Skip to content
Website
🧱 CFC 241Hydraulic distribution and balancingChapter 2 of 10 in the section

The hydraulic pressure test: test pressure, duration, permitted pressure drop and test report

The hydraulic test of a heat distribution network tolerates no approximation. On a construction site in French-speaking Switzerland, the heating installer applies the Suissetec guidelines to set the test pressure relative to the set point of the safety valve. This chapter details bleeding the network, holding the pressure, interpreting variations and drawing up the jointly signed test report.

Key takeaways

  • According to the Suissetec guideline, the test pressure is set at 1.3 times the maximum operating pressure.
  • Complete air bleeding must always precede the thermal equalisation stage before any pressure gauge reading is taken.
  • The minimum test duration allows plastic pipes to stabilise and every visible joint to be inspected.
  • The jointly signed test report protects the installer against any later dispute at acceptance of the work.

Determining the test pressure and stabilising the network before measuring

The hydraulic test guarantees the mechanical tightness and strength of the heat distribution pipes (main networks in steel, risers in copper, floor distribution in multilayer or cross-linked polyethylene) before they are concealed in service shafts, suspended ceilings or floor screeds. The Suissetec guidelines require heat generators, diaphragm expansion vessels and safety devices sensitive to overpressure to be systematically isolated, in order to avoid any damage to their internal mechanisms. The piping is filled slowly from the low point of the riser, keeping the manual air vents at the high points open. This careful bleeding removes all residual air pockets, whose compressibility would damp volume changes and distort the reading of the test pressure.

According to the Suissetec guidelines, the hydraulic test pressure is at least 1.3 times the maximum permissible operating pressure of the circuit, with a minimum value set at 4 bar. For a typical apartment-building installation protected by a safety valve set at 3 bar, the test pump raises the pressure to 4 bar measured at the highest point of the distribution. The installer connects a large-diameter calibrated pressure gauge, of accuracy class 1.0 and with a scale graduated in steps of 0.1 bar, directly to the test valve of the main manifold or to a dedicated drain connection.

Test parameters according to the hydraulic distribution material
Piping materialMinimum test pressureStabilisation phaseExpected mechanical behaviour
Black or threaded steel1.3 × P_operating (min. 4 bar)15 to 30 minutesStrictly constant pressure after thermal equilibrium
Brazed or pressed copper1.3 × P_operating (min. 4 bar)30 minutesFull pressure retention with no drop of the needle
Multilayer (PEX-Al-PEX)1.3 × P_operating (min. 4 bar)60 minutes with readjustmentViscoelastic expansion compensated by regular topping-up with water
Cross-linked polyethylene (PE-X)1.3 × P_operating (min. 5 bar)120 minutes with cyclesPlastic creep controlled by scheduled re-injections of fluid

Holding the test pressure and recording the jointly signed test report

Holding the pressure does not mean watching a needle for a few minutes before leaving the construction site. For plastic pipes subject to creep under stress, the method recommended by Suissetec splits the operation into two stages. The preliminary test compensates for the deformation of the material: the pressure is restored every ten minutes by manual pumping for half an hour, then observed for sixty minutes. If the pressure drop does not exceed 0.2 bar with no weeping at the pressed fittings or sockets, the main test can begin, for a contractual minimum duration of two hours, or even twenty-four hours on large distribution networks.

  1. Systematic visual inspectionExamine every pressed fitting, welded joint, flange and isolating valve with an inspection mirror and by touch. Applying absorbent paper to sensitive points immediately reveals micro-weeping that ambient heat may evaporate.
  2. Final reading and pressure analysisRecord the final pressure and the ambient temperature at the end of the test period. A drop that cannot be explained by cooling of the room requires the test to be stopped and the leak to be located by pressurising with air and applying a foaming agent.
  3. Depressurising to operating pressureOnce the test is validated, immediately bring the hydraulic load back to normal operating pressure, so as not to stress the sealing gaskets and valve seats unnecessarily before the installation is first commissioned.
  4. Jointly signed formComplete the hydraulic test report on site and have it signed without delay by the installer and by the site management or the consulting engineer.

This test report is the material proof of the condition of the work within the meaning of art. 367 CO. By signing it, the client attests that there is no apparent defect at the end of the tightness check. Two years later, if water damage occurs following the plugging of a partition by another trade or an unforeseen mechanical deformation, this jointly signed report formally clears the installer by proving that the piping as delivered was perfectly tight.

Pressure drift, thermal influence and non-conformity criteria

On the construction site, a falling pressure gauge needle does not systematically indicate a leaking pressed fitting or a porous brazed joint. The distinction between a physical loss of tightness and a thermodynamic variation determines the validity of the hydraulic test under the guidelines of the Suissetec association. The filling water generally comes from the site water supply at a temperature between 8 °C and 12 °C. Introduced into a closed building whose ambient temperature is around 20 °C, it warms up, which increases its volume and therefore artificially raises the pressure if the circuit is bled and closed. Conversely, a fluid introduced hot into a cold slab contracts in volume, which makes the pressure fall without a single drop leaving the pipe.

The rheological behaviour of the distribution materials also changes how the test is read. Cross-linked polyethylene (PEX) pipes and multilayer pipes undergo creep under stress: the polymer expands elastically as the load is applied. For these materials, the procedure requires a pre-test phase with regular readjustment of the pressure at the test pump before the countdown of the main test is started. On a network of welded black steel or pressed copper, elastic deformation is negligible; any continuous pressure drop after the degassing phase therefore indicates a material tightness defect.

Pressure behaviour of heating networks according to the type of pipe
Distribution materialMechanical effect under pressureNormal pressure trendAlert or test retake threshold
Black steel (welded or grooved)No elastic deformation at the scale of the pressure gaugeStrictly stable pressure after thermal equalisationContinuous drop of more than 0.1 bar over 2 hours
Copper and carbon steel (pressed)Almost no deformation, EPDM O-rings seatingRapid stabilisation within 30 minutesInstantaneous pressure drop or weeping at the fitting
Multilayer (PEX/Alu/PEX)Moderate creep of the polymer core under radial stressSlight initial drop compensated by maintenance pumpingLoss of more than 0.2 bar after the stabilisation phase
PEX and polybutylene (underfloor heating)Pronounced viscoelastic expansion of the wallRapid drop during the first hour requiring readjustmentContinuous decline with no plateau during the final 2-hour test

Using a calibrated pressure gauge of class 1.0 or 0.6, mounted at the low point of the section under test, remains mandatory to make the reading beyond dispute. The operating pressure gauges built into pump units or heat generators are not accurate enough to validate the tightness check.

Evidential value of the jointly signed test report and warranty cover

The pressure test only has contractual weight if a test report is drawn up immediately on the construction site. This document must bear the joint signatures of the CFC heating fitter or the site foreman and of the representative of the site management. A pressure reading kept only in the installer's own log is not admissible as joint evidence if water damage occurs later, in particular when screeds are poured or service shafts are closed.

  1. Compiling the technical test fileMark the physical limits of the section under test on the hydraulic principle diagram, identifying the closed isolating valves and the sensitive devices removed beforehand.
  2. Recording the physical test valuesRecord the nominal operating pressure, the test pressure applied, the precise start and end times of the measurement, the ambient temperature and the temperature of the filling water.
  3. Visual check of the jointsWalk the entire route to inspect every fitting, branch, valve and flange while the pipes are still visible and uninsulated.
  4. Joint signature and filingHave the test report initialled by the site management before the pipes are physically covered, then add the original to the as-built documentation file.

The SIA 118 standard governs the conditions for checking the work at acceptance. Under art. 367 CO, the client checks the condition of the work as soon as it is practicable to do so and notifies the contractor of any defects. The hydraulic test report proves that the piping was delivered free of any initial leak. If a leak is reported later during the statutory warranty period set by art. 371 CO, this document protects the installer against claims arising from mechanical damage inflicted on the pipes by other trades during the finishing work.

Retest protocol in case of a non-conforming pressure drop

When the pressure gauge shows a drop exceeding the tolerances permitted by the Suissetec guidelines or weeping appears, the hydraulic test is declared non-conforming. No compromise is acceptable: the test pressure, set at 1.3 times the maximum operating pressure with a usual minimum of 4 bar, must be held without failure. Trying to compensate for a drop by repeatedly injecting more water without identifying the origin of the fault invalidates the entire technical acceptance.

  1. Methodical sectioningClose the isolating valves riser by riser, then the stop valves of the floor manifolds. Isolating each sub-assembly makes it possible to pinpoint the leaking zone in pressure steps without discharging the entire circuit.
  2. Locating the leak and bleeding the fittingsCheck first the screwed devices, the automatic air vents left open and the pressed fittings that have not received their mechanical crimping. Use a neutral foaming leak detector on the demountable fittings.
  3. Mechanical correction of the jointDrain only the section concerned, cut out the defective connection and redo the pressing, the seal or the brazed joint in accordance with the piping manufacturer's jointing instructions.
  4. Repeating the complete test cycleRestart the test from the beginning: filling, careful degassing, raising to the test pressure, thermal stabilisation phase, then holding under continuous monitoring for the full contractual period.

The failed result must be recorded on the initial inspection sheet. As soon as the second attempt succeeds, a new hydraulic test report is drawn up. This document records the nature of the retest, the pressures observed, the holding time and the precise time stamp. It is signed jointly on the construction site by the heating installer and the site management, thereby ruling out any later dispute over the warranty of the work under the SIA 118 standard.

Frequently asked questions

How should I react if the pressure drops during the first 30 minutes on a multilayer pipe?

This initial drop reflects the inherent elasticity of synthetic materials under stress and does not mean there is a leak. The test pressure must be restored by manual pumping during the stabilisation phase prescribed by the Suissetec guidelines. The official holding measurement starts only after this stage of mechanical adaptation of the pipe.

Can the safety valves be left in place during the hydraulic test?

No. The safety valves of a distribution network are generally set at 3 bar, whereas the test pressure frequently exceeds 4 bar under the regulatory formula. The valves must be isolated or removed and temporarily replaced by sealed plugs to prevent them from opening or being damaged.

What should I do if a temperature difference changes the pressure gauge reading?

Filling water injected at a low temperature warms up in contact with the building's ambient air, causing a rise in pressure, or the reverse in the event of a cold draught. The fluid and ambient temperatures at the start and at the end of the test must be recorded on the jointly signed test report to justify these slight physical variations.

What is the legal value of the test report in the absence of the site management?

A document signed unilaterally by the heating fitter loses its value as joint evidence. If the site management cannot attend the final reading, the installer must notify it of the date in writing. In the event of proven default, recording the calibrated pressure gauges in time-stamped photos and giving formal notice help to protect the company's liability.

Texts and standards cited

  • SIA 118General conditions for the execution of construction work

In the same section