🧱 CFC 221The three barriers: air, insulation, driving rainChapter 1 of 10 in the section

Vapour barrier or vapour retarder: which one, and on which side of the insulation

By the end of this chapter, you will be able to determine precisely whether to install an airtight vapour barrier or a variable-permeance vapour retarder in a lightweight facade. You will master the principle of positioning it on the warm side of the insulation according to SIA 180 and know how to ensure the drying capacity essential to the durability of the walls.

Key takeaways

  • The vapour control membrane must always be installed on the warm side of the thermal insulation.
  • Any reversal of layers traps moisture in the insulation and causes damage through condensation.
  • SIA 180 requires verification that no water accumulates within the wall build-up.
  • Humidity-variable membranes allow summer drying towards the interior for walls closed on the outside.

Position the barrier on the warm side to prevent internal condensation

In building physics, water vapour naturally migrates from zones of high partial pressure to zones of low pressure, that is, from the heated interior to the cold exterior in winter. The fundamental rule for assembling a lightweight facade is to slow the vapour down before it reaches a cold zone where the drop in temperature triggers the dew point. Placing the vapour barrier or vapour retarder on the interior side, either directly against the insulation or separated by a technical void for service ducts, keeps the control layer above this critical temperature.

The thermal and hygrothermal design of building elements must prevent any harmful condensation within the material layers and ensure that their performance is maintained over the long term.

norme SIA 180
Hygrothermal behaviour of the lightweight facade layers from inside to outside
Position in the wallBuilding elementPhysical functionIndicative Sd value
1. Interior faceInterior finish or liningCladding and mechanical protectionVaries depending on the board
2. Immediately beneath the insulationVapour barrier or vapour retarderDiffusion control and airtightnessHigh or variable Sd
3. Core of the wallMineral or bio-based woolThermal resistance of the build-upVery low Sd (permeable)
4. Ventilated exterior faceBreathable rain barrierProtection against liquid water and wind-tightnessSd below 0.2 m

For the installation of window and door frames in the reveal, the principle remains the same: the interior connection strips must always have a higher resistance to vapour diffusion than the sealing strips applied on the exterior side. This hierarchy ensures that any accidental moisture penetrating the sealing joint can escape freely towards the air cavity or the exterior without stagnating at the fixings.

Choosing between a closed vapour barrier and a humidity-variable vapour retarder according to drying capacity

Drying capacity of the wall
The ability of a facade build-up to release, towards the interior or exterior, moisture trapped during construction or resulting from minor leaks, without damaging the insulation components.

The choice between a traditional vapour barrier with a fixed high Sd value and a vapour retarder depends entirely on the overall composition of the non-load-bearing envelope. In a conventional ventilated facade with a drained air cavity and a rain barrier that is highly open to vapour diffusion, a standard vapour retarder or a continuous vapour barrier provides perfect winter protection, since residual moisture is continuously removed by the exterior ventilation.

The situation changes as soon as the wall contains relatively vapour-tight outer layers, such as certain rigid bracing boards, direct metal cladding or elements under render. In this configuration, the trapped vapour cannot escape towards the exterior during the cold season. It then becomes essential to install a variable-permeance membrane on the interior side.

Variable-permeance membrane
Smart vapour retarder whose resistance to diffusion varies with the ambient relative humidity: closed in winter to block humid air from the dwelling, wide open in summer to allow the wall to dry out towards the interior.
  1. Identify the permeance of the outer faceCheck the technical data sheet of the exterior board or rain barrier to assess its Sd diffusion resistance.
  2. Calculate the drying potentialEnsure, in accordance with the requirements of SIA 180, that the annual moisture balance of the wall is strictly negative or zero.
  3. Select the appropriate membraneChoose an airtight vapour barrier if the outer face is ventilated, or a humidity-variable membrane if the outer face obstructs diffusion.
  4. Ensure continuity at the junctionsBond the overlaps and connections onto raw masonry using the adhesives and adhesive tapes of the system certified as airtight.

Execution of junctions and continuity of the airtight barrier

On the construction site, the failure of a vapour seal almost never originates from the membrane in the open field, but from the peripheral junctions and penetrations. According to SIA 180, the continuity of the envelope must be flawless to prevent flows of warm, humid air from entering the insulation build-up by convection. In winter, an infiltration of warm interior air carries considerably larger quantities of water than simple diffusion through a material. Installation requires a rigorous method, in particular at the junctions between the vapour retarder or vapour barrier and the structural work or window pre-frames.

  1. Preparation of mineral substratesThoroughly remove dust from concrete, brick or levelling renders in the reveal. Apply a suitable bonding primer before applying beads of paste adhesive or butyl adhesive tapes. The substrate must be dry, free from frost and free from release oil.
  2. Laying the strips and overlapsUnroll the strips horizontally or vertically with a minimum overlap of 10 cm. Always press down firmly on the adhesive tape designed for the membrane to expel air bubbles and activate the adhesive under mechanical pressure. Never settle for simple stapling onto battens without bonding.
  3. Connection to window pre-framesEnsure an airtight connection on the warm side of the frame or pre-frame using a pre-adhesive connection strip or a dedicated membrane with a plaster-key mesh edge. Provide an expansion loop to absorb differential movements of the structure.
  4. Treatment of technical penetrationsSeal every duct, electrical conduit or frame tie with pre-formed EPDM sleeves fitted with a self-adhesive collar. Any improvised penetration without an airtight gasket locally compromises the drying capacity of the wall.

Hygrothermal behaviour and operational selection criteria

The choice between a fully airtight vapour barrier membrane (very high fixed Sd value) and a variable-permeance vapour retarder depends on the nature of the outer layers and the possibilities for moisture to escape. In a ventilated facade closed to the exterior by low-permeability boards, or when insulating from the inside on existing masonry, the wall must absolutely retain a drying capacity directed towards the interior environment in summer. A humidity-variable membrane then sees its resistance to diffusion fall under the effect of high relative humidity, allowing the water retained in the insulation to evaporate into the heated room.

Decision aid for positioning membranes on the warm side
Facade configurationOuter layerPrescribed membrane typePredominant drying direction
Standard ventilated lightweight facadeAir cavity + open rain barrier (Sd < 0.2 m)Standard or humidity-variable vapour retarderTowards the exterior through the ventilated air cavity
Thermal renovation from the insideHistoric rendered or stone masonry wallVariable-permeance membrane mandatoryTowards the interior in summer
Room with high interior humidity (swimming pool)Any type of claddingContinuous metallic vapour barrier (Sd > 1500 m)Total blocking on the warm side, external drying only
Lightweight facade with airtight compact claddingBonded composite panels without ventilationWide-range humidity-variable vapour retarderStrictly towards the interior environment

For the proper execution of the work, the installation team must ensure that the materials are not exposed to direct weather on the construction site before the cladding is closed. The presence of liquid water trapped behind an airtight sheet causes rapid fungal problems, which the drying capacity of the wall would take several seasons to eliminate. Compliance with the recognised rules of the trade requires a systematic visual check of the bonding before the interior finishing boards are installed.

Managing condensation damage and repairing the envelope

A positioning error of a water-vapour-tight membrane causes rapid and severe damage within the facade build-up. If a closed vapour barrier is inadvertently installed on the cold side of the insulation, interior moisture passes through the structure, crosses the thermal insulation and meets this cold airtight barrier. The vapour condenses there into liquid form, saturating the insulation boards, drastically reducing their thermal resistance and causing mould.

As soon as traces of moisture appear at the fixings, characteristic odours or sagging of the insulation, the installation team must carry out targeted destructive testing. The technical protocol requires locally removing the exterior cladding, opening the rain barrier and taking moisture-content readings with a pin-type moisture meter directly in the thickness of the insulation and the secondary frames.

  1. Removal of wet elementsRemove the water-saturated insulation and dispose of the incorrectly positioned membranes. No mineral or bio-based insulation that has lost its mechanical strength may be retained in the wall.
  2. Drying of the secondary structuresMeasure the residual moisture content of the rafters or counter-battens. Closing up may only take place after the moisture content has returned to the equilibrium tolerances defined by the rules of the trade.
  3. Reinstatement of the airtight layerInstall a variable-permeance membrane or a suitable vapour retarder exclusively on the warm side of the insulation, with systematic adhesive bridging onto the structural work.

SIA 180 governs thermal protection and protection against moisture in buildings. In the event of an identified non-conformity compromising the building physics, art. 365 CO requires the contractor to inform the client if any circumstance compromises the proper or timely execution of the work. If a serious fault endangers safety, art. 229 CP punishes anyone who intentionally breaches the rules of the building trade.

Frequently asked questions

Why must an airtight vapour barrier on the outer face of thermal insulation be prohibited?

In winter, water vapour migrates from the heated interior environment towards the exterior under the effect of partial pressure. Positioned on the cold side, the vapour barrier blocks this vapour at the point where the temperature reaches the dew point. The water then condenses directly within the thickness of the insulation, causing its permanent thermal degradation, rotting of the timber substructures and accelerated corrosion of the metal angle brackets.

In what situation is a variable-permeance membrane technically indispensable?

The humidity-variable membrane is required when the wall's drying capacity towards the exterior is limited or non-existent, notably when insulating from the inside on dense masonry or beneath poorly ventilated metal cladding. In winter, it closes its pores to block interior moisture. In summer, as the facade warms up, it opens to allow trapped moisture to evaporate into the ventilated interior space.

How should the vapour retarder connection be treated at windows installed in the reveal?

The interior vapour retarder membrane must be connected airtight to the perimeter of the window frame using a specific vapour retarder adhesive tape or a dedicated solvent-free cartridge adhesive. An expansion fold of at least twenty millimetres should be provided in the corners to absorb the differential movements of the building and ensure continuous adhesion without any tension on the substrate.

What should be done if new mineral insulation has been exposed to condensation due to a reversal of layers?

The installation of an incorrectly positioned barrier requires the defective build-up to be removed. Any mineral wool mat whose fibres have compacted or disintegrated under the effect of liquid water must be removed from the construction site and replaced. It is prohibited to enclose wet insulation behind a new membrane without having checked that the underlying frame has a moisture content compatible with SIA 180.

Texts and standards cited

  • SIA 180Thermal protection and protection against moisture in buildings
  • CO art. 365materials and ground: the contractor is responsible for the good quality of the materials he supplies; if the materials supplied by the client or the ground designated by him are found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3)
  • CP art. 229breach of the rules of the building trade: anyone who, while directing or carrying out a construction or demolition, intentionally breaches the rules of the trade and knowingly endangers the life or physical integrity of persons faces a custodial sentence of up to five years or a monetary penalty; if through negligence, up to three years or a monetary penalty