the heating construction site, this means supplying correctly sized pipework that is leak-free, vented, balanced and insulated in accordance with the recognised rules of the art.
| Installation element | CFC 241 responsibility (Heating) | Third-party interface |
|---|---|---|
| Filling disconnector | Connection to the heating circuit | Installation of the disconnector on the drinking-water supply (CFC 250) |
| Underfloor heating beneath screed | Laying of pipes and manifolds and pressurisation | Embedding, expansion joints and moisture check (CFC 281) |
| Electrical distribution cabinet | Connection of circulators to the boiler room terminal block | Supply line and main circuit breakers (CFC 232) |
| Ventilation duct coils | Flow/return pipework and control valves | Air handling unit and air distribution network (CFC 244) |
Sequential methodology: from rough installation to the acceptance record
The execution of a hydraulic network leaves no room for improvisation. An imbalance on one riser inevitably leads to excess pump consumption, whistling at thermostatic valves and complaints about lack of comfort on the upper floors. The chapters of this section should be consulted in the actual order in which the work progresses on the construction site.
- Design and geometric layout (J3-01 and J3-09)Start by setting the pipe diameters according to the mass flow rates and the permissible pressure losses, allowing in advance for fixed points and free sliding to absorb thermal expansion without causing creaking.
- Integrity check and mechanical safety (J3-02 and J3-07)Before any insulation is applied, the network undergoes a water-pressure leak test documented in writing, while the pressure-maintaining unit and the safety valve are calibrated accurately.
- Conditioning of the heat-transfer fluid (J3-06)Filling must always be carried out with demineralised or softened water complying with the recommendations of the trade, preventing early scaling and the formation of destructive magnetite sludge.
- Hydraulic setting, pumping and insulation (J3-03, J3-05 and J3-08)The electronic circulators are adjusted to the correct characteristic curve. The balancing valves at the riser base and at the distributors are throttled to the setpoint values read on the differential pressure gauge, before the thermal insulation shells are closed.
- Final inspection and energy metering (J3-04 and J3-10)In the event of a complaint about under-heating at the end of a branch, a step-by-step diagnostic method rules out air-flow and mechanical pitfalls, complemented by the metrological verification of the individual heat meters.
Every thermal distribution network must undergo documented hydraulic balancing to guarantee the nominal flow rates at full load and at partial load.
Suissetec guideline
By applying this step-by-step approach, the site foreman ensures that the commissioning record is based on measured, indisputable physical quantities, eliminating costly rework after the tenants have moved in.
📘 Chapters in this section 10
Sizing pipework: flow rate, velocity, pressure drop and flow noise
Master pipe-section calculations to eliminate whistling and reduce pumping power.
Hydraulic distribution and balancingThe hydraulic pressure test: test pressure, duration, permitted pressure drop and test report
Secure your acceptance inspections with an impeccable, undisputed pressure test protocol.
Hydraulic distribution and balancingBalancing properly: flow rate calculation, balancing valves and recorded readings
Adjust the control valves to the actual values to guarantee comfort on every floor.
Hydraulic distribution and balancingThree degrees colder on the top floor: the diagnosis, step by step
Quickly identify the exact cause of a lukewarm radiator without needlessly raising the heating curve.
Hydraulic distribution and balancingSetting the circulator: curve, differential pressure and power consumption
Select the optimal control mode to halve the electricity consumption of the pumps.
Hydraulic distribution and balancingCircuit water: hardness, magnetic sludge, corrosion and treatment
Protect the heat exchangers against scaling and sludge through rigorous water conditioning.
Hydraulic distribution and balancingThe expansion vessel: volume, pre-charge pressure and safety valve
Calculate the useful volume and the pre-charge pressure to avoid nuisance tripping of the safety valve.
Hydraulic distribution and balancingInsulating pipework: thicknesses, singular points and losses in unheated rooms
Insulate pipework and fittings in the boiler room in accordance with the cantonal legal energy-efficiency requirements.
Hydraulic distribution and balancingLet it move: expansion, fixed points, sliding supports and creaking noise
Arrange fixed and sliding clamps to absorb expansion without transmitting structure-borne noise.
Hydraulic distribution and balancingMetering per dwelling: meter position, accuracy and disputes
Install and connect heat meters without disturbing the metrology or distorting the billing.
