🧱 CFC 221Ventilated cladding: framing, air gap and fixingsChapter 6 of 10 in the section

Metal cassettes: flatness tolerance, oil canning and layout planning

After this chapter, you will be able to check the flatness of the substrate before installation, prevent oil canning on metal cassettes in ventilated facades, size the thicknesses and stiffeners according to the format, and draw up a rigorous layout of open joints to absorb tolerances without betraying the visual alignment under raking light.

Key takeaways

  • Raking light reveals the slightest deformation of the metal and any misalignment of the primary substrate.
  • Prior checking of the structural work guarantees the precise alignment of the aluminium subframe.
  • Sheet thickness and bonded stiffeners prevent bulging under temperature differences.
  • Layout planning of open joints absorbs dimensional variations while guiding the visible edges.

Taming the substrate and neutralising oil canning in ventilated facades

Metal cassette cladding forgives no geometric deviation. In a ventilated facade, thin metal facings act as true mirrors of the imperfections beneath. As soon as the sun moves round and casts raking light onto the envelope, the slightest out-of-plumb in the subframe or the smallest internal stress in the sheet shows up as an unsightly wave effect, commonly called oil canning. This optical deformation does not directly endanger the mechanical stability of the structure, but it is one of the first grounds for aesthetic complaints from clients and architects.

Oil canning
Visible waviness on the surface of a flat metal sheet, caused by internal rolling stresses, temperature variations or mechanical restraint during fixing to the secondary framework.

To avoid this phenomenon, acceptance of the raw substrate is the unavoidable starting point for the facade installer. The permissible deviations of the reinforced concrete or masonry structural work must be compensated exclusively by the brackets and profiles of the adjustable secondary framework. A poorly aligned subframe imposes direct twisting on the cassettes during riveting or hanging. Fine adjustment of the vertical uprights using gauge rods and laser levels makes it possible to absorb the irregularities of the supporting wall even before the thermal insulation and the rainscreen membrane are installed.

The thickness of the metal is the second fundamental lever against buckling. A thin aluminium sheet reacts strongly to thermal gradients between the sunlit exterior and the ventilated air cavity. Beyond a certain cassette diagonal, simply folding the edges is no longer enough to contain surface expansion. Incorporating omega-profile stiffeners on the back, joined by flexible structural bonding, stabilises the panel without restricting its natural thermal movement.

Stability criteria for aluminium cassette facings
Cassette developmentIndicative minimum thicknessRear stiffener requiredBehaviour under raking light
Side less than 600 mm2.0 mmNot required in standard zoneExcellent optical stability
Side between 600 and 1000 mm2.0 to 3.0 mmRecommended depending on exposureSensitive to restrained fixings
Side greater than 1000 mm3.0 mm or composite sheetMandatory at the centre of the panelHigh risk of waviness

Rigorous layout planning and management of open hanging joints

The layout planning of metal cassettes is not limited to a purely aesthetic distribution dictated by window openings. It directly governs the envelope's ability to expand freely while maintaining perfect sight lines. In a lightweight non-load-bearing facade, the open joint acts as a geometric buffer: it absorbs the manufacturing tolerances of the cassettes machined in the workshop, compensates the installation clearance on the construction site and masks the differential micro-movements induced by frost cycles and strong sunshine.

  1. Setting out the reference axesSet out the vertical and horizontal axes on the subframe uprights with a laser line, re-adjusting the cumulative dimensions every three modules.
  2. Checking the sliding fixingsCheck that each cassette has a fixed reference point and slotted sliding points to avoid any mechanical pre-stressing.
  3. Adjusting the open jointUse calibrated synthetic spacer shims to guarantee a constant joint width over the full height of the facade.
  4. Checking in workshop and outdoor lightVisually check the alignment of the edges before the final tightening of the concealed fixing parts or hanging brackets.

Managing the folded edges at the open joints demands millimetre precision. Any squareness defect or crushed fold changes how light reflects on the edge of the cassette, simulating a false misalignment even when the overall plane is correct. Black trim profiles or dark recessed joint backings accentuate the contrast and conceal the substructure. This allows the eye to pick up only the regular grid intended by the project, while preserving the opening of the air cavity needed for rear ventilation.

In contractual and regulatory terms, the facade contractor ensures that the work is carried out according to the recognised rules of the trade. Art. 364 CO recalls the general obligations of diligence and loyalty of the contractor in carrying out the work entrusted to them. As soon as the tolerances of the concrete substrate exceed the compensation capacity of the lightweight framework, or the prescribed thickness proves insufficient to guarantee the flatness required by the surface appearance, art. 365 CO requires the client to be informed immediately of any circumstance jeopardising the proper execution of the work.

Checking the raw substrate and aligning the substructure

The final flatness of a metal cassette cladding depends first and foremost on the geometry of the supporting masonry or concrete. Polished or powder-coated metal acts as an optical mirror: the slightest level offset in the hanging framework generates twisting in the panels, which becomes glaring under raking sun. The facade installer must check the deviations of the structural work before any setting out of the thermal brackets.

Permissible flatness tolerances and compensation methods in ventilated facades
Item checkedChecking spanPermissible deviationCorrective device
Raw concrete substrate (CFC 211)2.00 m straightedge± 5 mmAdjustment ranges of the thermal brackets
Clay masonry substrate2.00 m straightedge± 8 mmShims under insulated brackets
Secondary framework profiles2.00 m straightedge± 2 mmSliders and adjustable self-drilling screws
Edges of installed cassettes10 m sighting line± 3 mmAdjustment of the brackets and suspension points

To avoid transmitting mechanical stresses to the facing sheets, the aluminium uprights must be aligned with a rotating laser with absolute rigour. The use of thermally broken brackets with slotted holes makes it possible to compensate the out-of-plumb of the concrete without forcing the load-bearing profiles. An upright restrained under tension passes its warping on to each clipped or riveted cassette.

Sheet thickness, stiffeners and control of oil canning

Oil canning, or optical buckling, is a visible waviness of the sheet under the combined action of differential thermal expansion, wind pressures and internal stresses from folding. To neutralise this phenomenon on large modules, the facade installer ensures a suitable material thickness and the integration of stiffeners bonded to the underside.

  1. Selecting the nominal thicknessMatch the raw metal thickness to the development of the cassette: minimum 2.0 mm in aluminium for small formats, 3.0 mm for cassettes with a side over 1.20 m or subject to strong wind suction.
  2. Shaping the folds and returnsMake continuous perimeter turned-down edges of at least 25 mm to enclose the panel and create geometric rigidity on all four sides.
  3. Fitting the stiffening profilesFix omega or U profiles to the back face using a viscoelastic structural adhesive tape or an elastomer adhesive, to absorb thermal movements without marking the visible face.
  4. Freeing the hanging pointsIt is essential to distinguish the central or upper fixed point from the sliding points on the suspension plates, so that the metal can stretch freely.

The layout planning of open joints is the last visual defence against distortion. A regular open joint of 15 to 20 mm absorbs the dimensional elongation of aluminium (of the order of 1.2 mm per metre for a temperature difference of 50 °C) while breaking up the continuous reflections that accentuate the waviness of the walls. Concealed fixings by suspended interlocking avoid pinching of the edges mechanically, the first cause of bulges appearing in strong summer heat.

Finally, handling on the construction site requires suction-cup lifting beams to preserve the flatness of large plates. An edge impact or a twist during unloading creates an irreversible onset of waviness that the substructure will never be able to straighten out during assembly.

Managing appearance non-conformities and acceptance under critical light

On metal cassette cladding, the appearance of buckling visible under raking sun is the most frequent dispute at completion inspections. When the overall or local flatness of a panel is contested, visual assessment cannot be improvised: it must be carried out at a minimum observation distance consistent with the customs of the trade, excluding extreme lighting angles that are not representative of normal use of the building.

Diagnosis of metal cassette deformations and remedial options
Observed symptomTechnical originCorrective action
Bulging at the centre of the trayDetached stiffener or undersized sheetRedo the structural bonding or replace with a reinforced panel
Broken open joint lineMisalignment of the brackets on the frameworkFine adjustment of the brackets and millimetre shimming of the profiles
Buckling at the edgesThermal restraint at the fixed pointsOvalising the holes to restore free sliding

If the raw substrate showed an out-of-tolerance deviation not corrected by the adjustable brackets, responsibility for the overall deformation lies with the installation chain. The contractor applies the Code of Obligations to document precisely the origin of the defect, whether it is a machining error in the hangers or a deflection carried over from the concrete slab. Under art. 367 CO, the client reports defects as soon as they are noticed during the regular inspection of the delivered surfaces.

Repairing a damaged cassette in the middle of a ventilated facade requires an intervention method that does not alter the alignment of the adjacent elements. Concealed fixings by interlocking sometimes require partial dismantling of an entire bay from the parapet, underlining the importance of an initial layout plan incorporating occasional dismantling keys.

Frequently asked questions

How is a flatness defect on a metal cassette formally measured?

The measurement is made with a two-metre straightedge and a millimetre steel rule, placed on the visible face of the cassette without applying any mechanical stress. The maximum deflection at the centre of the sheet is measured, as well as the misalignment between two neighbouring trays at the open joint. The reading must be recorded jointly by both parties, avoiding periods of strong direct sunshine.

What observation distance applies to judge oil canning on a facade?

The appearance inspection of a ventilated metal cladding is carried out at a normal distance of at least five metres, perpendicular to the wall or at a normal viewing angle. Observations made close to the facing under rising or setting sun cannot serve as the sole contractual reference, since raking light inevitably accentuates the natural variations in stiffness of the metal sheet.

Can a cassette deformed by thermal restraint be straightened directly on the scaffolding?

No, a cassette that has undergone plastic buckling through blocked expansion retains a permanent residual deformation. The panel must be removed to check the condition of the framework, the fixings must be released by opening suitable slotted holes, and a new element with the appropriate thermal clearances must be fitted. Any mechanical force applied locally to the visible face permanently marks the finish coating.

Why do open joints reveal the flatness defects of the substructure more?

Open-joint layout planning creates a network of sharp shadow lines that emphasise the slightest offset in depth. Any misalignment or twist of a vertical framework profile immediately transfers a tilt to the folded edge of the cassette. The visual discontinuity breaks the linearity of the joint, making visible from a distance a misalignment that would remain imperceptible on a continuous flat cladding.

Texts and standards cited

  • SIA 118General conditions for the execution of construction work
  • CO art. 367after delivery, the client checks the condition of the work as soon as it is able to do so and notifies the contractor of any defects; for an immovable structure, the client has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); either party may request an examination by experts (para. 2).