🧱 CFC 241Heat pump: source, installation and noiseChapter 6 of 10 in the section

The brine circuit: antifreeze, concentration, purging and pressure check

Filling a brine circuit tolerates no approximate dosing. An under-dosed mixture exposes the evaporator to destructive ice formation, while an overdose collapses the seasonal efficiency through thermal throttling and excess circulator consumption. This chapter guides you through optical calibration with the refractometer, complete degassing at high flow rate and the lasting securing of the static pressure.

Key takeaways

  • The antifreeze protection is measured exclusively with an optical refractometer calibrated for the fluid used.
  • Flushing is carried out loop by loop at a sustained flow rate to drive out all air pockets completely.
  • The static pressure is set strictly to the pre-charge of the expansion vessel dedicated to the brine.
  • The standardised label on the manifold records the type of glycol, the mass percentage and the date of the pressure test.

Refractometer dosing and loop-by-loop hydraulic flushing

The geothermal heat-transfer fluid ensures heat exchange without freezing during the sub-zero return temperatures at the evaporator. Visual estimation or the float hydrometer are strictly prohibited on the construction site: the viscosity of the mixture and temperature variations distort density readings. Only the optical or digital refractometer gives an exact reading of the freezing point, which must lie between -13 °C and -15 °C for ground probes in French-speaking Switzerland. This usually corresponds to a dosage of 25 % to 30 % of antifreeze fluid. The instrument must first be calibrated with demineralised water and the measurement must be read on the scale corresponding to the molecule used (monoethylene glycol or monopropylene glycol). Under-dosing leads to surface icing of the plate evaporator, abruptly degrading the heat exchange and causing a low-pressure fault shutdown, or even mechanical perforation of the exchanger. Conversely, a massive overdose increases the kinematic viscosity, degrades the flow regime and needlessly overloads the circulators, drastically reducing the overall coefficient of performance of the installation.

Injection and control parameters for a geothermal loop
Technical parameterMethod or toolReference valueConsequence of a defect
Antifreeze concentrationCalibrated optical refractometer-13 °C to -15 °CExchanger icing or loss of efficiency
Flushing velocityFlushing station flowmeter> 0.45 m/s per probeResidual air bubble and loss of prime
Dilution waterConductivity meter< 100 µS/cm (demineralised water)Mineral deposits and localised scaling
Loop filtrationWashable tank strainer100 µm at dischargePremature clogging of the heat pump strainer filter
  1. Refractometer calibration and mixture preparationClean the measuring prism with a soft lint-free cloth, place two drops of distilled water on it and set the boundary line to 0 °C. Prepare the mixture of demineralised water and antifreeze in the pumping tank, then check the index to confirm the target freezing point before any filling.
  2. Connecting the station and loop-by-loop purgingConnect the high-capacity flushing pump to the filling valves of the manifold. Isolate all probe circuits and open only the first loop. Maintain a sustained flow rate ensuring a minimum flow velocity of 0.45 m/s in order to carry away the air trapped in the lower bends.
  3. Continuous bleeding and sequential switchingCirculate the fluid to the open tank through the fine-mesh filter until the return is completely clear, with no emulsion or air splashing. Close the purged loop, switch to the next one and repeat the operation. Carry out a final overall circulation to equalise the pressures.

Static pressure, annual check and mandatory labelling

After the heat-transfer fluid has been completely degassed, the adjustment of the static pressure determines the durability of the installation and protects the brine pump against cavitation. The cold static pressure must be defined taking into account the geometric height of the building and the nitrogen pre-charge of the brine expansion vessel. Before the final filling, the vessel membrane must be checked with a pressure gauge without water pressure: the nitrogen pre-charge is commonly set between 0.5 and 1.0 bar depending on the high point of the internal pipework. The static filling pressure of the brine is then set 0.3 bar above this cold pre-charge, ensuring a minimum fluid reserve in the bladder. The safety valve of the geothermal circuit, generally set at 3 bar, prevents any accidental overpressure following summer temperature rises.

The annual check of the brine circuit is essential to prevent any insidious corrosion of the stainless steel or copper-brazed plate evaporator. The technician takes a sample to measure both the freezing point with the refractometer and the pH using test strips or a calibrated pH meter. Thermal ageing and micro-ingress of oxygen eventually degrade the glycol molecules into glycolic or formic acids, which exhaust the buffering corrosion inhibitors. A pH below 7.5 or a cloudy, blackish appearance indicates critical acidification requiring complete draining, pressure flushing and injection of a fresh charge. All measured values are recorded in the heat pump's operating logbook.

Brine viscosity and refractometer metrology

In a ground-source or brine-to-water heat pump, estimating the antifreeze mixture by eye is a technical fault with serious consequences. A lack of product immediately exposes the plate evaporator to destructive freezing during winter peak loads, when the evaporation temperature drops below zero. Conversely, an over-concentrated brine penalises the coefficient of performance (COP) throughout the service life of the installation. Monopropylene glycol or monoethylene glycol has a dynamic viscosity clearly higher than that of water. Beyond a concentration of 25 % to 30 %, the hydraulic pressure losses in the geothermal probes or ground baskets increase exponentially. The flow in the tubes and the exchanger risks changing from turbulent to laminar, which drastically degrades the overall heat transfer coefficient and forces the circulator to consume a disproportionate amount of electrical power.

To guarantee the right balance between thermal protection and hydraulic efficiency, the measurement is carried out exclusively with an optical or digital refractometer fitted with automatic temperature compensation (ATC). Antifreeze testers or float hydrometers are strictly prohibited on the construction site: their reading depends too closely on the temperature of the fluid sampled and on the anti-corrosion additives, causing reading errors of several percent. Before each check at the manifold, the operator calibrates the refractometer with a few drops of distilled water, aligning the light-dark boundary line on zero. The brine is then placed on the clean prism, the cover is closed without trapping an air bubble and the freezing point is read directly on the scale specific to the type of fluid used. As the scales for propylene glycol and ethylene glycol differ, exact identification of the product is essential to avoid unintentional under-protection.

Influence of the monopropylene glycol content on the physical parameters at 0 °C
Concentration by volume (%)Freezing point (°C)Pressure loss factorFlow regime in the probe
15 %-5 °C1.15Optimal turbulent (high risk of freezing)
25 %-14 °C1.35Turbulent maintained (recommended compromise)
33 %-21 °C1.65Laminar transition (degraded efficiency)
45 %-32 °C2.10Fully laminar (circulator overconsumption)

Flushing flow rate, static pressure and traceability in the boiler room

A perfect concentration does not protect the installation if air pockets remain in the buried circuits. Filling is never done via the drinking water network without a compliant backflow preventer, nor with the small circulator of the heat pump. Flushing and purging require a powerful external pumping station, capable of delivering a minimum flow velocity of 0.5 m/s in each probe loop to carry the bubbles out. The operation is carried out loop by loop on the manifold, keeping the other valves closed. Circulation is continued until all foam has disappeared in the transparent tank of the station. In the boiler room, the permanent installation of a microbubble air separator on the brine return, immediately upstream of the evaporator, captures the gases released during continuous operation and avoids nuisance trips of the low-pressure switch.

The permanent labelling of the circuit in the boiler room seals the compliance of the work. Placed visibly in the immediate vicinity of the brine manifold and the filling unit, this marking avoids disastrous mix-ups during future repairs or maintenance. In the case of subsequent top-up, mixing two fluids of different origin — for example a monopropylene glycol with an ethylene glycol or incompatible inhibitor packages — causes gelling of the product or massive precipitation of organic sludge, irreparably clogging the heat exchanger.

  • Exact trade name and chemical nature of the heat-transfer fluid (e.g. inhibited non-toxic monopropylene glycol).
  • Actual measured percentage by volume and the corresponding frost protection temperature (in degrees Celsius).
  • Total volume of heat-transfer liquid contained in the whole geothermal system (in litres).
  • Date of initial commissioning and identity of the heating installation company (CFC 241).

Fault diagnosis and recovery protocol on a brine circuit

On a ground-source heat pump, a malfunction of the geothermal circuit rarely comes from a compressor failure. Two faults account for the majority of commissioning breakdowns: blockage by an air lock following incomplete flushing and blocking of the exchanger by crystallisation of the fluid. A low-pressure alarm on the refrigerant circuit almost systematically indicates a collapsed brine flow or a film of ice on the evaporator plates. If the loop pressure gauge shows a drop below the required static pressure, the safety shutdown blocks heat production to protect the generator against bursting of the exchanger block.

Field diagnostic tree for a fault on the source circuit
Observed symptomPhysical causeMetrological checkCorrective action
Immediate LP shutdown at start-upAir pocket at the high point or closed loop valveZero differential pressure across the circulator terminalsDynamic loop-by-loop purge with the flushing pump
Gradual drop in evaporationInsufficient antifreeze concentration, onset of icingReading of the refractive index on the refractometerPartial draw-off and re-injection of pure glycol to correct
Abnormal circuit pressure lossGlycol overdose causing excess viscosityDensity measurement or protection temperature below -20 °CMetered dilution with softened water and new optical check
Brine pressure at 0 barExternal leak or deflated expansion vessel membraneCheck of the nitrogen pressure of the vessel disconnected from the circuitNitrogen recharge to P0, leak search and return to Pstat
  1. Isolating the generatorSwitch off the heat pump control. Close the isolating valves of the evaporator to lock out the machine before any connection.
  2. Immediate optical checkTake a few drops of fluid via the drain valve and measure the protection with the temperature-compensated refractometer.
  3. Pressure flushingConnect the external mobile station with basket filter. Inject the fluid in counter-flow loop by loop until all emulsion has disappeared.
  4. Pressure adjustment and traceabilityRestore the cold static pressure. Replace the identification label on the manifold, stating the date, the product and the value read.

Frequently asked questions

Why is the float hydrometer prohibited for setting the water-glycol mixture?

The acid tester or float hydrometer is calibrated for a fixed liquid temperature, generally 20 °C. On a heating construction site in winter, a brine at 6 °C distorts the density reading through volume contraction, displaying a misleading thermal protection. Only the optical refractometer with automatic temperature compensation gives a reliable measurement of the refractive index of propylene or ethylene glycol.

How do you remove an air bubble trapped in a deep geothermal probe?

Purging a 150-metre probe cannot be done with the internal circulator of the heat pump. A test pump must be connected, capable of supplying a flow rate of at least 2 to 3 cubic metres per hour per loop, generating a flow velocity above 0.6 metres per second. This velocity carries the air pockets to the open degassing tank of the station.

What static pressure should be applied on a brine manifold in the basement?

The initial pre-charge pressure of the expansion vessel membrane must compensate for the static height of the highest point of the geothermal connection, plus a cavitation reserve for the circulator, i.e. approximately 0.5 bar at least. In workshop practice, the circuit is filled cold between 1.5 and 2.0 bar to maintain a constant positive pressure margin in the circuit.

What technical details must appear on the brine circuit label?

The label fixed on the manifold must state the exact nature of the antifreeze, in particular whether it is propylene or ethylene glycol based, its brand name, the measured concentration by volume and the corresponding protection temperature. It also records the estimated total volume, the commissioning date and the cold operating pressure to ensure maintenance follow-up.