Key takeaways
- Measuring the flow and return temperatures at the foot of each riser identifies the fault.
- Blindly raising the heating curve creates overheating without correcting the under-flow at the terminal units.
- The actual flow rate measured at the balancing valves confirms the lack of hydraulic authority.
- Recording joint inspection records frames the remedial work on defects in accordance with standard SIA 118.
What is checked in the boiler room and the mistakes to avoid immediately
When an under-heating complaint comes in from penthouses or converted attics, the first mistake in the field is to change the central control settings. Raising the flow set point of the boiler or heat pump solves nothing. This manoeuvre temporarily masks the imbalance while causing massive over-consumption on the lower floors, whistling at the thermostatic valves on the ground floor and a drop in the overall efficiency of the installation.
The diagnosis must begin in the basement with an overall inspection of the hydraulic distribution. Before operating any valve, the fitter checks the static pressure of the system on the manifold pressure gauge. Insufficient water pressure or a deflated expansion vessel starves the top of the riser and encourages air to accumulate in the terminal radiators, mimicking a network failure.
- Checking static pressure and air ventingCheck that the filling pressure compensates for the geometric height of the building plus a minimum service margin at the high point.
- Recording temperatures at the foot of each riserUsing a calibrated contact thermometer, measure the flow and return temperature of each riser under stabilised set-point conditions.
- Measuring the actual flow rate at the foot of the riserConnect an electronic differential pressure gauge to the pressure test points of the balancing valves to determine the actual volumetric flow rate in cubic metres per hour.
A comparative analysis of the temperature drops immediately reveals the origin of the problem. If an end-of-line riser shows a temperature difference between flow and return clearly greater than that of the central risers, the heat-transfer fluid is not circulating fast enough to supply the last emitters. The actual flow rate measured at the regulating valve then confirms a critical hydraulic under-flow compared with the nominal design value.
Joint inspection record and methodical rework of the distribution
When the thermal shortfall is evidenced by room temperatures below the contractual requirements, the installer must organise a measurement session on site. In contracts subject to standard SIA 118, the remedying of defects requires indisputable data to be produced before any alterations to the works begin. Art. 368 CO sets out the client's rights in the event of defects in the work, including repair at no cost if the installation does not deliver the agreed performance.
| Measuring point | Observed temperature difference | Measured / theoretical flow | Corrective action |
|---|---|---|---|
| Risers close to boiler room | Very small drop (3 to 5 K) | Measured over-flow (+40 %) | Throttling of the static balancing valve |
| Distant risers / attic | Excessive drop (> 18 K) | Measured under-flow (-50 %) | Opening the valve or fitting a differential pressure regulator |
| Top-floor radiators | Body lukewarm at the top, cold at the bottom | Almost no flow at the radiator heads | Replacing the thermostatic valve body |
The joint inspection records taken before remedial work must be recorded in minutes signed jointly by the client's representative and the contractor. This document formalises the differential pressures measured, the actual flow rates and the indoor temperatures measured at the centre of the reference rooms, with shutters closed and thermostatic heads fully open.
Restoration relies on two targeted technical actions. In the basement, the installer adjusts the setting of the differential pressure control valves to ensure hydraulic authority on the most disadvantaged sections. On the top floor, dismantling the terminal units makes it possible to check that there is no sludge in the adjustment elbows and to readjust the internal presetting of the thermostatic bodies to the Kv value required by the heat-loss calculations.
Temperature measurements per riser and recording of the actual flow rate
Once raising the overall heating curve or changing the circulator set point has been ruled out to avoid overheating on the lower floors, the investigation moves to the foot of each riser. Under-heating found on the upper floors of a residential building most often results from a hydraulic supply deficit. The heat-transfer fluid preferentially takes the short loops located near the heating plant. To establish the fault objectively without altering the regulating devices, the installer applies a rigorous measurement procedure, starting with the flow and return temperature measurement for each riser.
- Recording surface temperatures with a contact thermometerMeasure the temperature on each flow and return pipe at the bottom of the risers. Clean the metal of any trace of rust or flaking paint so that the contact probe can be applied with thermal paste. A flow-return temperature difference on a riser greater than the design value reveals a circulation speed that is too low and a flow insufficient to reach the terminal radiators.
- Measuring the differential pressure across the balancing valvesConnect an electronic differential pressure gauge to the piezometric pressure test points of the existing regulating valves. This measurement gives the actual delta p across the device in order to determine precisely the imbalance and the actual flow rate measured, by comparison with the manufacturer's pressure-drop curve.
- Checking for the absence of a hydraulic short circuitCheck the return temperature of the risers closest to the main distribution. A return abnormally close to the flow temperature reveals an excessive flow bypassed at the foot of the building, depriving the disadvantaged risers of the required head.
| Finding at the foot of the riser | Flow-return difference (delta T) | Measured flow compared with calculation | Consequence on the top floor |
|---|---|---|---|
| Riser close to boiler room | Small (4 to 8 K) | Above 140 % | Overheating, thermostatic valve throttled |
| Intermediate riser | Normal (15 to 20 K) | Compliant (90 to 110 %) | Room temperature compliant |
| Riser at the end of the network | High (above 25 K) | Below 60 % | Thermal shortfall of 3 K at the winter peak |
Joint inspection records and remedying of defects
Resolving a heat distribution problem engages the contractor's contractual liability. In the case of a recent building or a full boiler-room refurbishment that has not reached the contractual temperature targets, the intervention follows formal rules. Taking joint inspection records before remedial work is the essential step for defining the scope of services without dispute over the award.
These records must be taken jointly with the site management or the client's representative, during a stabilised heating period and without direct sunshine on the façades. They include the written record of the indoor temperatures measured at the centre of the rooms at 1.5 metres above the floor, the flow and return temperatures of each riser, and the differential pressure measured at the foot of each section.
- Partial draining and fitting of automatic pressure-independent balancing valves on the under-supplied risers.
- Replacement or resetting of the existing manual valves according to the heat load calculation provided by the engineering office.
- Targeted flushing of the sludged risers that have caused abnormal singular pressure losses observed on the differential pressure gauge.
- Checking the stroke of the valve stems and presetting the thermostatic bodies of the top-floor flats.
- Drawing up the final hydraulic balancing report, signed by the installer and sent to the site management.
Final compliance is not judged on the mere impression of the occupants, but on the stabilisation of the calculated flow rates at the regulating valves. The installer records the final values on the balancing sheet attached to the boiler-room operating file, certifying that each riser receives its nominal volumetric flow regardless of variations in opening on the other levels.
Escalation protocol and rework under warranty in case of persistent imbalance
When the initial adjustments do not eliminate the temperature difference on the top floor, the installer must avoid the classic pitfall: raising the heating curve or forcing the circulator speed. This manoeuvre masks the hydraulic imbalance, creates whistling at the thermostatic valves on the lower floors and causes unjustifiable over-consumption. Faced with a difference that persists, the file moves from simple operational adjustment to the contractual handling of a technical non-conformity.
The first step is to formalise joint inspection records before any further intervention on the regulating devices. The installer places calibrated room-temperature loggers in the cold flats and in the reference flats on the lower floors for a minimum of forty-eight hours. At the same time, a flow and return temperature measurement per riser is taken in the boiler room, together with a reading of the differential pressure on each riser-foot balancing valve. This comparison between the theoretical design flow and the actual measured flow objectively establishes the volume deficit suffered by the most disadvantaged branch.
- Checking the terminal pressure dropCheck the setting of the thermostatic valve mechanisms on the top floor and check that there is no residual air at the air vent at the top of the riser.
- Checking the authority of the riser-foot valvesReplace outdated fixed devices with automatic differential pressure regulators to absorb the load variations of the building.
- Joint balancing reportRecord the final mass flow rates, the temperature drops riser by riser and the stabilised room temperatures.
The defect is definitively cleared once the actual flow rates have been realigned with the engineer's calculation sheets. The installer records these values in the final operating file handed over to the site management.
Frequently asked questions
Why should the heating curve not be raised to heat the top floor?
Raising the heating slope to compensate for a lack of supply at the top level systematically overheats the lower flats. The thermostatic valves on the intermediate floors close abruptly to curb this excess supply. This reaction displaces the residual flow, induces hydraulic noise and generates unnecessary energy consumption, without correcting the physical cause, which remains the lack of differential pressure available on the upper branch.
What should be done if the actual flow measured at the foot of the riser remains below the calculated value?
If the fully open balancing valve does not reach its set-point flow, the authority of the pump and the pressure drop of the upstream distribution must be checked. Partial sludging of the riser foot or a clogged strainer in the boiler room often limits the flow. After cleaning the strainers, adding a differential pressure regulator stabilises the riser independently of valve closures on the other circuits of the building.
How can joint inspection records acceptable to the site management be recorded?
The procedure requires calibrated measuring instruments. The room loggers are fixed in the centre of the living rooms, away from solar gain and draughts. In the boiler room, the contact temperatures on the flow and return of each riser are noted at the same time with a calibrated surface-mounted thermometer. These measurements are initialled jointly on a hydraulic record form.
What remedial work is required if the risers have no measuring points?
Where there are no pressure test points on the risers, the minimum remedial work requires partial draining and the fitting of modern balancing valves with piezometric test points. Without these devices, the actual flow cannot be quantified or adjusted. The installer takes advantage of this shutdown to fit automatic flow or differential pressure regulators in order to ensure lasting dynamic balancing over the full height of the building.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work and handling of defects
- CO art. 368Client's rights in the event of defects in the work: refusal, price reduction, remedial work, damages