Commissioning, control tuning and acceptance: the execution framework
This section guides site foremen and construction managers through the critical phases of thermal commissioning. It covers balancing heating curves, running tests under real load, drawing up the acceptance records and the contractual follow-up of the first winter season. It sets out the steps required to hand over a robust installation, instruct the operator and clear defects efficiently in accordance with SIA 118.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
60 days
Statutory period to report defects in an immovable work
5 years
Statutory limitation period for defects in an immovable work
2 years
Usual period for claims for apparent or hidden defects
0.2 to 0.8
Characteristic curve slope for low-temperature underfloor heating
Scope of work, real-condition tests and technical limits
Commissioning a thermal installation is the decisive transition between mechanical installation on the construction site and the dynamic operation of the building. The heating installer is fully responsible for the heat-transfer fluid: pressure test, complete flushing of the circuits, meticulous venting of non-condensable gases, checking the charge pressures of the expansion vessels and verifying the hydraulic safety devices. This critical phase demands absolute rigour to guarantee the energy efficiency of the generators and the comfort of the occupants from the first winter demand.
| Component or task | Heating installer (CFC 241) | Adjacent trade |
|---|---|---|
| Terminal control | Connection of actuators and curve setting | Low-voltage wiring and communication bus (CFC 238) |
| Underfloor heating | Gradual temperature rise of the water circuit | Drying check and screed moisture measurement (CFC 281) |
| DHW top-up | Checking the thermal priority of the generator | Sanitary distribution, mixers and drinking-water recirculation (CFC 250) |
| Electrical supply | Checking the current drawn by the circulators | Connection to the main switchboard and sub-circuit breakers (CFC 232) |
From a hydraulic standpoint, the conformity of the distribution depends on strict compliance with the design flow rates prescribed by SIA 384/1. The installer checks that the temperature difference between flow and return of each loop matches the heat load calculations. Static or dynamic balancing valves must be set to the specified values to avoid distribution imbalances, the primary causes of pipe whistling and cold zones on distant floors.
Methodical progression: from first firing to the end of the warranties
Optimising a thermal system is a continuous process that extends over the whole of the first heating season. An installation perfectly adjusted in workshop conditions or in mid-season needs to be put to the test by sub-zero temperatures to reveal the time constants specific to the building envelope. The chapters of this section take foremen and construction managers through a structured route, addressing in turn the requirements of tuning, contractual compliance and warranty under SIA 118.
- Climate calibration and initial settings (J5-01 to J5-03)Determine the slope and curve base point suited to the emitters, relying on a sensibly positioned outdoor sensor. Assess the dynamic behaviour of the envelope to set night setbacks sensibly, thereby avoiding excessive overcapacity demands on the generators during the morning boost phases.
- Acceptance records and handover of the works (J5-04 and J5-05)Record every flow, temperature and pressure measurement rigorously on the joint acceptance record. Then train the operators or caretakers using condensed technical documentation and display the call-out contact details permanently in the boiler room to secure operation.
- Winter operation, remote monitoring and fault handling (J5-06 to J5-08)Deploy emergency solutions without delay during critical shutdowns in severe cold to ensure frost protection is maintained. When faced with complaints from the client, technically assess the severity of the defects to determine priority interventions, while monitoring operating parameters through authorised remote-monitoring modules.
- Season fine-tuning and closing the warranties (J5-09 and J5-10)Use the feedback from the first winter to perfect the control settings and methodically clear outstanding defects. Hand over a comprehensive works file including the updated execution diagrams and the certificates of conformity, which are essential to seal the administrative closure of the works contract.
Diligent handling of faults during the probationary year prevents disputes at formal acceptance. Under art. 367 CO, the owner checks the condition of the work and promptly notifies any defects found, the period being sixty days for immovable works. By keeping the complete history of the intervention sheets and commissioning records, the contractor establishes his good faith and demonstrates the conformity of his work in view of the statutory limitation period set in art. 371 CO.
Finally, the success of a handover depends on the transparency of the instructions given to the client. A properly equipped operator does not make handling errors that damage compressors or motorised valves. Reading these modules in full gives site teams a proven method to close their thermal construction sites calmly, sustain commercial relationships and protect the company against unfounded warranty callbacks.
📘 Chapters in this section 10
Setting the heating curve: slope, parallel shift and correction by occupant feedback
Adjust the slope and offset to eliminate user complaints from the first autumn chills.
Commissioning, control and acceptanceThe outdoor sensor: façade, sun, exhaust air and the consequences of a poor choice
Place the sensor away from parasitic airflows to avoid supply temperature drift in your controllers.
Commissioning, control and acceptanceRéduit de nuit : économie réelle, relance et bâtiment à forte inertie
Control the boost times to guarantee morning comfort without oversizing the generator output.
Commissioning, control and acceptanceThe commissioning report: readings, settings and signatures
Record every hydraulic measurement to contractually validate performance at the switchover to operation.
Commissioning, control and acceptanceRemettre l'installation : instruction, notice courte et contacts d'urgence
Hand over a readable installation to the client with a concise manual that prevents unnecessary call-outs.
Commissioning, control and acceptanceNo heating in January: on-call duty, remote diagnosis and emergency heating
Organise emergency winter call-out and electrical backup to keep the affected building frost-free.
Commissioning, control and acceptanceQualifying the defect: nuisance to use, minor defect, major defect
Distinguish temporary discomfort from a fundamental defect to prioritise interventions in accordance with SIA 118.
Commissioning, control and acceptanceRemote monitoring: useful alarms, access and limits of intervention
Set up relevant remote technical alerts without violating the privacy of the building's occupants.
Commissioning, control and acceptanceThe first season counts double: warranty, adjustment visit and reservations
Use the fine settings of the first winter season to clear the warranty defects.
Commissioning, control and acceptanceThe as-built file: up-to-date hydraulic diagram, data sheets and warranties
Gather the final hydraulic diagrams and technical manuals to formally close the works file.
