Key takeaways
- Any installation of sheeting requires the anchorages to be sized beforehand by a qualified scaffolder.
- Micro-perforated nets limit wind load while retaining paint and residual dust.
- Spraying stops as soon as the wind carries the spray mist towards unprotected neighbouring areas.
- The scaffolding must be evacuated as soon as gusts appear that compromise the stability of workers.
Fixing sheeting without creating a sail effect or overloading the anchorages
Façade scaffolding is fitted with sheeting or nets to contain stripping dust, prevent tools from falling and shield painters from draughts. However, clothing a tubular structure radically changes the horizontal forces transmitted to the structural work. In accordance with the Ordinance on Construction Work, the overall stability of the structure must remain assured against foreseeable weather loads. The painter never alters the anchoring pattern: this task falls exclusively to the qualified scaffolder. Before hanging any panel, the site foreman checks with the erecting company that the plugs and eye screws have been sized for the area and porosity of the chosen sheeting.
- Knitted-mesh windbreak nets: with a permeability above fifty per cent, they reduce lateral thrust while stopping direct roller spatter.
- Micro-perforated sheeting for façade renovation: permeability of around twenty to thirty per cent, effectively channelling the spray mist while letting average dynamic pressures filter through.
- Heat-shrink or waterproof sheeting: reserved for asbestos removal or construction sites under heavy containment, requiring the anchor points in the load-bearing masonry to be systematically doubled.
- Soft self-severing plastic ties: fasteners calibrated to break under violent gusts, releasing the sheet to avoid destructive overloading of the metal frame.
Sheeting is always installed from top to bottom, tensioning the strips without creases to prevent the continuous flapping that fatigues the metal fixings. Joints between panels are made with an overlap of at least twenty centimetres, tied along the vertical standards. If MeteoSwiss issues a storm or violent thunderstorm warning, the painter intervenes preventively by lifting the lower skirts or opening the relief slits provided for the purpose to let air circulate.
Wind thresholds on the platform and control of overspray on neighbouring property
On working platforms, the painter's ease of movement and the safety of third parties require strict management of air movement. Under the Ordinance on Construction Work, the employer adapts the organisation of the construction site to prevent falls from height and stops work as soon as natural conditions compromise the stability of persons. On a façade, wind is not only a source of discomfort: it turns paint spray into volatile aerosols liable to drift over tens of metres. Mineral silicate paints are particularly aggressive: their alkaline salts chemically attack the glass of neighbouring windows and car paintwork through irreversible etching if there is no protective screen.
| Wind speed | Product behaviour and risks | Operational decision by the team leader |
|---|---|---|
| 0 to 20 km/h | Practically no product drift, normal stability of the worker | Normal application by roller or airless spray gun under standard net. |
| 20 to 35 km/h | Spray mist deflected outside the scaffolding area | Complete stop of spraying; continuation possible by hand roller subject to low screens. |
| 35 to 50 km/h | Violent flapping of sheeting, risk of loss of balance and roller spatter | Complete stop of exterior painting work; tools withdrawn and drums closed. |
| Above 50 km/h | Dangerous thrust on guardrails, risk of components being torn away | Immediate descent from the scaffolding; sheeting secured and equipment tied down. |
To contain overspray at ground level and protect public space, the painter supplements the vertical nets with a sealed arrangement at the foot of the structure. The first platform level receives perfectly fitted toe boards and a waterproof sheet rising along the inner guardrail, preventing washing drips or paint runs from flowing onto passers-by or municipal public land.
- Prior wind-speed measurementThe team leader measures the wind speed at the most exposed point of the top level before authorising the spray valves to be opened.
- Preventive protection of the neighbourhoodVehicles parked nearby are moved or protected with breathable covers, and the glazing of the lower floors is masked with an electrostatic film.
- Emergency withdrawal in case of sudden gustsWhen foehn or a storm front exceeds the permissible limits, the team shuts off the pump pressure, lowers the buckets to the ground and leaves the platforms without unnecessary delay.
Withdrawal protocol in gusts and emergency release of sheeting
Sheeted façade scaffolding reacts like rigging in atmospheric turbulence. When the wind rises beyond the permissible service limits, the tensile forces transmitted to the anchor points increase exponentially. Under the OTConst, installations must be used so as to preserve at all times the safety of workers and the stability of the structure. As soon as gusts reach the critical thresholds, the team leader orders the immediate evacuation of the platform and the folding back or release of the sheeting to reduce wind load.
Work stoppage is organised according to a strict hierarchy. As soon as the wind measured with the portable anemometer exceeds 30 km/h, airless spray application of paint is stopped immediately to prevent product drift. Between 30 and 45 km/h, brushing or manual roller touch-up work remains technically possible but requires increased vigilance. From 45 km/h, wind load on waterproof or micro-perforated scaffolding generates oscillations and horizontal thrusts that threaten the anchorage in the masonry: the team descends to the ground.
- Wind-speed measurement and checking of alertsMeasure the gusts at the highest platform level with a cup anemometer and monitor the MeteoSwiss bulletins, in particular warnings of foehn, sustained bise or imminent thunderstorms.
- Securing and lashing of equipmentLower or firmly lash the resin cans, mixing tubs, access ladders and tool boxes on the working platforms to prevent any object from falling.
- Partial unhooking or rolling up of the sheetingOpen the perimeter connections or cut the fusible textile ties, starting with the upper levels, then roll up and strap the net strips against the vertical standards.
- Evacuation and closing off of accessDescend through the internal hatches, close the ladder gates and block access to the first level to prevent third parties from climbing onto the structure.
Containment of spray and protection of the immediate surroundings
The contractor's civil liability is directly engaged when third parties suffer damage from siloxane paint mist, mineral dispersion splashes or sanding dust. Particles sprayed with an airless gun partly dry in the air and can be carried by a moderate thermal breeze over several tens of metres, contaminating the bodywork of parked vehicles, the glazing of adjoining buildings or the fabric awnings of neighbours.
| Wind speed | Authorised operations | Protection required | Risk to neighbours |
|---|---|---|---|
| 0 to 15 km/h | Application by airless spray gun, roller, brush | Standard windbreak net or ventilated waterproof sheeting | Low; fallout contained within the footprint of the platform |
| 15 to 30 km/h | Manual application by roller and brush | Spray gun must stop; sheeting fastenings reinforced | Medium; droplets thrown by external turbulence |
| 30 to 45 km/h | Dry preparation, brushing, sanding with extraction | Partial opening of the sheeting to limit the sail effect | High; solid residues and dust blown away |
| More than 45 km/h | Complete stop and immediate evacuation of the platform | Sheeting rolled up or unhooked; platform cleared | Critical; danger of mechanical tearing away of the structure |
Before starting application on a façade exposed to the public road or a shared car park, the site manager sets up a neutralisation perimeter. Parking spaces within the foreseeable spray cone are signposted in advance or marked off with construction site barriers. For vehicles that cannot be moved, fitting complete non-woven polyethylene covers is essential. Commercial ground floors, shop windows and external joinery of the structure being treated are masked airtight with cloth adhesive tape and high-density polyethylene film at least 50 micrometres thick.
To control internal overpressure without tearing the sheeting, the use of micro-perforated nets with an air permeability of 30 to 50 per cent offers the best compromise between retaining paint spray and reducing aerodynamic drag. At the foot of the scaffolding, a weighted net skirt or one fixed to the safety toe board prevents dust escaping towards pedestrian routes, in accordance with the general prevention rules laid down by the OTConst.
Emergency management: sheeting torn away, sudden gusts and overspray damage
When the wind rises suddenly and exceeds forecasts, the wind load on the net or sheeting turns the working scaffolding into a collector of destructive forces. The OTConst requires work to be stopped and elevated workstations to be left as soon as weather conditions no longer guarantee the safety of workers. The team leader immediately orders all the painters down to the ground, without attempting to fold back a sheet flapping violently in the gusts. Access to the platforms is immediately barred at the base hatches with a chain and a prohibition sign.
- Evacuation and alertBring the teams down, close the access points at ground level and notify the appointed scaffolder and the site management without delay so that the holding of the anchorages can be checked.
- Safety perimeterMark off the exclusion zone at the foot of the building with construction site barriers, to prohibit pedestrians from passing and vehicles from parking beneath the sheeted areas.
- Neutralising the sail effectOnly the scaffolder is qualified to cut or release the fixings on the underside in order to flatten the sheet or reduce the tearing-away effect on the anchorages.
In the event of accidental escape of spray mist or runs towards public land or neighbouring plots, application is stopped on the spot. If car bodywork or glazing receives micro-droplets, the priority is to leave the situation as it is without rubbing the dry surface, which would cause irreversible micro-scratches on recent clear coats. The painter notes the registration numbers of the affected vehicles, photographs the deposits in raking light and informs the site management.
Frequently asked questions
May the painter add couplers or alter the scaffolding anchorages?
No. The painter is a user of the structure and does not hold scaffolder qualifications. Altering an anchorage, moving an anchor bar or strapping sheeting directly to a standard without a load-redistribution calculation compromises the structure. If the net is flapping or threatens to give way, the painter records the danger, marks off the ground and contacts the scaffolder responsible for the installation for any intervention.
At what precise wind threshold must the painter leave the scaffolding?
Spray application stops as soon as the wind exceeds twenty kilometres per hour to avoid loss of trajectory. As soon as gusts reach forty-five kilometres per hour, micro-perforated nets transmit dangerous forces and standing becomes precarious. The OTConst prescribes stopping outdoor activities: the team secures the paint pots, locks the access points and descends to the ground.
How should you react immediately if paint spray settles on a neighbouring car?
Stop spraying immediately and photograph the bodywork from several angles with the weather visible. Do not attempt any mechanical wiping with a dry cloth or cellulose thinner, which would damage the original clear coat. Immediately fill in an accident report form with the driver or inform the building caretaker, then send the report to your professional civil liability insurer.
Which sheeting fixing should be preferred to limit damage in an unforecast storm?
On a painter's scaffolding, only micro-perforated nets with a low wind-load coefficient are used, fixed with fusible plastic ties designed to give way under heavy loads. These calibrated breaking links open before the tensile force shears the anchor plugs fixed in the masonry, thus preventing the complete overturning of the tubular structure.
Texts and standards cited
- OTConstOrdinance on the Safety and Health Protection of Workers in Construction Work