Key takeaways
- An air cavity closed at the top traps moisture and completely cancels the thermal stack effect.
- The rodent screen greatly reduces the gross geometric area: the real open area must be compensated for.
- At the base of the façade, provide a minimum of fifty square centimetres of free opening per linear metre.
- At lintels, split the framing to ensure air exhaust below the sill and air inlet above.
Sizing the inlet areas at the base and the outlet areas at the top of the works
Ventilated cladding relies on a simple physical principle: natural thermal draught. If fresh air cannot enter freely at the bottom, or if it meets a sealed stop at the top, convection stops. Water vapour then migrates into the insulation or condenses on the back face of the cladding, causing damage to the secondary framing and the rain-screen membrane. A ventilated façade whose upper outlet is blocked behaves like an unventilated wall subjected to excessive thermal gradients.
- Residual ventilation area
- Net area available for airflow, deduced from the metal thickness and the arrangement of the perforations of the rodent screen, expressed in square centimetres per linear metre of façade.
At the base of the works, the ground clearance relative to the finished ground or to the slab on gravel must be respected to limit rainwater splash-back. The free air inlet area must reach a minimum of 50 cm² per linear metre of façade for usual building heights up to three storeys. The minimum thickness of the air gap between the cladding and the rain-screen membrane is 20 mm, increased to 30 mm or 40 mm on greater heights or depending on the type of cladding installed.
| Position on the envelope | Minimum gap thickness | Net free air area | Protection detail required |
|---|---|---|---|
| Façade base (plinth) | 20 mm | 50 cm²/lm | Perforated rodent-proof profile in aluminium or stainless steel |
| Outlet under roof coping | 20 mm | 50 cm²/lm | Rain-screen deflector with opening facing downwards |
| Junction under ventilated eaves | 20 mm | 100 cm²/lm | Continuous fine-mesh screen under the soffit |
At the top of the façade, the air outlet is located under a parapet flashing, under a metal coping or at an eaves junction. The most frequent mistake is to press the insulation or the rain-screen membrane against the upper cover sheet, closing the pressure-relief chamber. The airflow must be able to escape to the outside without creating a direct entry point for powder snow or driving rain.
Ensuring continuity of airflow at openings and lintels
Each opening in the envelope represents a physical break in the air cavity. The lintel of a window abruptly cuts the rising air cavity, while the sill of the window frame blocks the air supply for the portion of façade above. Without specific provisions in the laying of battens or framing profiles, large areas of cladding remain completely disconnected from air circulation.
- Interrupt the framing below the window sillStop the vertical uprights approximately 30 mm below the metal flashing. This clearance ensures the escape of rising warm air without creating condensation under the sill.
- Fit a perforated profile under the lintel dripInstall a rodent-proof profile on the underside of the lintel to feed fresh air back into the network of air cavities located above the window frame.
- Divert the airflows at the reveal uprightsSpace the vertical reveal profiles at least 20 mm from the standard rafters so that air can get around the corner of the opening towards the adjacent bays.
Where the framing is installed horizontally to receive vertical cladding, air circulates vertically behind the battens by means of counter-battening. A simple horizontal batten laid flat completely blocks the air cavity. The contractor meets the general duties of his profession under art. 364 CO by carrying out these framing details in accordance with the recognised rules of the trade, thus ensuring the durability of the works against summer overheating and rotting of the substructures.
As regards the organisation of workstations when fixing the framing in the opening reveal, crews take care to prevent tools and metal parts from falling to the levels below, in accordance with OTConst art. 17, which requires suitable measures so that workers are not endangered by falling materials.
Installation requirements for rodent screens and maintaining the free area
Accidental blocking of the base of the cladding is among the most recurrent non-conformities found on ventilated façades. Fitting a perforated ventilation profile or a rodent screen is essential to prevent small animals and insects from entering the air cavity. However, this component introduces an immediate airflow pressure loss that must be compensated for when laying out the framing.
- Free passage coefficient (mesh open area)
- Ratio, expressed as a percentage, between the area of the actual openings (holes, slots) of a screen or perforated profile and the total gross area of the profile. It determines the effective area remaining for airflow.
An aluminium or galvanised steel profile commonly delivered to the construction site has an opening coefficient between 40% and 50%. Consequently, to obtain a real free area that meets the airflow requirements, the gross thickness of the ventilation gap often has to be increased. If the required net area is 200 cm² per linear metre, a screen offering 50% perforation open area requires a geometric profile area of at least 400 cm² per metre, otherwise the thermal draught will be choked.
| Type of intrusion protection | Average opening ratio | Minimum air cavity thickness | Risk of clogging by fouling |
|---|---|---|---|
| Oblong perforated sheet (5x20 mm) | 45% to 55% | 40 mm | Low (dust falls away) |
| Round perforated sheet (diameter 4 to 5 mm) | 35% to 45% | 50 mm | Medium (dry leaves, cobwebs) |
| Fine expanded-metal mesh | 60% to 70% | 30 mm | High (retains pollen and dust) |
The screen must be installed rigidly, mechanically fixed against the bottom rail or the starter profile, without leaving a peripheral gap greater than 5 mm against the outer cladding or the insulation. The use of light staples on timber framing is to be avoided in favour of stainless steel screws with wide washers. The screen must never serve as direct support for the bottom of the panel or cladding batten, to avoid any crushing that would reduce the opening to zero.
Singular points and internal obstacles: airflow continuity at lintels and cross-members
The outlet area at the top of the works, often located under the parapet flashing or the roof soffit drip, follows the same rule of continuous flow. A flat roof connected without clearance to the façade cladding blocks the stack effect. The rising flow is also stopped dead as soon as the framing meets a glazed opening. At a lintel, fitting a continuous watertight metal flashing creates a horizontal airtight barrier if no provision is made to divert the circulation.
- Airflow splitting under the window sillInterrupt the ventilation channel under the window sill by creating an exhaust slot to the outside, protected by the drip of the flashing, preventing overpressure under the upstand.
- Re-injection of fresh air at the lintelFit a horizontal perforated profile on the underside of the lintel, in front of the blind box or the window pre-frame, providing an independent air inlet to feed the upper section of the façade.
- Installation of interrupted framing cross-membersWhere horizontal secondary framing is used for vertical cladding, use only discontinuous joists or a double crossed batten layer (continuous vertical counter-battening at the back, discontinuous horizontal battening at the front) so as not to compartmentalise the air cavity into sealed boxes.
- Visual check of insulation matsCheck the flatness and mechanical retention of the semi-rigid insulation panels using suitable star anchors to prevent bulging or detachment of the mineral wool in the ventilated cavity.
In contractual and legal terms, the contractor is liable for the conformity of this work. Under CO, if a component supplied by the site management or a plan detail provided proves defective and compromises the functioning of the façade, the contractor informs the client. The general criminal liability of builders recalled in CP also penalises failure to comply with the recognised rules of the trade that endangers persons, in particular in the event of collapse of cladding degraded by trapped moisture.
Handling ventilation obstructions and non-conformities
On a ventilated cladding construction site, the blocking of an air cavity frequently results from an unresolved interface conflict: a connecting flashing pinched against the rain-screen membrane, a decompressed insulation mat bulging between the rafters, or a rodent screen crushed by the installation of the first cladding profile. An air cavity closed at the top or blocked under a lintel turns the ventilated façade into a closed enclosure, trapping condensation moisture and cancelling the principle of air pressure equalisation.
- Finding and stopping the fixing of the claddingAs soon as a crushed air cavity or a blocked screen is identified, immediately stop screwing or riveting the panels in the affected bay to avoid destructive removal later.
- Geometric check of the free areasCheck the effective passage at the obstacles with a rule or gauge. Measure the net passage area by subtracting the space occupied by the perforated screen, to make sure the required airflow ratios are met.
- Mechanical rework and provision of bypassesStraighten or replace deformed rodent-proof profiles. At the lintel, insert shims under the flashing to restore a low exhaust area and open the air inlets needed above the window frame.
- Formalisation and duty to notifyIf the problem comes from an insulation thickness incompatible with the set-back of the framing prescribed by the site management, apply the written duty to notify under the SIA 118 standard before any further installation.
Work on scaffolding requires strict compliance with preventive measures against falls. In accordance with OTConst, façade scaffolding must be installed as soon as the fall height exceeds 3 m. Coordination between the façade installer and the joiner ensures precise alignment of the connecting sheets to avoid any accidental choking of the airflow.
Frequently asked questions
How can ventilation be maintained under the sill and at the lintel of an opening?
Airflow continuity at an opening requires splitting the flow. Under the sill board, the air exits through a slot protected by a rodent screen. At the lintel, fresh air enters through an opening provided between the cladding and the upper metal cover. This arrangement avoids creating a zone of stagnant air under the bottom rail and above the fixed frame.
Which rodent screen should be chosen so as not to block the air draught?
A standard screen reduces the geometric area by 30 to 50% because of its perforation ratio. To keep the required minimum area, select a profile with oblong perforations offering sufficient free passage or increase the projection of the cladding relative to the face of the insulation. Using a mesh that is too tight promotes rapid fouling by dust.
What should be done if the thermal insulation protrudes and narrows the air cavity?
If the semi-rigid insulation bulges and reduces the air cavity below the required dimension, forcing the cladding by crushing is out of the question. Add fixing discs to press the wool back against the supporting wall or fit compression battens. If the bulging persists, the contractor formally reports the sizing defect in the structural work or the framing.
Why must an air outlet at the top under the coping remain open?
An air cavity closed at the top eliminates the thermal stack effect. Without dynamic depression, the water vapour that has passed through the envelope cannot escape and condenses on the cold inner face of the cladding, wetting the framing and degrading the rain-screen panel. A protected slot must be provided on the underside of the top-termination or parapet sheet over the entire perimeter.
Texts and standards cited
- norme SIA 118General conditions for carrying out construction work
- OTConstscaffolding for façades in building construction work: façade scaffolding must be installed as soon as the fall height exceeds 3 m; the top rail must project at least 80 cm beyond the edge of the highest zone presenting a risk of falls (100 cm if the guardrail is less than 60 cm from the edge) (para. 2)
