🧱 CFC 241Emitters: underfloor heating and radiatorsChapter 3 of 10 in the section

Before pouring: pressurisation, monitoring and written record

This chapter details the hydraulic test and monitoring procedures for underfloor heating coils before the screed layer starts work. You will learn how to lock in the joint inspection record, keep the network under constant pressure during pouring, and methodically locate an undetected leak before the mortar sets.

Key takeaways

  • The hydraulic test is carried out with water or air depending on the actual risk of frost.
  • The pressure gauge stays in place and visible at the inlet of each distribution manifold.
  • The signed joint inspection record formally transfers custody of the work to the screed layer.
  • Infrared thermography precisely locates concealed punctures after the screed has hardened.

Maintain the test pressure and sign the joint inspection record before embedding

Connecting the coils of PEX or multilayer pipes to the distribution manifolds marks the end of the mechanical installation. Before any embedding by the screed company, the heating installer must fill the system, bleed all the air and pressurise the network. This test is not a mere internal check: it guarantees the physical integrity of each loop before the pipe becomes inaccessible.

Thermal stabilisation of the fluid requires a mechanical resting time of at least two hours. Synthetic materials undergo an initial phase of elastic relaxation, which naturally lowers the initial reading by a few tenths of a bar without any leak. Once the pressure has been readjusted and stabilised over a period of 24 hours, the installer proceeds with the joint signing of the record with the site supervisor and the representative of the screed company.

  1. Reading and locking the pressure gaugeFit a calibrated dial pressure gauge of class 1.6 or better on the bleed valve of the manifold, equipped with a witness needle or a fixed visual marker.
  2. Visual check of sensitive areasInspect each loop outlet, each expansion joint crossing fitted with its corrugated sleeve and each retaining clip.
  3. Signing the joint inspection recordHave the hydraulic test record countersigned, stating the pressure reading, the exact time and the intact visual condition of the emitter networks.

The role of the written record is legal as much as technical. Under art. 365 CO, the contractor notifies the client of any circumstance that jeopardises the proper or timely execution of the work. Handing over a leak-tight network, attested by a record before pouring, establishes the initial conformity of the piping. If damage occurs afterwards during the delivery of aggregates or the pulling of the mortar, the document relieves the heating installer of the presumption of defective workmanship.

Monitoring the network under the screed and locating accidental mechanical rupture

Throughout the pouring of the flowing or traditional screed, the piping must remain under a pressure of at least 3 bar. This internal load serves two critical functions: it prevents the pipe wall from being crushed under dynamic loads and instantly signals an accidental puncture.

Typical causes of puncture and pressure-drop symptoms
Mechanical damageSymptom at the pressure gaugeImmediate consequence
Pinching by the wheel of a loaded wheelbarrowSudden pressure drop to 0 barWater geyser visible in the fresh mortar
Blow from an aluminium straightedge or rakeSlow, continuous pressure dropConcealed seepage within the thickness of the insulation
Later drilling for a door stop or bufferTotal loss as soon as the sheath is breachedLocalised dampness of the hardened screed

The pressure gauge must be placed in a clear corner, at eye level and protected by a temporary cabinet so that it remains perfectly legible from the circulation areas of the installation staff. If the needle drops during pouring, the screed layer must stop work on the affected area. Locating the damage in the fresh mortar is immediate thanks to the bubbling or spraying of pressurised water, allowing direct manual exposure and repair with a certified sleeve before hardening.

Infrared thermography makes it possible to map the pipe spacing precisely and to spot a diffuse hot patch that spreads abnormally around the leak point. Demolition is then limited to a targeted core drilling of the screed to insert two axial or radial crimp fittings under heat-shrink sleeving, guaranteeing a lasting repair without compromising the overall expansion of the heated panel.

Active monitoring under pressure and joint handover protocol

Installing underfloor heating coils exposes cross-linked polyethylene or multilayer pipes to severe mechanical damage until they are finally embedded. The repeated passage of wheelbarrows, the supports of pouring trestles or the scraping of metal straightedges can crush, cut or puncture a circuit. To prevent any concealed damage, the network must remain under continuous water pressure throughout the pouring of the flowing or traditional screed.

Each floor distributor receives a manifold fitted with isolating valves, an automatic air vent and a dry or glycerine-filled dial pressure gauge with a minimum diameter of 63 millimetres and a suitable accuracy class. This pressure gauge must be placed in plain view, at eye level, directly in the distribution cabinet or on a rigid riser pipe, so that the site supervisor and the workers can read the needle at a glance. A sudden pressure drop instantly warns the teams of damage to a coil before the mortar sets.

Operational checks and hold points before the screed layer starts work
Check stepTarget parameterTechnical actionDocumentary validation
Filling and bleedingComplete air bleedingFlushing circuit by circuit with clear water via the drain valveVisual check on the return pipes with no air emulsion
Test pressurisation6 bar stableMaintaining the pressure for at least 2 hours for elastic stabilisation of the pipeInitial reading on the technical check sheet
Leak-tightness checkZero pressure dropVisual check of the crimp or compression fittings on the manifold outletsCountersigning of the leak-tightness test sheet
Handover of the substrateService pressure maintainedTime-stamped photograph of the pressure gauge in the presence of the site managementSignature of the joint inspection record for handover of the work

Before the screed company pours the mortar, the heating installer formalises the acceptance of their network by a joint written record. This document attests that all the loops are laid out according to the detailed plans, free from sharp bends or deformations, and that the pressure gauge shows the prescribed pressure. Without this record signed jointly with the site management and the screed layer, the installer remains exposed to a presumption of fault in the event of a leak discovered afterwards.

Locating a leak after pouring and diagnostic methods

When an accidental puncture has not been detected or a pressure gauge has dropped to zero after the screed has hardened, locating the breach without destroying the whole floor is a high-precision operation. Conventional hydrostatic pressurisation makes it possible to isolate the faulty circuit by closing the micrometric valves on the distribution manifold one by one. As soon as the punctured loop is identified by the individual test pressure gauge, non-destructive techniques take over.

  1. Forced temperature riseConnect a mobile service circulator to the leaking circuit and inject water heated to between 40 and 50 °C in order to initiate heat transfer in the embedding.
  2. Infrared thermography scanningView the surface with a calibrated thermal camera. The coil appears as regular hot lines, while the rupture creates a characteristic diffuse patch due to hot water soaking into the porosity of the screed.
  3. Tracer gas injection where there is no complete leak-tightnessDrain the residual water with compressed air and inject a mixture of nitrogen and 5 % hydrogen at 3 bar. Use an electrochemical detector at floor level to pick up the hydrogen rising through the microcracks.
  4. Acoustic correlation listeningPlace a piezoelectric geophone on the suspect areas to pick up the hissing noise of the pressurised fluid against the cement or anhydrite matrix.

Once the anomaly has been located to within a few centimetres, it is exposed mechanically with a light chipping hammer, avoiding any transverse impact on the adjacent coils. The embedding is removed all around the pipe over a length of 300 millimetres. The crushed or punctured section is cut perpendicular to the axis with a clean pipe cutter, without burrs or deformation of the cross-section.

After crimping the repair sleeve, a new leak-tightness test under pressure is carried out on the manifold for 60 minutes before any local filling. Coordination with the screed layer then ensures filling with a shrinkage-compensated repair mortar, guaranteeing the absence of air voids around the sleeve and thermal conductivity consistent with the rest of the room.

Handling damage: intervention protocol and liability

When a pressure gauge drops during the pouring of the flowing or traditional screed, or reveals a loss of leak-tightness during the acceptance check, the origin of the damage must be dealt with using technical rigour and contractual clarity on the Swiss construction site. A puncture caused by the repeated passage of a loaded wheelbarrow, a blow from a tool heel or the careless driving in of a metal level pin tears the wall of the cross-linked polyethylene or multilayer pipe. The incident creates a concealed water leak in the mass of the embedding. If the pressure drop occurs while the screed layer is working, pouring operations must be stopped on the affected bay so that the fresh mortar around the damaged pipe can be cleared before the material starts to set.

  1. Location and bleedingIsolate the faulty circuit at the distribution manifold, drain the residual water or maintain a pneumatic injection of compressed air to slow the spread of moisture in the thermal insulation panels.
  2. Exposure and cuttingCut the screed with a light pneumatic chipping hammer around the marked area, without touching the neighbouring loops. Cut the damaged section with a well-sharpened pipe cutter, then calibrate and deburr the ends cleanly.
  3. Permanent connectionInsert a coupling fitting certified for installation under screed, with radial crimping or an axial sliding ring in dezincification-resistant brass, then cover the metal part with a heat-shrink sleeve or a rot-proof protective tape.

After fitting the mechanical fitting, the heating installer again applies the test pressure of six bar for two hours before the mason rebuilds the screed with a non-shrink grouting mortar. Where the damage is found on a hardened screed, the costs of thermographic investigation, core drilling and reinstatement fall on the company responsible for the mechanical damage. Art. 97 CO provides that the debtor is liable to make good the damage, unless it proves that no fault is attributable to it. The initial joint protocol protects the installer by attesting the conformity of the network before the surface is handed over.

Frequently asked questions

What water pressure should be maintained in the coils while the screed layer pours the mortar?

During pouring, the pipes must remain under a water pressure of between 3 and 6 bar, monitored by a calibrated pressure gauge fixed to the manifold. This hydraulic load prevents the pipe wall from being crushed under point loads and instantly signals an accidental puncture through a water jet or a needle drop. If there is a risk of frost on the construction site, dry compressed air can replace water at the same test pressure.

How can you prove that a pipe was punctured by a structural work operative and not during the installation of the heating?

Proof is established by the joint leak-tightness record signed by the heating installer and the screed applicator before embedding begins. This document records the starting pressure, the exact time and the visual condition of the manifolds. Supplemented by a dated photograph of the pressure gauge at the opening of the screed site, it attests that the network was leak-tight when the work was handed over, engaging the liability of the trades working on the surface.

Why does the manifold pressure gauge sometimes lose 0.3 bar the next day without any water leak?

A slight drop in pressure on the dial does not necessarily indicate a pipe rupture. The phenomenon mainly results from the natural viscoelastic expansion of synthetic materials such as cross-linked polyethylene under stress, as well as from the cooling of the filling water in contact with the cold slab. If the pressure stabilises after a slight manual readjustment without dropping to zero, the network is deemed leak-tight and presents no risk of leakage under the screed.

How can you precisely locate a leak on a floor circuit once the screed is dry?

Locating a leak under hardened screed is done without demolishing the whole floor by combining several non-destructive diagnostic methods. The heating installer injects lukewarm water into the isolated loop to spot the abnormal thermal halo with the infrared camera. If the floor stays cold, a mixture of nitrogen and hydrogen serves as a tracer gas: the electronic sniffer detects the gas rising through the porosity of the mortar at the exact spot of the breach.

Texts and standards cited

  • COnon-performance of the obligation: the debtor is liable to make good the damage, unless it proves that no fault is attributable to it