Key takeaways
- A dispersion paint exposed to frost suffers irreversible degradation of its synthetic binders.
- Volatile solvents require permanent ventilation to prevent any accumulation of flammable vapours.
- The Chemicals Ordinance requires separate storage with suitable retention trays.
- The quantities permitted on the upper floors are strictly limited to the crew's daily needs.
Protecting water-based binders from frost without creating a thermal risk
Water-based paints, whether interior acrylic dispersions, water-soluble primers or silicate resins, contain a significant proportion of liquid water. When the ambient temperature falls below zero degrees, the water crystallises inside the bucket. This mechanical expansion breaks the polymer emulsion and permanently separates the binding resins from the mineral fillers and pigments. A dispersion that has frozen cannot be recovered either by mechanical stirring with a mixer or by gradual warming: it forms stringy lumps and loses all adhesion and spreading ability.
To preserve the buckets during winter periods on unheated construction sites on the Swiss Plateau or in Alpine valleys, the contractor must provide a temperature-controlled room or install an insulated heated cabinet. The temperature setting must be maintained permanently between five and fifteen degrees. However, it is strictly forbidden to use this temperature-controlled room to store thinners, solvent-based primers, epoxy resins or white-spirit-based varnishes. The rise in temperature accelerates solvent evaporation, increasing the vapour pressure inside the metal cans and creating an explosive atmosphere in a closed room with no high and low ventilation.
| Product family | Required storage range | Effect of a temperature below 5 °C | Effect of a temperature above 30 °C |
|---|---|---|---|
| Acrylic wall dispersion | Between 5 °C and 25 °C | Irreversible gelling and loss of binding power | Water evaporation and skin formation on the surface |
| Silicate or mineral paint | Between 8 °C and 20 °C | Binder crystallisation and heavy sedimentation | Premature solidification in the container |
| Organic solvent-based enamel | Between 5 °C and 20 °C | Sharp increase in viscosity when drawing off | Overpressure in the cans and release of explosive vapours |
| Synthetic thinner or acetone | Between 5 °C and 18 °C | No risk of freezing but temporary thickening | Risk of spontaneous ignition at the slightest hot spot |
The team leader therefore provides a temperature-controlled storage area dedicated exclusively to water-based products. This area receives the buckets placed on wooden pallets or insulating blocks to avoid direct thermal contact with a cold concrete slab. Opened drums must be tightly resealed after each use to limit the formation of a surface crust caused by the warm air currents generated by site heaters.
Isolating flammable substances and observing safe quantities
The Chemicals Ordinance and the directives of the Swiss Association of Cantonal Fire Insurance Institutions govern the storage of hazardous products. Paints containing solvents, chemical strippers, two-component polyurethane resins and cleaning thinners are flammable liquids. They must be kept separate from the workers' rest room or canteen, and from areas housing heat-producing appliances or temporary electrical panels. Main storage takes place in a ventilated, key-locked external container, or in a fire-resistant safety cabinet installed on the ground floor.
To prevent contamination of soil and watercourses in accordance with environmental protection provisions, every container holding a chemical product must stand on a leak-proof retention tray. The capacity of this tray must be able to hold at least the entire volume of the largest container stored, or one hundred per cent of the total volume if the storage is located in a groundwater protection zone. Metal solvent cans must never be stacked unstably or exposed to direct sunlight behind unshaded glazing.
- Define a ventilated outdoor area for solvents, away from escape routes and fire-service access.
- Keep the safety data sheets in a visible pouch at the entrance of each storage area.
- Place a foam or multipurpose powder extinguisher within five metres of the solvent store.
- Keep a bag of mineral absorbent to deal immediately with any accidental spillage of product.
- Prohibit the use of tools that produce sparks or naked flames in the immediate vicinity of open containers.
At application workstations on the upper floors of the building, the foreman limits the supply to the quantities strictly necessary for the day's work. The original twenty-litre packagings stay in the general store: the painters carry up suitable working containers fitted with sealed lids. At the end of the day, unused can remnants, brushes soaked in thinner and rags soaked in drying oil must be brought back down to the main store. Rags soiled with solvents or oils must be placed in a sealed metal box to eliminate any self-heating phenomenon.
Spatial organisation of storage under the OPChim and management of incompatibilities
The Chemicals Ordinance (OPChim) requires a rigorous spatial organisation of hazardous substances from the moment they are delivered to the construction site. The foreman may not group all packagings in a single service room for convenience. Aqueous dispersions, primers and water-based finishing resins must be kept permanently frost-free, between 5 °C and 25 °C. Even brief freezing irreversibly breaks the binder emulsion: the polymers precipitate into a lumpy mass unfit for application. Conversely, flammable solvent-based products must never be placed next to a heat source, a fan heater or an electric convector heating the room. Separation into two sealed and distinct zones is the only solution consistent with Swiss good practice.
| Product category | Permitted temperature | Required packaging | Risk if not complied with |
|---|---|---|---|
| Water-based dispersions and binders | +5 °C to +25 °C | Dry temperature-controlled room, cans kept off the bare ground | Permanent coagulation through frost, material lost |
| Solvents, thinners and cellulose varnishes | 0 °C to +25 °C | Ventilated fire-resistant cabinet or external container | Explosive vapours on contact with a hot body |
| Epoxy and polyurethane systems (2K) | +10 °C to +25 °C | Leak-proof tray, resins kept apart from hardeners | Blocked polymerisation or exothermic thermal reaction |
| Chemical strippers and pump cleaners | +5 °C to +20 °C | Leak-proof high-density polyethylene tray | Corrosion of metal containers, harmful fumes |
Access to the main storage room complies with the requirements of the CFST directive on chemical products. Any container or store housing products labelled with hazard pictograms must be locked with a key outside of issuing times. This space may not be shared with the changing room, the canteen or the power tools. The manufacturer's original labelling must remain legible; any decanting into neutral cans without official labelling compliant with the OPChim is strictly forbidden to eliminate the risks of poisoning or confusion.
Admissible quantities at workstations and retention devices
On floors undergoing finishing work, storing complete pallets to limit handling creates an unlawful fire load and increases the concentration of VOCs in the ambient air. The fire protection regulations of the Swiss Association of Cantonal Fire Insurance Institutions (AEAI) strictly limit the products present at the workstation to the volume needed for the current day. Surplus reserves stay in the ventilated external container or the dedicated technical room, equipped with natural high and low ventilation.
- Calibrating the morning's needsThe team leader calculates the volume of dispersion or solvent corresponding to the planned daily progress and draws off only these quantities from the main store into labelled sealed buckets.
- Setting up the mobile retentionAll mixing, dilution and brush or roller rinsing stations are set up on a leak-proof polyethylene retention tray, supplemented by a bag of mineral absorbent to deal with spills.
- Systematic return at the end of the dayAt the end of the shift, each opened bucket or pot is tightly resealed to block the release of VOCs. The containers return to secure storage and the roller sleeves are wrapped in film.
The installation of retention trays under storage drums complies with the Water Protection Ordinance. The store must have no drain connected to the pipework. Metal or synthetic trays must retain the capacity of the largest container stored or at least ten per cent of the total liquid volume. This precaution ensures that no accidental puncture during handling spreads binders or solvents onto the concrete slab or into the ground.
Managing storage failures: frost, overheating and spillages
On a construction site in French-speaking Switzerland, a breakdown in the paint storage conditions requires an immediate response to protect the substrates and the safety of the staff. When an acrylic dispersion or a water-based resin is exposed to a sub-zero temperature over a winter weekend, the polymer chain breaks. Never attempt to warm the drum with a torch or on a hot-air heater. The product must be warmed slowly under cover, then stirred mechanically. If the paste shows lumps, a stringy texture or a phase separation that no longer homogenises, the resin is permanently destroyed. Applying a gelled product leads to poor adhesion, early chalking and guaranteed blistering of the dry film. This batch must be logged and disposed of through the construction waste stream in accordance with the Waste Ordinance.
Conversely, a temperature rise in an area housing polyurethanes, epoxies or cleaning solvents causes an accumulation of flammable vapours under the ceiling. If a strong solvent smell escapes from a closed container or a safety cabinet, the instruction prohibits operating any conventional electric switch, starting any compressor and handling any power tool, in order to prevent an igniting spark. The crews open the exits wide to create natural cross-ventilation before any approach. The personnel locate the leaking or deformed can while wearing a mask with a combined cartridge for organic vapours.
Every material failure is the subject of a joint inspection record with site management. Noting the minimum temperature recorded, the batch number and the quantities damaged relieves the painter of responsibility for schedule delays. The emergency supply of new temperature-controlled drums safeguards the quality of the system without compromising the final tolerances of the coating.
Frequently asked questions
How can you check on site whether an emulsion paint has irretrievably frozen?
After slow thawing at 18 degrees for twenty-four hours, stir the bucket with a helical mixer. If the consistency resembles cottage cheese, if insoluble lumps remain or if the liquid floats without binding to the pigment, the paint is dead. Apply a sample to a plaster board: a film that cracks, powders or peels on drying confirms the destruction of the resin, requiring the entire bucket to be discarded.
Can cleaning solvents and water-based paints be stored in the same room?
No. The AEAI fire protection regulations and the Chemicals Ordinance require combustible materials to be separated from non-flammable products. Volatile solvents require a ventilated safety cabinet or a separate room not heated by a direct flame. Placing a cellulose thinner near a fan heater keeping acrylic paints frost-free is a serious source of ignition. Water-based products, for their part, require a positive, temperature-controlled environment.
What maximum quantity of solvents may be kept at the workstation each day?
The site rule strictly limits the volumes present at the workstation to the foreseeable consumption for the daily shift. Beyond five litres of flammable liquids or reactive mixtures, the cans must stay in their fire-resistant safety cabinet or in the ventilated external container. Any unused container must be resealed as soon as the product has been drawn off, in order to reduce VOC emissions and the risk of ignition.
What should be done with rags soaked in hardening oil or solvent at the end of the day?
Rags soaked in drying oils for joinery or in solvents present a proven risk of spontaneous self-heating that can lead to the store catching fire. It is forbidden to throw them in a ball into general-waste skips. Store them temporarily in a self-closing airtight metal box or immerse them in a closed bucket of water before their disposal in compliance with the rules for special construction waste under the Waste Ordinance.
Texts and standards cited
- OPChimChemicals Ordinance: requirements for storage, handling and prevention of the dangers linked to hazardous substances
- OLEDOrdinance on the Limitation and Disposal of Waste: sorting, separate disposal of special waste and management of construction site residues