Key takeaways
- The substrate must always be at a temperature at least three degrees above the dew point.
- In autumn, application stops at two in the afternoon to guarantee complete drying before evening arrives.
- The substrate temperature must never fall below five degrees nor exceed thirty degrees in the sun.
- A shower on an uncured dispersion leaches out the binders and requires complete redoing of the whole wall section.
The thermal window and the dew point on an autumn day
On Romandy construction sites at the end of the season, the temptation is great to extend application until four in the afternoon to finish a façade. In October, this decision almost always leads to damage. Even if the thermometer still shows twelve degrees in the air at that moment, the temperature drop accelerates as soon as the sun goes below the horizon or behind the terrain. The relative humidity of the air then climbs sharply to reach saturation in the early evening. A water-based paint applied in the late afternoon suffers this condensation directly on its still-fresh film, which blocks the physical process of resin coalescence and causes surfactant runs or an irreversible dulling of the film.
Application work may only be carried out if the air temperature and the substrate temperature comply with the manufacturers' technical data sheets, ensuring that the substrate temperature is kept three degrees above the dew point during application and drying.
norme SIA 257
- 08:00 to 10:00: Morning check and evaporationThe air is often at five degrees and the walls remain saturated with overnight moisture. Application is out of the question. This time is used for mechanical protection, brushing or installing the nets on the scaffolding while waiting for the substrate to warm up naturally.
- 10:00 to 13:30: Usable application windowThe ambient temperature exceeds eight degrees, the substrate reaches ten to fifteen degrees and humidity falls below seventy per cent. This is the only slot for applying dispersion finishing paints or exterior glazes.
- 14:00: Autumn cut-off time for applicationLast admissible pass of the roller. The remaining four hours of daylight allow the aqueous phase to evaporate and the surface to close before the hygrometric shift at dusk.
- 17:00: Temperature drop and dew depositThe surface temperature of the wall drops sharply below that of the ambient air through radiation to the clear sky. If the film is not dry through, the condensation water dissolves the soluble additives of the product.
Imminent rain and low sun: controlling drying times and substrate exposure
Managing the weather outdoors is not just about avoiding frost or night-time. The two other major adversaries of the painter are the unexpected shower and direct solar radiation. Rain occurring less than six hours after applying an acrylic dispersion leaches the uncured resin, leaving indelible whitish marks on the renders and the underlying sheet-metal work. Conversely, applying to a render or metal joinery heated white-hot by the sun poses an equally destructive problem. The metal surface of a dark railing or a render exposed due south can quickly exceed fifty degrees in summer, even at twenty-five degrees in the shade.
| Weather factor | Permitted limit value | Direct technical risk | Required site measure |
|---|---|---|---|
| Minimum substrate temperature | +5 °C (standard resin) / +8 °C (silicate) | No coalescence, early chalking | Postpone the work or sheet the scaffolding with heating |
| Maximum substrate temperature | +30 °C to +35 °C according to manufacturer's data sheet | Flash drying, blistering, visible lap marks | Work progressively, following the shadow of the building |
| Relative humidity of the air | 80 % to 85 % maximum | Blocking of evaporation of the aqueous phase | Stop exterior application as soon as the air is saturated |
| Threat of precipitation | Evaporation time of 4 to 6 hours | Binder wash-out, pigment runs | Consult the rain radars and sheet the façades |
The usable window in October: hour-by-hour sequence and dew risk
In French-speaking Switzerland, the month of October demands strict discipline on façade renovation and exterior woodwork construction sites. The temptation to extend application in the late afternoon to complete a façade or finish a series of eaves invariably ends in defects. A coat of acrylic or alkyd emulsion paint spread at four in the afternoon suffers the temperature collapse as soon as the sun sets. As soon as the relative humidity exceeds the critical threshold, the evening dew settles on a film whose coalescence is only just begun, causing surfactant exudation, partial wash-out of the binder or a permanent loss of gloss.
| Time slot | Average ambient conditions | Substrate condition | Workshop instruction and decision |
|---|---|---|---|
| 07:30 - 09:00 | 4 to 7 °C, relative humidity above 90 % | Damp substrate, residual condensation film present | Painting prohibited. Preparatory work at ground level, dry brushing or mechanical sanding under cover. |
| 09:00 - 11:00 | 8 to 11 °C, relative humidity falling towards 75 % | Surface drying under natural ventilation, substrate temperature rising | Humidity check with a contact thermo-hygrometer. Impregnation or primer coat may be started. |
| 11:00 - 14:30 | 12 to 16 °C, relative humidity stabilised between 55 and 65 % | Dry substrate, ideal surface temperature more than 5 °C above the dew point | Full application window. Apply intermediate and finishing coats by roller or brush. |
| 14:30 - 15:30 | 13 to 14 °C, rapid drop in light and humidity beginning to rise again | Cooling of north- or east-facing walls | Last limit for applying a water-based finishing coat requiring four hours of dust-free drying. |
| From 15:30 | Below 10 °C, relative humidity exceeding 80 % | Rapid temperature drop, substrate approaching the condensation zone | Application stopped completely. Clean the equipment, secure the sheeting and pack up the workstation. |
Compliance with the requirements of SIA 257 prohibits any application on a substrate that is condensing or at risk of condensing in the hours following application. In autumn, the evaporation interval of the aqueous phase lengthens considerably: the polymer particles cannot fuse if water remains trapped in the film because of saturated outdoor humidity. When dew strikes a fresh dispersion at around half past five in the evening, the water dissolves the water-soluble surface materials, leaving irreversible whitish streaks that require complete sanding and redoing after full drying.
Overheating, direct sun and wind: controlling the maximum thermal limits
Managing an outdoor construction site requires organising the rotation of the teams around the building in step with the sun's path. East-facing façades are treated in mid-morning, once the initial warming has driven off the overnight dampness without the surface becoming hot. As soon as the sun moves towards the zenith, the painter moves to the west or north elevation, returning to the south side only in the late afternoon, when the masonry has dissipated its maximum heat radiation.
- Systematic checking of the substrate temperature with an infrared thermometer: the permissible range according to SIA 257 is between +5 °C and +30 °C, exceptionally +35 °C if the manufacturer's technical data sheet expressly guarantees it.
- Mandatory installation of micro-perforated nets on the scaffolding: this protection reduces direct solar radiation by 40 to 60 % and slows the drying wind that prematurely accelerates surface setting.
- Monitoring of local barometric forecasts: a forecast rain front requires a safety margin of at least six hours for acrylic systems, time that is essential to guarantee resistance to wash-out.
- Postponing without hesitation work on metal or powder-coated wood in case of direct radiation, as dense substrates accumulate heat that is incompatible with the tension of an alkyd or polyurethane film.
The site foreman records every reading in the site log: ambient temperature, relative humidity of the air, substrate surface temperature and calculated dew point. These objective data underpin any notices of work interruption submitted to the site management. When the limit thresholds set by SIA 257 or by the suppliers' data sheets are exceeded, suspending activity protects the company against unpaid rework imposed at acceptance of the work.
Weather damage during application: resumption protocol and treatment of defects
When the weather turns faster than forecast, defects in the fresh film are immediate. In autumn, a coat of acrylic dispersion or mineral paint applied in the late afternoon is hit by the dew point before the binder has fully coalesced: the surface water dissolves the surfactants and causes whitish runs, localised dulling or complete soaking. In midsummer, direct sun on a render overheated beyond the admissible limits blocks penetration of the primer and causes blistering through instant evaporation of the solvents or the mixing water. In the face of these construction site incidents, any precipitation aggravates the damage.
- Stabilisation and complete dryingStop work and let the substrate dry in depth for 48 hours without mechanical intervention, until the trapped moisture has been completely removed.
- Washing and removal of surfactantsRinse abundantly with clean water under low pressure with gentle brushing to remove salts, water-soluble additives and surface chalking without eroding the substrate.
- Checking residual adhesionCheck the mechanical strength of the cleaned substrate by a cross-cut test or wet rub test according to the requirements of SIA 257.
- Scraping back and redoing the coatSand the edges of detachment, dust off carefully, apply an adhesion promoter if the binder has been depleted, then redo the finishing coat, scrupulously respecting the usable time window.
The site foreman records these incidents in the works log, measuring the substrate temperature and the ambient humidity. If the interruption results from unforeseeable bad weather outside the ranges tolerated by the technical data sheets, the contractor sends a notice of interruption to the client in accordance with the contractual rules of SIA 118, thereby discharging his technical responsibility.
Frequently asked questions
Can a façade be painted in October as long as the ambient air shows 12 °C in the afternoon?
The air temperature is misleading. In October, the substrate cools from three in the afternoon under the effect of rising moisture and wind. By four o'clock, the dew point is frequently reached, saturating the render with liquid water. Even with air at 12 °C, a water-based film does not have time to evaporate its liquid phase before condensation, leading to wash-out and loss of adhesion according to SIA 257.
How should you react when a thunderstorm shower rinses a façade painted two hours earlier?
Do not try to scrape or touch up the still-fresh product. Let the façade drain and dry completely over several dry days. Once the substrate is dry, assess the extent of the wash-out: unfixed pigments must be brushed off and washed with low-pressure water. After the substrate has dried through, apply a new complete coat to restore the opacity and the minimum thickness prescribed by the manufacturer's data sheet.
Why is it prohibited to apply exterior paint on a substrate exposed to full sun?
Under direct radiation, a mineral or metal surface can reach 50 °C while the air shows only 25 °C. This excessive heat causes abrupt evaporation of the water or solvents in the product. The binder no longer achieves its normal coalescence, the film dries on the surface before having wetted the substrate, which causes visible lap marks, superficial crazing and rapid detachment through blistering.
What are the limit temperature values for applying an exterior paint system in French-speaking Switzerland?
SIA 257 and Swiss technical data sheets generally require a minimum application temperature of +5 °C for dispersions and silicone resins, and up to +8 °C for pure silicate paints. The maximum substrate temperature must not exceed +30 °C to +35 °C. In addition, the substrate temperature must always remain 3 °C above the calculated dew point.
Texts and standards cited
- norme SIA 257Paint, varnish and wall coverings: execution conditions, thermo-hygrometric requirements and acceptance criteria for substrates
- norme SIA 118General conditions for the execution of construction work: managing construction site interruptions due to bad weather and duties to inform