🧱 CFC 241Section 2 of 610 chapters

Heat pump: source, installation and noise: the execution reference

Intended for heating installers, site foremen and foremen, this section details the complete installation of a heat pump in line with Swiss good practice. From the choice of source to acoustically compliant siting under SIA 181, including brine connection and condensate drainage, it provides the criteria essential for ensuring thermal efficiency, preventing neighbour disputes and passing the works acceptance.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

Swiss technical installation recommendations

80 cm

Minimum frost-free depth for the condensate drainage trench in French-speaking Switzerland

Norme SIA 384/2

25 % to 30 %

Usual mass concentration of propylene glycol to ensure frost protection of a closed loop

Norme SIA 181

3 dB

Minimum theoretical acoustic attenuation provided by a solid screen blocking the direct line of sight to the source

art. 367 CO

60 days

Statutory period for notifying defects found in a building work during regular inspections

Technical scope: what the installer handles and what is delegated

Installing a heat pump requires a strict delimitation of responsibilities on the construction site. The heating installer under CFC 241 is responsible for the entire thermal cycle: selection of the source, sizing according to SIA 384/2, physical siting, hydraulic connections and adjustment of the heating curves. Interactions with the immediate surroundings require rigorous coordination with the neighbouring trades to avoid shifting of responsibility in the event of an acoustic dispute or underperformance.

  • Handled directly: sizing of the generator, calculation of the acoustic proof for the permit application, installation of the intermediate base, anti-vibration connections, brine manifolds and flow balancing.
  • Primary and secondary connections: hydraulic connection of the buffer tanks, management of pressure safety devices, air venting, make-up with demineralised water and antifreeze treatment of the closed circuit.
  • Control settings: configuration of the heating curve slope, time delay of the backup stages, cycle reversal parameters for defrosting and programming of the night setback time slots.

Conversely, the heating installer must not encroach on reserved competences. The main electrical supply from the main switchboard, residual-current protection and sizing of the supply line are the responsibility of the electrician under CFC 232. The domestic drinking water connection falls under CFC 250, while the embedding of the coils and the screed drying protocol belong to CFC 281. Finally, forced-air distribution through ducts falls under CFC 244.

Execution path: the logical order for siting and setting up the heat pump

The success of a thermal installation tolerates no improvisation in the sequence of work. The decisions taken during the feasibility study directly determine the final compliance of the construction site with regard to the municipality and the requirements of SIA 181.

  1. Choice of resource and admissibility statusCheck geological feasibility via the cantonal groundwater protection register or analyse the air resource available on the plot (chapters J2-01 and J2-05).
  2. Predictive acoustic calculation and official formDetermine the sound power of the machine, calculate the geometric attenuation towards the windows of noise-sensitive rooms and include the necessary noise barriers to validate the permit (chapter J2-02).
  3. Mechanical base and condensate managementBuild a decoupled slab, install anti-vibration mounts sized according to the rotation frequency and ensure frost-free gravity drainage of the defrost water (chapters J2-03 and J2-04).
  4. Source hydraulics and sealingPressurise the probes or the evaporator, adjust the glycol content with the refractometer and check the integrity of the sealed refrigerant circuit (chapters J2-06 and J2-07).
  5. Commissioning, defrosting and acceptanceSet the defrost termination parameters, measure the actual seasonal performance factor against the catalogue promises and instrument the installation in the event of a neighbour complaint (chapters J2-08, J2-09 and J2-10).
Critical validation milestones on the construction site
StepCheckpointTechnical referenceRisk if omitted
Outdoor sitingDistance to neighbouring windows and directivitySIA 181 standardObjection to the building permit or order to relocate the unit
Base blockContinuous resilient joint between base and slabProfessional rulesPropagation of structure-borne noise into the living structure
Water drainageFrost-free depth of the sump or heating cableSwiss requirementsFormation of ice sheets and blocking of the fan by frost
Brine circuitDensity of the water-glycol mixtureSIA 384/2Freezing of the evaporator or severe drop in heat transfer

All pressure measurements, volumes of antifreeze injected and acoustic compliance certificates must be recorded systematically in a report placed in the works file handed to the trade manager at acceptance of the works.

📘 Chapters in this section 10

Heat pump: source, installation and noise

Air, geothermal probe or groundwater: what really decides the choice

Compare the available resource, plot constraints and operation to lock in the right source from the preliminary design stage.

Heat pump: source, installation and noise

Noise in the neighbourhood: siting, screen, night mode and complaint

Calculate the acoustic attenuation at the receiver to site the outdoor unit without risking a block at the public inquiry.

Heat pump: source, installation and noise

Decoupling the machine: base, anti-vibration mounts and flexible connections

Install the concrete base and calibrate the dampers to stop the propagation of structure-borne noise into the frame dead.

Heat pump: source, installation and noise

Draining condensate: actual volume, pipe freezing and ice sheets

Size the gravity drainage and the heating cable to eliminate the risk of a winter ice rink on the pavement.

Heat pump: source, installation and noise

Drilling a borehole heat exchanger: suitability map, authorisation and protected groundwater

Consult the cantonal water protection registers to start drilling without incurring liability for the aquifer.

Heat pump: source, installation and noise

The brine circuit: antifreeze, concentration, purging and pressure check

Dose the glycol with the refractometer and degas the closed circuit to sustain heat exchange without cavitating the circulator.

Heat pump: source, installation and noise

Refrigerant: leak-tightness, register and what an unauthorised person must not touch

Know the boundaries of legal intervention on the hermetic circuit in order to record the checks in the maintenance log.

Heat pump: source, installation and noise

Defrosting: frequency, loss of efficiency and the sign of a wrong setting

Identify abnormal cycle reversal to correct the heating curve before the machine freezes up completely.

Heat pump: source, installation and noise

Advertised COP, real-world efficiency: what the catalogue doesn't tell you

Decipher the discrepancies between the factory data sheet and the seasonal performance factor recorded on the heat meter.

Heat pump: source, installation and noise

A complaint arrives: measuring at the receiving point, corrective measures and what is negotiable

Respond methodically to a neighbour's formal notice by checking the compliance of the installation with regard to the municipality.