Key takeaways
- From a drop of two metres towards the outside, the open opening requires collective protection.
- The temporary guardrail must be installed before the old frame is unsealed or removed.
- The temporary device is fixed by pressure or by direct anchoring in the structural work.
- Interior marking-off isolates the danger zone to prevent unsecured workers from approaching.
Determining the securing obligation according to the fall height and the opening profile
When replacing glazed elements in a façade, removing the sashes and then cutting out the frame creates a raw opening to the outside. If the façade has no complete external working scaffolding with operational guardrails at this level, this opening directly exposes personnel to a risk of falling into the void. The risk must be determined before demolition or dismantling work begins, by measuring the difference in level between the walkable interior floor and the exterior ground or any underlying landing surface.
Art. 23 OTConst states that the perimeter guardrail is installed in unprotected places where the fall height is greater than 2 m. For the installer of exterior joinery, the decisive height is measured from the bearing edge of the opening or the interior working floor to the finished exterior ground, or to the first landing obstacle located directly below the opening. The presence of a masonry sill changes the assessment of the risk: if the top edge of the raw sill after removal is less than one metre from the walkable interior floor and the fall to the outside exceeds two metres, collective protection becomes immediately required.
Installing the temporary opening guardrail and organising the interior marking-off
The temporary guardrail must be installed before any heavy dismantling of the old window. Art. 22 OTConst sets the requirements for the perimeter guardrail: a top rail whose upper edge is at least 100 cm above the walkable surface, at least one intermediate rail, a toe board of at least 15 cm, and a maximum spacing of 47 cm between elements. Within the depth of a window reveal, the temporary device must comply with these dimensions or consist of an equivalent solid or lattice element preventing a worker from passing through.
| Device | Fixing principle | Advantages | Construction site constraints |
|---|---|---|---|
| Extendable jack strut | Mechanical pressure by screw thread between the side reveals | Installed without drilling, quick adjustment | Rigorous check of the stability of the raw masonry |
| Clamped metal posts | Jaws clamped onto the masonry sill or the slab | Leaves the reveal completely clear for inserting the new frame | Requires a load-bearing sill and sufficient projection |
| Plugged timber or metal frame | Direct anchor screws into concrete or calcium silicate brick | Very high resistance to horizontal forces | Requires drill holes to be made good after removal |
The chosen equipment must be positioned so as to allow the complete removal of the old frame without losing its structural integrity. When the new window is to be inserted into the opening, the team coordinates the temporary removal of the guardrail only if compensatory measures are in place or if the new frame acts as a barrier once it is mechanically fixed in the structural work.
- Position the temporary guardrail slightly set back towards the outside or inside of the rebate so as to work freely.
- Check that the clamping pads are locked to avoid any slipping on smooth concrete or residual render.
- Check the height of the top rail to maintain strictly 100 cm above the finished interior floor.
- Keep the 15 cm toe board to prevent tools, wedges or chisels falling into the public area below.
In addition to the physical restraint at the façade, interior marking-off is mandatory to prevent access to the room or the handling area. On renovation construction sites where other trades are moving about, signage with red and white tape or a rigid extendable barrier must be placed at least two metres back from the opening. This delimitation protects people not involved in the installation against inadvertently approaching the void and signals a zone for handling heavy glazing.
Coordinating opening phases and maintaining collective protection
When replacing glazed elements in renovation or when structural work is closed in late, removing the frame instantly leaves a gaping opening to the outside. As soon as the void is created, the work zone falls under the fall-prevention rules. Under art. 23 OTConst, a perimeter guardrail is installed in unprotected places where the fall height is greater than 2 m. On the upper floors of a residential or office building, the façade void meets this criterion immediately once the fixing brackets of the old frame are cut.
The organisation between demolition/removal teams and exterior joinery installation teams must rule out any break in the continuity of collective safety. Removing an opening at 8:00 and only bringing in the new subframe or monobloc frame at 14:00 needlessly exposes the construction site. The phasing requires installing an extendable temporary guardrail clamped in the masonry reveals, or mechanically fixing light scaffolding uprights, before even removing the old cut-out frame. If the exterior access has no compliant ground-based scaffolding, protection is provided entirely from the interior slab.
| Construction site configuration | Fall height | Device required in the reveal | Interior marking-off |
|---|---|---|---|
| Upper ground floor above a semi-buried basement | Less than 2 m | Protection optional under the ordinance, but a visual rail is recommended | Red and white signalling tape 1 m from the finished face |
| Typical floors without ground-based scaffolding | Greater than 2 m | Complete temporary guardrail (top rail, intermediate rail, toe board) | Rigid chain or workshop barrier with prohibition sign |
| Floor with façade scaffolding in place | Working platform less than 50 cm from the drip rebate | Exterior platform acting as restraint | Work zone delimited to prevent access by third parties |
| French window opening onto a void (demolished balcony) | Greater than 2 m | Rigid stop barrier mechanically fixed to the jambs | Access marking-off reserved for properly equipped installers only |
Installing reveal guardrails and managing interior traffic
The temporary interior opening guardrail must be rigid and able to withstand accidental pushes from fitters handling heavy joinery. Systems with a horizontal pressure jack, wedged against the clay brick or concrete of the jambs, are the quickest solution without damaging the structural work intended to receive the perimeter thermal insulation or the airtightness strips. These telescopic props must incorporate the support for a top rail, an intermediate rail and a toe board to hold back falling demolition debris towards the public road or lower levels.
- Clearing and cleaning the revealRemove residual rubble, degraded mortar and old metal fixings on the three interior faces of the reveal to ensure a stable bearing surface for the pads of the temporary guardrail.
- Installing the clamping propPlace the telescopic prop horizontally at the required height and operate the clamping screw with the dedicated lever until sufficient pressure is obtained without bursting the masonry lining.
- Fitting the intermediate rails and the toe boardInsert the intermediate crossbar and fix an end-on timber board or a metal retaining section flush with the threshold to contain splashes of plaster, mineral wool or drill bits.
- Setting up the interior marking-offClose off access to the room or erect a mobile barrier at least one and a half metres from the reveal to prevent other trades (painters, electricians, plumbers) working in the same dwelling from approaching.
Managing unforeseen events and opening protection failures
On a renovation construction site, the unprotected opening directly exposes fitters and other trades to a risk of falling over the void. Art. 23 OTConst sets out the cases where the perimeter guardrail is used, installed in unprotected places where the fall height is greater than 2 m. If removing the old frame reveals unforeseen deterioration of the masonry that prevents reliable anchoring of the reveal props or clamping plates, the installation of collective protection fails at the critical moment.
As soon as mechanical instability prevents the temporary opening guardrail from being secured, the team suspends the removal operation. Art. 22 OTConst specifies the requirements for the perimeter guardrail, in particular the top rail at least 100 cm high, the intermediate rail and the toe board of at least 15 cm. If this device cannot be rigidly fixed in the splayed reveal, the team leader closes off access to the room from the inside with a rigid open-work barrier fitted with a prohibition sign, to neutralise the work zone.
- Immediate evacuation of the work area back from the void and report to the foreman.
- Installation of a rigid physical barrier at the room entrance with the interior access locked.
- Immediate written notification to the site management reporting the geometric or structural obstacle.
- Temporary installation of personal fall protection attached to a structural anchor point accepted in accordance with the recognised rules of the trade.
When the new frame cannot be wedged and fixed on the same day, the opening must never be left gaping overnight. The installer fits a solid wood-based panel, mechanically fixed to the rebates to withstand horizontal thrust and wind. For the pricing of these emergency closure devices, refer to /soumissions/.
Frequently asked questions
What should be done if the window sill has a height of less than 100 cm?
As soon as the finished masonry sill is less than 100 cm above the interior floor and the exterior fall height exceeds the regulatory threshold, the opening becomes a dangerous void once the sash is removed. The installer must install an extendable temporary guardrail, locked by mechanical clamping between the reveals, to recreate a complete barrier comprising top rail, intermediate rail and toe board before removing the existing frame.
Is red and white signalling tape enough to close off interior access?
No, a simple chain or plastic tape is not compliant marking-off in the face of a fall-from-height risk. The interior device must be physically impassable, in the form of stable rigid barriers or closure panels locked in the door opening. Visual signage complements the physical obstacle but never replaces it, strictly preventing any third-party intrusion into the room containing the gaping opening.
Can the temporary guardrail be fixed directly to the frame of the old window?
This practice is strictly prohibited because it compromises safety during the cutting or tearing-out of the old frame. The temporary guardrail must be entirely secured to the raw masonry, via the side reveals or the lintel. This guarantees permanent restraint while cutting the fixing brackets, handling the removed metal or timber elements, and fully cleaning the rebate receiving the new frame.
How should an opening be secured when exterior façade scaffolding is already in place?
If the façade scaffolding is erected less than 30 cm from the wall with a working platform at the level of the opening and correctly positioned rails, it provides collective protection against falls to the outside. On the other hand, if the distance to the wall exceeds this tolerance or if no scaffolding platform runs directly alongside the opening, installing a reveal guardrail is still required before any removal of the frame.
Texts and standards cited
- OTConst art. 22requirements for the perimeter guardrail: top rail whose upper edge is at least 100 cm above the walkable surface, at least one intermediate rail, toe board of at least 15 cm, maximum spacing of 47 cm between elements.
- OTConst art. 23use of the perimeter guardrail: installed in unprotected places where the fall height is greater than 2 m, for slopes more than 2 m high and steeper than 45°, and near bodies of water and watercourses (para. 1).