Key takeaways
- Check the level and squareness of the frame before changing the position of the sash.
- Adjust the height and the lateral offset directly on the lower corner bearing.
- Correct the parallelism and the upper corner engagement by turning the screw of the stay arm.
- Test the uniform compression of the sealing gasket using the paper-strip test.
Correct the plumb and squareness of the sash using the corner bearing and the stay arm
An external window fitted square can show major malfunctions as soon as it is put into service if the perimeter clearances are not balanced. A sash rubbing on the lower frame or catching at the opening gap damages the hardware, distorts the profiles and breaks the continuity of the sealing barrier. The three-dimensional adjustment is carried out methodically on the sash in the open position, using hexagon (Allen) keys, generally 4 mm.
- Height adjustment on the corner bearingRemove the protective cover from the lower corner hinge. Turn the vertical axial screw at the top of the bearing to raise or lower the whole sash by a few millimetres, until the contact against the lower rail of the frame is released.
- Lateral adjustment at the bottom of the sashWork on the horizontal screw housed in the lower bearing support. This moves the base of the sash to the right or left, re-centring the bottom of the sash in relation to the side rebates.
- Adjustment of the stay arm on the top railReach the adjustment screw located on the stay arm, on the upper hinge side. Turning it tilts the sash towards the hinge or away from it, restoring the vertical plumb of the espagnolette stile and the overall squareness of the sash.
When adjusting the stay arm and the lower hinge is not enough to straighten a sagging sash, the problem often comes from poor distribution of the insulating glass load. Diagonal packing inside the sash rebate transfers the loads to the lower bearing. This must be checked before the metal adjustment threads of the hardware reach the end of their travel.
Adjust the seal compression at the keeps and validate with the paper strip
Air and wind-driven rain tightness depends on the even compression of the central gasket and the closing gasket. Insufficient compression causes audible whistling in windy conditions and promotes liquid infiltration by capillary action. Conversely, excessive tightening wears the elastomers prematurely and stiffens the handle to the point of abnormally stressing the operating rods.
| Mechanical or acoustic observation | Main cause in the hardware | Adjustment required |
|---|---|---|
| Localised air whistling at the top | Lack of support from the stay arm or slack upper roller | Adjust the eccentric of the upper roller inwards |
| Handle hard to bring back to the closed position | Excessive overall compression or rubbing on the keep | Turn the rollers to the neutral position or move the keeps back |
| Water infiltration at the foot of the window | Lower gasket poorly compressed or sagging sash | Raise the sash and increase the eccentricity of the lower rollers |
Compression is adjusted by changing the orientation of the locking rollers distributed along the espagnolette and the extension rods. These clamping parts have an eccentric or octagonal head. A quarter-turn with a suitable key changes the striking axis by 0.5 mm to 1 mm relative to the fixed keep fitted on the frame.
In accordance with the SIA 118 standard, the contractor is responsible for the conformity of the work delivered. Under art. 365 CO, the contractor is responsible for the good quality of the material it supplies and informs the client without delay if a circumstance jeopardises the soundness of the work. Acceptance without a compression check exposes the installation team to warranty call-backs for wind tightness defects.
Roller synchronisation and diagnosis of operating faults
A tilt-and-turn window whose squareness and basic compression are correctly set can still show severe operating faults under wind pressure or during wind-driven rain. The cause almost always lies in a lack of kinematic synchronisation between the locking rollers and their receiving keeps on the frame. When the handle is operated, each mushroom or roller cam must enter the centre of the keep recess with sufficient engagement travel to compress the sealing lip evenly without forcing the transmission rod.
| Observed symptom | Probable mechanical origin | Adjustment required | Tool required |
|---|---|---|---|
| Sharp crack when closing in turn mode | Mushroom roller striking the entry of the keep | Correct the sash height at the corner bearing or move the keep back | 4 mm hexagon key or Torx T15 |
| Handle stiff in the horizontal position (90°) | Side rollers locked in excessive compression | Reduce the eccentricity of the rollers (switch to neutral mode) | 11 mm flat spanner or special roller key |
| The sash tilts when opened in turn mode | Misuse-prevention device out of sync or worn | Adjust the protrusion of the locking tab on the edge of the sash | PZ2 cross-head screwdriver |
| Persistent air whistling in gusts | A roller on the top rail not engaging | Adjust the pull of the spacing stay arm towards the frame | 4 mm hexagon key |
The key component ensuring the durability of the whole assembly remains the lifting keep combined with the misuse-prevention device. Without this element correctly set in the lower rebate, the weight of the insulating glass puts excessive load on the corner bearing during repeated closing cycles. The lifting ramp must catch the sash shoe over the last 15 millimetres of its travel to lift it gently by 1 to 2 millimetres, thus relieving the upper axis of the stay arm.
Methodical acceptance procedure and validation at critical points
Acceptance of a glazed envelope element requires an objective record of conformity before the site is handed over. The team leader applies a sequence of physical checks to each sash to make sure there are no air leaks or residual water infiltration. Recording the rebate clearances is the essential first step: the nominal clearance must remain strictly uniform on all four sides of the element.
- Visual check of the gasket imprintApply a film of greasy chalk or talc around the perimeter of the inner sealing lip. Close the window in the locked position, then reopen it. Check the continuity of the white trace transferred onto the frame: any break indicates an air-leak zone where the gasket does not make contact.
- Localised pull test with a paper stripInsert a calibrated 80 g/m² paper strip every 30 centimetres, and immediately next to each locking roller. The strip must resist being pulled out without tearing while offering firm hold under straight manual traction.
- Checking free travel and rebate clearancesUsing a calliper or depth gauge, measure the overlap of the sash on the frame at four points. The difference between opposite measurements must not exceed 1.5 millimetres, to ensure the keeps receive the rollers with a sufficient safety margin.
- Tilt test under stressOpen the sash in tilt mode, check the mechanical stability of the limiting stay arms and make sure the handle cannot be turned accidentally towards the turn position without re-engaging the misuse-prevention device.
The final handover of the windows to the client also involves lubricating the moving parts with a resin-free and acid-free oil on the stay arm axes, pivot points and sliding plates. The acceptance record documents the final adjustments and the tolerances measured, thereby formally releasing the installer from liability for later misalignments caused by natural settlement of the building.
Action to take for residual infiltration and whistling
When a tilt-and-turn sash whistles under wind pressure or lets water infiltrate despite the usual adjustments, the mistake is to compress the rollers to their maximum value. Excessive compression distorts the sash, stiffens the handle and will irreversibly crush the EPDM gasket without solving the air-tightness defect.
The installation foreman then applies a step-by-step remedial sequence to isolate the geometric or mechanical cause before considering partial removal.
- Checking the parallelism of the frameCheck the straightness of the fixed frame stiles with a laser level and tape measure. Bowing of more than 2 mm at the centre reveals an overtightened through-fixing without a rigid packer, which prevents the roller from reaching the flat of the keep.
- Re-setting the glazing with bridge packingIf the closing clearance remains uneven despite the stay arm adjustment stop, unclip the glazing beads and correct the setting blocks and wedging packers of the insulating glass. This mechanical action restores the sash's own squareness by triangulation of the glass.
- Checking the sealing barriersCheck the continuity of the inner sealing membrane and the drainage of water in the lower rebate. Missing pressure equalisation or blocked drainage nozzles send water back onto the floor during gusts.
If the masonry support or the frame structure shows abnormal settlement distorting the sub-frame, the contractor refers to the obligations of art. 365 CO. Under this article, if a circumstance jeopardises the regular or timely execution of the work, the contractor informs the client immediately. The report will state the deviations found in relation to the tolerances of the SIA 118 standard.
Frequently asked questions
How should a sheet of paper that tears during the test be interpreted?
A torn sheet of paper indicates excessive compression of the closing gasket. This excessive pressure accelerates ageing of the elastomer lips, abnormally stresses the axis of the corner bearing and makes the handle too hard to operate. The locking roller must be loosened by a quarter-turn with an Allen key to restore a firm slide without tearing.
Why does the window still rub at the bottom after adjusting the stay arm?
Adjusting the screw of the upper stay arm tilts the head of the sash towards the hinge but does not raise the window vertically. To free the lower profile that catches the lower keep, remove the cap of the lower corner bearing and work directly on the vertical height adjustment screw with a 4 mm hexagon key to lift the whole sash.
When must the glazing be re-packed rather than the hardware adjusted?
Re-packing the glazing is necessary when the hardware screws reach the end of their travel without correcting the out-of-square condition. By removing the glazing beads to redistribute the plastic packers between the glass and the sash profile, the weight is transferred to the lower diagonal on the hinge side. This restores the right angle without forcing the mechanics of the metal corner drives.
How to deal with a persistent whistle localised in the opposite upper corner?
Air passing through the upper closing corner results from a stay arm not pressed home or a top roller not entering its keep. Remove the faceplate to adjust the stay arm pressure using the eccentric provided on the upper link, or move the frame keep sideways along the vertical stile to ensure full engagement when the handle is turned.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material it supplies; if the material supplied by the client or the ground designated by the client is found to be defective, or if another circumstance jeopardises the regular or timely execution of the work, the contractor informs the client immediately, failing which it bears the consequences (para. 3).
- norme SIA 118General conditions for the execution of construction work