Key takeaways
- The SIA 118 standard guarantees defect-free execution, never the absence of natural wear of coatings.
- Progressive chalking and loss of gloss are the result of weathering, not of an application defect.
- South-west exposure is subject to ultraviolet radiation that halves the usual repainting intervals.
- An explicit contractual statement in the quote formalises the client's obligation to carry out regular maintenance.
Distinguishing an execution defect from weathering under the SIA 118 standard
On a façade renovation or exterior woodwork construction site, the boundary between an application defect and natural deterioration gives rise to heated disputes in claims made after acceptance. The works contract subject to the SIA 118 standard governs the painter's liability for latent or apparent defects at formal acceptance. This warranty commits the applicator to the conformity of their system: observance of drying times, the minimum dry-film thickness recommended by the technical data sheet, mechanical preparation of the substrate and use of a suitable bonding coat. It is in no way a promise that the coating will be immune to bad weather.
- Execution defect in exterior painting
- Non-conformity of the work with the recognised rules of the trade at the time of delivery, showing as blistering under the film, flaking in sheets due to poor adhesion, soaking of the substrate or early wash-off caused by a non-compliant application temperature.
Conversely, normal wear results from the combined action of ultraviolet radiation, thermal shocks, driving rain and atmospheric pollutants. The progressive loss of gloss, the steady fading of organic pigments in bright colours or slight surface chalking after several freeze-thaw cycles are the physical ageing inherent to the binder. According to the professional practice recognised by the SIA 118 standard, these alterations cannot be reclassified as defects of the work if the substrate was prepared within the required tolerances.
| Visual appearance | Technical classification | Root cause on the work | Legal attribution |
|---|---|---|---|
| Widespread blistering of the film after one season | Execution defect | Excessive moisture content of the substrate at the time of application | Responsibility of the painting contractor |
| Flaking in scales along the edges of the timber | Execution defect | Insufficient rounding of edges or lack of impregnation | Responsibility of the painting contractor |
| Uniform surface chalking without loss of adhesion | Normal wear | Progressive degradation of the resin by UV | Maintenance burden on the client |
| Regular biological soiling on a north façade | Normal wear | Condensation moisture and shaded exposure | Periodic maintenance of the building |
Defining service life by orientation and locking down the quote
The service life of a paint system can vary by a factor of three on the same building. A timber cladding under a projecting north-facing eave keeps its mechanical integrity for more than a decade. The same profile exposed to the south-west, subject to spray, daily temperature swings and full sun, will need refreshing every four to six years. Announcing an overall service life without linking the maintenance cycle to the environment creates a false expectation in the client.
| Orientation and geometry | Main stresses | Indicative film service life | Recommended maintenance cycle |
|---|---|---|---|
| Sheltered north façade | Residual moisture, plant growth | 8 to 12 years | Low-pressure wash at 5 years, renovation at 10 years |
| Exposed south / south-west façade | Maximum UV radiation, thermal shocks | 4 to 6 years | Annual check of edges, reapplication at 5 years |
| West façade battered by winds | Torrential rain, continuous freeze-thaw cycles | 5 to 7 years | Weathertightness check at 3 years, touch-up coat at 6 years |
To prevent confusion from the tender stage onwards, the quote must include an unambiguous wording formally separating the statutory warranty commitment from the coating renovation cycle. This statement delimits the scope of professional liability towards clients who equate the warranty period with a complete exemption from maintenance.
Restating this technical framework in the descriptive quote makes the owner responsible from the outset. By recording the condition of the substrate before the works and specifying the frequency of renewal of the sacrificial coats, the site manager protects the company's margin and secures the final settlement of accounts.
On-site characterisation: separating an execution defect from climatic erosion
On a rendered façade, exterior woodwork or metalwork, the boundary between poor workmanship and natural wear is a recurring source of dispute during warranty visits. For the building painter, the distinction rests on physical criteria that can be measured during the on-site diagnosis. An execution defect engages the applicator's liability when it results from a failure to follow the rules of the trade: insufficient preparation of the substrate, excessive residual moisture at the time of application, dilution outside the technical data sheet, absence of a bonding primer or chemical incompatibility between the old coating and the new film. These anomalies show up as early mechanical failure of the film, regardless of direct solar radiation.
Conversely, normal wear stems from the continuous attack of weather, temperature swings and ultraviolet radiation. It is in no way a defect of the work within the meaning of the SIA 118 standard or the Code of Obligations (CO). The progressive surface degradation of an organic binder, the loss of gloss of a polyurethane enamel or the surface chalking of an acrylic resin belong to the natural ageing kinetics of exterior finishing materials. Disorders must be classified by localised destructive testing using cross-cut adhesive tape or by sampling flakes to determine the exact failure plane.
| Visible manifestation | Failure plane / Technical finding | Classification | Attribution |
|---|---|---|---|
| Widespread blistering after rain | Failure between the mineral substrate and the primer; presence of trapped moisture or salts | Execution defect | Contractor (poor preparation or substrate too damp at application) |
| Flaking in sheets on the underside | No adhesion on an old chalking, unfixed or glazed substrate | Execution defect | Contractor (no fixing primer or sanding) |
| Uniform chalking without detachment | Surface erosion of the binder under ultraviolet action; free pigments to the touch | Normal wear | Client (normal maintenance cycle according to exposure) |
| Loss of lustre and micro-crazing on the south-west | Surface tension of the film due to repeated thermal shocks | Normal wear | Client (foreseeable climatic stress) |
| Run marks and rust stains | Perforation of the film on sharp unchamfered edges or untreated screws | Execution defect | Contractor (insufficient thickness on edges or no anti-rust coat) |
Contractual clauses and life-cycle management according to exposure
The service life of an exterior paint system cannot be guaranteed on a flat-rate basis without correlating the type of binder with the compass orientation of the building and the design of the eaves. A south-west-facing façade suffers the combined effect of driving rain and maximum sunshine cycles, which halves the time to photochemical degradation of the film compared with an east-facing façade or one sheltered by a generous drip edge. On exterior woodwork such as eaves or fascia boards, clear stains or oils erode quickly under strong radiation, requiring a maintenance refresh well before the statutory warranty periods for the work expire.
- Written notification of technical limits from the quote stageAlways state in the special remarks of the quote the degree of exposure of the façades and specify the expected service life of the chosen system (acrylic dispersion, siloxane resin, potassium silicate or alkyd-urethane enamel).
- Joint inspection record at joint acceptanceDraw up a joint acceptance record on completion of the works in accordance with the SIA 118 standard, recording the initial state of the colours, the conformity of the dry-film thickness and the absence of blisters.
- Handing over the maintenance booklet to the clientGive the client the maintenance recommendations specific to the building: periodic checks of the perimeter sealing joints, gentle cleaning of pollutant deposits and preventive treatment against moss to stop early ageing.
Dispute management: investigating the claim and defending conformity
When the client reports premature deterioration during the period for notice of defects under the SIA 118 standard, the priority is to arrange a joint on-site visit. Never accept a spontaneous repair without having established the exact nature of the deterioration. The painter must analyse the failure using objective tools: a magnifying glass, a standardised cross-cut test to check the adhesion of the coats, and a moisture meter to check the condition of the substrate. This immediate diagnosis makes it possible to determine whether the problem stems from an execution defect or from exceptional weather stresses that are not covered.
- Condition survey and verification of the quote's assumptionsCheck whether the operating and passive protection conditions match the original data of the quote. In particular, check the condition of the drip edges, sheet-metal copings and rainwater drainage.
- Sampling and analysis of the filmsMeasure the dry-film thickness on the disputed areas and on sheltered areas to compare erosion. Flakes are taken to check for the presence of the prescribed priming coat.
- Drawing up the joint recordRecord the technical facts observed without admitting liability prematurely. Note the exposure of the façade, the presence of trees or splash-back from the ground, and biological soiling.
In the event of persistent disagreement with the site management, the company requests arbitration by a technical adviser of the Swiss Federation of Master Plasterers and Painters or by a neutral expert. The report will rely on the manufacturers' technical data sheets and on the reservations originally stated in the quote. If the rules of the trade were followed and the deterioration results from climatic exposure or from a lack of maintenance of the woodwork, the cost of investigations and reinstatement falls exclusively on the client under the Code of Obligations (CO).
Frequently asked questions
Does pronounced fading on a south façade after three years fall under the warranty on the work?
No. Surface fading and loss of gloss under the direct action of ultraviolet rays are natural deterioration and not a defect under the SIA 118 standard. The painter does not guarantee absolute colour stability against the weather, but the mechanical cohesion of the paint film. If the film does not flake and does not chalk excessively, the contractor has no obligation to make good free of charge.
What statement should be inserted in the quote to limit the service life of deep colours outdoors?
The following should be written expressly: "Colours with a light reflectance value below thirty per cent absorb strong radiant heat. This thermal stress accelerates the ageing of the binder and causes an unavoidable change in appearance. The warranty on the work covers the adhesion of the finishing system but excludes changes in shade and lightening under solar exposure, in accordance with the suppliers' technical data sheets." This wording prevents any later dispute.
Can the client demand a ten-year contractual warranty on a façade renovation?
Under Swiss law, the statutory period for asserting defects in a building work is governed by the Code of Obligations (CO) and the SIA 118 standard. A ten-year warranty is unsuitable for exterior paint coatings subject to freeze-thaw cycles and solar radiation. Accepting such a clause exposes the company to bearing the normal wear of the building; the painter must formally refuse this extension or make it conditional on a regular maintenance contract.
What should be done if the site management refuses to sign the acceptance record?
When the client uses the work without formalising acceptance or refuses the record without legitimate reason, the contractor must send a written formal notice. The letter states that the works are complete and requests that a final joint inspection appointment be set. Under the mechanism of the Code of Obligations (CO) and the SIA 118 standard, a work that is not contested within the set deadlines is deemed accepted without reservation.
Texts and standards cited
- SIA 118General conditions for the execution of construction works: acceptance of the work, notice of defects and warranty periods.