Key takeaways
- Corner profiles absorb expansion while ensuring the overlap that keeps the wind seal.
- The reveal return maintains a continuous air cavity without compressing the opening insulation.
- The upper drip edge throws run-off water clear of the façade plane.
- The junction between dissimilar materials prevents galvanic corrosion and absorbs differential thermal movement.
Executing ventilated corners and reveal returns
On a ventilated façade built to Swiss rules of the art, the corner is the first line of defence against mechanical and climatic stresses. Whether it is an external corner closed by an extruded aluminium profile or an open corner leaving the hollow joint visible, the secondary framing must always decouple the two wall faces. Never screw a single bracket directly to two perpendicular walls, in order to prevent any damage caused by differential shrinkage of the structural work or thermal expansion of the cladding.
- Fit a corner profile at least 1.5 to 2.0 mm thick in powder-coated aluminium sheet or stainless steel to prevent any waviness under wind load.
- Mechanically overlap the rainscreen membrane by at least 150 mm behind the corner edge, sealed with a wind-tight, UV-resistant acrylic adhesive tape.
- Always maintain the 5 to 8 mm expansion gap at panel ends to absorb the annual temperature swings in alpine or plateau climates.
- Double up the framing battens or aluminium uprights to give each cladding end a continuous, independent support.
The window reveal, for its part, combines two contradictory requirements: insulating the reveal right up to the window frame to eliminate linear heat loss, while ensuring moisture is removed through a free air cavity. The reveal insulation, often limited to 30 or 50 mm, receives a rainscreen membrane turned up and sealed directly onto the window profile by means of a pre-compressed connection tape. The air cavity of at least 20 mm runs continuously up behind the reveal panel to emerge under the lintel.
| Work zone | Fixing type | Minimum air cavity | Critical check point |
|---|---|---|---|
| Closed external corner | Stainless steel screw with EPDM washer | 30 mm behind framing | Continuous rainscreen overlap without tears |
| Open internal corner | Rivets or lacquered screws on double batten | 30 mm behind framing | Protection of the flexible membrane from direct UV radiation |
| Vertical reveal return | Concealed fixings or clamped stop profile | 20 mm free in reveal | Ventilation not obstructed by the insulation return |
| Window sill / upstand | Metal flashing with splice plate | Not ventilated under watertight flashing | Continuity of the waterproofing under the frames and at end upstands |
Fitting lintel drip edges and handling mixed junctions
The horizontal break in the cladding at an opening requires a flawless water-shedding device. The upper metal drip edge, often formed from aluminium or zinc-titanium sheet metalwork, provides the transition between the general cladding and the window lintel. It is inserted under the rainscreen membrane of the main façade with a lap of at least 100 mm to catch any water ingress and discharge it clear of the wall. A minimum slope of 8% towards the outside prevents water standing during driving rain.
- Forming and fixing the lintel flashingFold the sheet with a 20 mm rear crushed fold fixed to the framing, a plane sloping outwards and a drip falling 20 mm in front of the finished face of the window joinery.
- Fitting the vermin guardFit a perforated ventilation profile upstream of the drip edge to guarantee the free air inlet area without allowing small animals or debris to enter.
- Watertight connection to the rainscreen membraneFold the façade membrane down onto the vertical upstand of the drip edge and bond it with an approved adhesive tape resistant to ageing and extreme temperatures.
- Fitting the side returnsFold heels of at least 20 mm at the ends of the drip edge to direct the collected water to the outside of the reveals and prevent any lateral infiltration.
The junction between ventilated cladding and another material, for example render on external thermal insulation or a raw concrete plinth, requires strict physical and mechanical separation. Direct contact between dissimilar metal framing or cladding causes severe galvanic couples in damp conditions. EPDM shims or chemically neutral insulating underlays are always interposed.
The contractor applies the recognised rules of the art and is liable for technical defects arising from construction details that do not comply with the manufacturers' requirements or the industry's professional recommendations.
norme SIA 118
Air cavity continuity and reveal return linings at window openings
The treatment of reveals is the critical zone on which the thermal and airflow durability of the work depends. When connecting to the subframe or the window frame, the rear ventilation cross-section must on no account be blocked by the lining panel or sheet. Air circulating vertically behind the main skin must find a controlled outlet or continue rising along the secondary framing, without creating a moisture trap against the thermal insulation.
To ensure water vapour is removed while blocking driving-rain ingress, the added reveal return is fixed to aluminium or stainless steel angle brackets. These leave a free channel of at least 20 mm. A perforated vermin guard in stainless steel or aluminium, with calibrated perforations of 3 to 5 mm, protects the gap at the base and head of the reveal. The edges of fibre-cement panels, high-pressure laminates or timber boards must be machined with a clean chamfer, then treated on the cut edge with a water-repellent saturator before fixing.
| Cladding material | Reveal connection profile | Required expansion gap | Corner edge treatment |
|---|---|---|---|
| Autoclaved fibre-cement | Folded 15/10 mm lacquered aluminium sheet | 5 mm to 8 mm per linear metre | Factory chamfering and clear impregnation |
| Ventilated solid timber (larch/Douglas fir) | Open-slatted reveal board on batten | 8 mm to 10 mm at the base of the rebate | Bevel cut at 15° forming a drip |
| Compact laminate (HPL) | Anodised aluminium corner channel | 3 mm per metre from the fixed point | Careful deburring, no sealing with sealant |
| Composite metal panels | Folded sheet with crimped return | 2 mm to 4 mm depending on the panel layout | Cold folding with minimum radius of 2 mm |
The connection between the lining profile and the sill piece or window subframe must never rely on a simple bead of silicone exposed to the weather. A pre-compressed sealing tape of a class impregnated to resist driving rain is used, backed by an airtight seal on the inside. Water collected on the surface of the reveal must drain freely to the drip flashing without bypassing the insulating barrier.
Managing lintel drip edges, corner profiles and material transitions
At the lintel, the horizontal break in the cladding requires a rigorous drip device. The drip-edge sheet in folded aluminium or zinc-titanium must be sized with a slope of at least 8% towards the outside. Its front drop has a crushed fold or a projection of at least 15 mm forming a drip break, preventing run-off water from rising by capillary action towards the head of the frame. External and internal corner profiles, for their part, require different treatment depending on whether they are executed with open joints or with metal trim profiles.
- Preparing the corner substructureAlign the vertical uprights set back from the edge to allow the corner angle profiles to expand without creating a hard point.
- Fitting the lintel flashing with drip edgeMechanically fix the water-shedding sheet to the framing, ensuring a watertight lap with the upper rainscreen membrane by adhesive bridging.
- Fitting the upper ventilation grillePosition the perforated profile under the drip edge, leaving an airflow cross-section that complies with the stack-effect requirements.
- Junction with the adjacent materialInterpose a chemically neutral separation profile where the ventilated cladding meets perimeter render or raw masonry.
For site safety when installing corners and lintels at height, access requires stable platforms. Art. 26 OTConst requires the installation of façade scaffolding as soon as the fall height exceeds 3 m, thus providing secure support for the fine adjustment of the metal profiles. Adjusting the laps must never force the panels; through-fixings must have slotted or oversized holes to preserve the clearance needed for the thermal movement imposed by the Swiss climate.
Handling assembly non-conformities and reworking critical points
On a ventilated façade construction site, a misalignment at the corner profile, a poorly sized drip edge or an interruption of ventilation at a window reveal immediately compromises the driving-rain protection barrier. As soon as the foreman identifies a dimensional deviation or an out-of-flush condition, cladding installation must be stopped locally to avoid enclosing a defect in the air cavity.
- Check squareness and the minimum 5 mm expansion gap at internal and external corner profiles.
- Check the continuity of the drip edge at the lintel with an effective drip projection of 30 mm.
- Measure the residual ventilation cross-section in the window reveal, ensuring at least 200 cm² per linear metre.
- Check the EPDM sealing tape and chemical compatibility at junctions with other claddings.
If the concrete or masonry substrate has non-compliant tolerances that prevent precise adjustment of the framing, the contractor applies the usual contractual provisions. In accordance with art. 365 CO, if the client supplies a defective substrate or if an unforeseen situation prevents proper execution, the façade contractor reports the facts so that the plumb corrections can be organised before final installation.
| Defect identified | Direct consequence | Remedial measure on site |
|---|---|---|
| Drip edge slope reversed | Water infiltration towards the insulation | Remove the sheet, rework the wedge to ensure a minimum fall of 5° towards the outside. |
| Pinched reveal return | Thermal blockage and condensation | Trim the cladding to restore a continuous 20 mm air cavity behind the lining. |
| Bare aluminium-steel contact | Accelerated galvanic corrosion | Interpose an insulating resilient strip or rot-proof neoprene shims. |
During corrective work requiring the removal of façade elements, collective safety remains the priority. Art. 26 OTConst sets the criteria for façade scaffolding on building construction sites, notably as soon as the fall height exceeds 3 m, with a top guardrail rising at least 80 cm above the work area.
Frequently asked questions
How do you ensure cladding ventilation behind a narrow reveal lining?
When the window return does not leave the space needed for a double framing, the metal or fibre-cement lining is fixed on specific perforated brackets or thin aluminium omega profiles. These profiles provide a continuous rear air cavity of 20 mm connected to the main network, closed at head and base by a perforated insect guard calibrated to stop pests without breaking the convective flow.
What slope should the lintel drip edge have to prevent run-off water returning?
The drip-edge sheet folded in the workshop must have a minimum slope of 5° towards the outside, completed by a drip fold descending at least 30 mm below the edge of the cladding. The back of the piece rises against the rainscreen membrane by at least 100 mm, forming a continuous barrier that sheds run-off water without risk of wetting the upper rail of the window subframe.
How do you treat the external corner between two claddings with different expansion coefficients?
The junction is made using a decoupled spacing corner profile, mechanically fixed to a common substructure but with slotted holes for the element with high thermal expansion. A gap of 5 to 8 mm is left between the panel edges and the base of the profile rebate. The framing connections receive a flexible sealing tape that ensures wind-tightness without mechanical restraint.
What should be done when the glazed opening is set too far forward relative to the face of the cladding?
This situation prevents the regular development of the drip edge and the ventilated return. The façade contractor suspends fixing of the perimeter lining and documents the offset. If the window cannot be set back, the technical solution is to make a watertight metal cassette forming a surface-mounted external subframe, covering the window frame with a compressible seal while keeping a rear ventilation slot for the façade.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).
- OTConst art. 26façade scaffolding in building construction work: façade scaffolding must be installed as soon as the fall height exceeds 3 m; the top guardrail must extend at least 80 cm above the edge of the highest area at risk of falls (100 cm if the guardrail is less than 60 cm from the edge) (para. 2).