Key takeaways
- A three-metre panel generates a violent sail effect even in a moderate breeze.
- A visual and pneumatic check of the suction cup seal is required before each handling operation on the construction site.
- Manual handling requires two qualified fitters for any sheet exceeding one square metre.
- Above thirty kilograms, the use of mechanical lifting equipment becomes the technical rule.
Checking suction cups and anticipating the sail effect according to Suva guidelines
On a ventilated façade, cladding in fibre cement, high-pressure laminate or large-format ceramic comes in individual panels that can exceed three metres in length, with a significant weight per unit area. In even a moderate breeze, this format behaves like a genuine ship's sail. The Suva safety guidelines point out that the blast effect or corner overpressure can instantly tear the element from the fitters' hands, unbalancing the team on the scaffolding decks or causing the material to fall fatally onto the walkways below.
In accordance with art. 82 LAA, the employer shall take all measures that experience has shown to be necessary, that are feasible according to the state of the art and that are appropriate to the given conditions, in order to prevent occupational accidents and illnesses. In the context of installing exterior cladding, this implies strict monitoring of wind speed by means of a portable anemometer installed on the highest working platform. From a wind speed of 30 km/h, the transport and positioning of large panels must be suspended.
The grip of manual lifters depends entirely on the cleanliness of the surface and the integrity of the rubber sealing lip. Dust from sawing the framework or residues from cutting fibre cement work microscopically under the suction cups, causing a slow but irreversible loss of vacuum during lifting. Devices fitted with a manual pump piston have a red warning line on the pump body: if the red ring reappears after the initial pumping, the vacuum is compromised and the grip must be repeated.
- Cleaning the substrateDust the gripping area on the panel with a clean, dry cloth. Never apply greasy products or solvents, which would degrade the elastomer of the suction disc.
- Inspecting the rubberExamine the elastomer disc of the suction cup. Immediately reject any device showing cuts, cracks or permanent deformation of the circular profile.
- Pumping and proof loadingOperate the piston until the red warning indicator has disappeared completely. Before any movement, apply a vertical proof pull of a few centimetres above the blocks.
- Monitoring the pressure gaugeFor battery-powered portable suction cups, check the digital gauge display or the automatic shut-off of the compressor indicating that a compliant vacuum is being maintained.
Organising the installation team and coordinating mechanical lifting aids
Art. 17 OTConst provides that, at workstations and walkways, measures must be taken so that workers are not endangered by the collapse of building elements or the fall of objects and materials. Lifting a composite sheet or mineral panel of more than one square metre may on no account be entrusted to a lone fitter. The two-person team is the minimum working unit. The two façade fitters must position themselves on either side of the centre of gravity to keep a stable footing and jointly absorb unexpected aerodynamic loads.
On a façade scaffolding, the room to move is restricted by the tubular uprights, diagonals and guardrails. A panel three metres long cannot be pivoted without continuous verbal coordination. One of the fitters is designated as leader: he announces the set-down times, the locking into the starter blocks and the approach against the sections of the intermediate framework. No lateral movement on the deck is made walking backwards without first checking that there are no obstacles on the floor, such as offcuts of EPDM strips or riveting tools.
| Unit mass | Panel surface area | Personnel required | Recommended handling equipment |
|---|---|---|---|
| Less than 25 kg | Less than 1.50 m² | 2 façade fitters | Double manual suction cups with lever or piston |
| Between 25 kg and 50 kg | From 1.50 m² to 3.00 m² | 2 to 3 fitters | Portable vacuum suction cups with hand-held spreader bar |
| More than 50 kg | More than 3.00 m² | 3 fitters and 1 crane operator | Motorised suction cup spreader bar suspended from a winch or crane |
As soon as the weight of the panel exceeds fifty kilograms, or its geometry makes manual work unstable, the use of a mechanical aid becomes essential to protect the fitters' health and the installation geometry. Using a bracket fixed to the structure, a construction site material hoist or a stand-alone suspended suction cup spreader bar relieves strain on the lower back. The mechanical gripping device must then have a dual, independent vacuum circuit, in accordance with the recognised rules of the trade, to hold the component in the event of failure of one of the pneumatic chambers.
Guiding, dynamic stabilisation and managing façade turbulence
As soon as a ventilated cladding element reaches three metres in length, its flat surface develops considerable wind exposure at the moment it crosses the plane of the scaffolding. A large-format composite or fibre-cement sheet offers a surface of more than three square metres. At building corners or in the corridors created by inner courtyards, an apparently moderate airflow generates sudden venturi effects. According to art. 17 OTConst, at workstations and walkways, measures must be taken so that workers are not endangered by the collapse of building elements or the fall of objects and materials. Lifting must therefore never be carried out with the load left free to swing.
The path of the panel, whether it is raised by a scaffolding winch or a mobile bracket, requires the continuous use of guide ropes attached to the lower ends of the piece. These lines allow the fitters who remain on the ground or on the lower deck to steer the cladding without exposing their hands under the load. In parallel, the operators stationed on the working level receive the sheet using manual positioning suction cups with controlled vacuum, fitted with a red visual indicator. These tools serve only to direct the millimetre-precise movement of the element towards the load-bearing framework, and not to bear its dead weight if the lifting device has not been locked.
| Measured wind force | Estimated dynamic pressure | Effect on a 3.00 × 1.20 m panel | Organisational measure required |
|---|---|---|---|
| 0 to 15 km/h (light breeze) | < 15 N/m² | Lateral force below 55 N (approx. 5.5 kg) | Normal handling by two fitters with manual suction cups |
| 16 to 30 km/h (moderate wind) | 15 to 45 N/m² | Thrust of 55 to 160 N, pronounced swinging | Guide ropes mandatory, mechanical support from a spreader bar |
| 31 to 45 km/h (fresh to strong wind) | 45 to 100 N/m² | Thrust up to 360 N (uncontrollable sail effect) | Immediate stop to the handling of large formats |
| > 45 km/h (gusts) | > 100 N/m² | Risk of suction cups being torn off and of falling | Securing and lashing down all stored panels |
Storage on the floor level, temporary securing and locking to the framework
Conveying sheets onto the scaffolding deck requires rigorous logistics. No large panel may simply be left standing against the uprights or guardrails. Packs placed on the extension brackets must be wedged on floor-level racks connected to the tubular structure. Each element must be held by ratchet straps until the exact moment it is fixed in place. In accordance with art. 82 LAA, the employer shall take all measures that experience has shown to be necessary, that are feasible according to the state of the art and that are appropriate to the given conditions, in order to prevent occupational accidents and illnesses; workers shall assist him in this. This obligation takes on its full meaning when synchronising the two-person installation team.
- Presenting and bringing the panel up to the load-bearing sectionThe panel is held by the battery-powered suction cup spreader bar or by two double manual suction cups. The two-person team brings it up parallel to the vertical aluminium or timber uprights, maintaining the width of the open joint by means of calibrated spacer blocks.
- Temporary mechanical holdAs soon as the sheet contacts the sealing strips or the framework, one operator holds the sheet in place with the suction cup while the other engages façade vice clamps or immediately fits two holding fixings at the centre of gravity.
- Safely removing the lifting suction cupsThe load is released from the mechanical aid only once the temporary screws or rivets are anchored in the sections. The vacuum pump is released only after verbal confirmation between the two fitters.
- Final fixing and checking the fixed pointsThe two-person team carries out the complete screwing pattern according to the cladding manufacturer's instructions, alternating fixed points and sliding points to ensure free thermal expansion without deformation under wind.
At the end of the shift or in the event of a sudden deterioration in weather conditions, no panel may be left on blocks or held only by clamps. Partially fixed elements are subjected to cyclic pressures and suctions that prematurely fatigue unlocked fixings and can tear off the light framework. Teams must secure each completed work section and fold the suction cups back into their carrying cases after fully wiping the elastomer membranes.
Emergency procedure: loss of vacuum, sudden gust and making safe
A thermal gust at the top of the scaffolding or a vacuum-loss alarm instantly turns the handling of a large cladding panel into a critical construction site situation. According to art. 82 LAA, the employer shall take all measures that experience has shown to be necessary and appropriate to the conditions in order to prevent accidents, while workers actively assist him. With a sheet three metres long, the cladding acts like a genuine sail in the wind. As soon as the path escapes control or the balance of the two-person team wavers, the installation manoeuvre must be suspended immediately.
- Stop order and protection of the fittersThe person in charge of the manoeuvre orders an immediate stop. The fitters stop resisting the gust while off balance so as not to be thrown against the rails or the guardrail of the scaffolding.
- Emergency mechanical pressing against the frameworkIf the panel is already at floor level, the two-person team presses it firmly against the vertical sections of the ventilated framework and immediately secures it using padded clamps.
- Lowering to the ground under a cordoned-off zoneIn the case of mechanical lifting, the crane operator lowers the load smoothly to the ground or onto the lower deck, within the secured perimeter, to protect workstations against falling materials in accordance with art. 17 OTConst.
- Clamping and lashing on a ballasted trestleOnce the panel is set down, the operators fit a ratchet lashing strap around the storage rack to eliminate any risk of overturning under the effect of air eddies.
After such an event, resuming installation requires a methodical technical check before any new lifting attempt. The team leader inspects the manual suction cups or the spreader bar, cleaning the pads and looking for micro-cracks caused by sharp edges. A five-minute static vacuum holding test on a test sheet validates the circuit. Finally, gusts are measured with an anemometer in the installation area: if the wind exceeds the safety tolerances, work remains stopped.
Frequently asked questions
At what wind threshold must the installation of large cladding panels be stopped?
The Suva guidelines and professional rules recommend assessing the risk from 30 km/h and imperatively stopping manual or spreader-bar handling as soon as the wind reaches 40 to 45 km/h in gusts. With a three-metre panel, the exposed surface turns the load into an uncontrollable sail. The team leader measures the actual speed at the top of the structure using a portable anemometer before each delicate lift.
What should be done immediately if the vacuum indicator of a suction cup turns red?
As soon as the red safety ring appears on the piston of the manual suction cup or the audible signal of the spreader bar sounds, lifting stops immediately. Operators must not try to re-prime the pump while keeping the load in the air. The panel must be set down immediately on a stable surface or pressed against the framework, then the faulty suction cup is taken out of service for a complete inspection of the sealing gasket.
Can a façade panel weighing more than 40 kg be handled by two people without mechanical aid?
No. For an element exceeding 30 to 40 kg or more than two square metres in area, working in pairs without mechanical assistance exposes fitters to musculoskeletal disorders and critical losses of balance. It is essential to use a façade crane fitted with a battery-powered suction cup spreader bar or an installation forklift. The team on the ground then only provides guidance using suitable ropes.
How should cladding sheets be temporarily stored on scaffolding in the event of a storm?
Storing large unfixed panels on scaffolding is strongly discouraged. In the event of a sudden deterioration in the weather, the sheets must be laid flat on softwood blocks or placed on a floor-level rack suited to the permissible load of the decking. The whole must be firmly lashed to the tubular structure of the scaffolding with ratchet lashing straps, preventing any wind exposure under the panel.
Texts and standards cited
- LAA art. 82general prevention rules: the employer shall take all measures that experience has shown to be necessary, that are feasible according to the state of the art and that are appropriate to the given conditions, in order to prevent occupational accidents and illnesses; workers shall assist him.
- OTConst art. 17protection against the collapse of building elements or the fall of objects and materials: at workstations and walkways, measures must be taken so that workers are not endangered.
