Key takeaways
- A heavily insulated envelope blocks interior heat and lowers the temperature of the external render.
- Night-time radiation causes continuous surface condensation, which favours the growth of algae and fungi.
- The absence of a roof overhang and the presence of trees considerably increase the local moisture input.
- The contractor must record regular maintenance as a normal operating cost of the delivered building.
The physics of the insulated façade and the night-time condensation mechanism
On old, uninsulated masonry, the heat flow passing through the wall continuously warmed the external rendering. This energy loss had a direct drying effect, limiting the time liquid water remained on the facing. With the installation of modern external insulation, this heat flow is cut by 80 to 90%. The finishing layer, made up of a thin reinforcing mortar and a render a few millimetres thick, has a very low thermal capacity. It is thermally decoupled from the mass of the building.
During the night, under a clear sky, the outer surface of the render radiates heavily towards the sky. This night-time undercooling phenomenon lowers the temperature of the render below the ambient air temperature, often by 2 to 4 kelvins. As soon as this surface temperature drops below the dew point of the outside air, the ambient moisture condenses directly on the façade. The water remains present as a liquid film for many hours, creating the nutrient medium essential for the germination of micro-organisms.
- Night-time undercooling
- Lowering of the temperature of an external surface below the ambient air temperature, caused by long-wavelength thermal radiation emitted towards a clear, open sky.
North and north-west orientations accentuate the problem dramatically: the façade receives no direct solar radiation during the morning to evaporate this water film. The daily duration of surface wetting there is three to four times longer than on a south façade. Moreover, the immediate proximity of deciduous trees, living hedges or bodies of water alters the local microclimate by keeping relative humidity constantly high while continuously dispersing plant and fungal spores onto the walls.
Roof overhangs, limits of additives and contractual maintenance protocol
The evolution of contemporary architecture has made flat roofs without eaves and clean parapet copings widespread. Yet a traditional roof overhang performs two major protective roles: it mechanically protects the upper two thirds of the wall against driving rain and it reduces the solid angle of view towards the sky, which slows night-time undercooling. Removing the overhang amounts to exposing the entire façade cladding to direct weathering and maximum cooling.
| Constructional or environmental factor | Impact on the insulated façade | Preventive measure during execution |
|---|---|---|
| Roof overhang greater than 40 cm | Protection against rain and limitation of night-time radiation | Recommend the eaves during coordination meetings |
| Flush parapet coping | Direct run-off of laden water and maximum cooling | Provide a drip edge with a clean drip projecting 30 mm |
| Tall vegetation within 3 metres | Permanent shading and continuous input of organic particles | Record the pruning of plantings in the building file |
| Thin organic render | Low thermal inertia and slowed surface drying | Prefer a thick mineral render with high capillary absorption |
Modern render formulations incorporate encapsulated biocidal and fungicidal agents intended to delay algae proliferation. However, the contractor must never guarantee a façade free of soiling over a period of several years. These active chemical substances are water-soluble; they are gradually depleted by leaching under the repeated action of rainwater. Depending on the severity of exposure to the weather, the chemical surface protection loses most of its effectiveness after a period of three to six years.
To avoid becoming involved in a dispute when green or red algae first appear, the site manager must formalise the required maintenance plan in writing, from the tender phase or at the handover of the work. It should be stated in black and white that the insulated façade requires regular gentle cleaning, without an aggressive high-pressure cleaner that would destroy the grain of the render, supplemented by the spray application of a suitable curative and preventive treatment solution. Surface maintenance is an integral part of the operational maintenance of the property.
Site and vegetation factors: analysing the microclimate of the building
The appearance of micro-organisms is not due to a defect in the external thermal insulation system, but to a strict combination of surface temperature and ambient moisture input. When a building is located at the edge of a forest, close to large deciduous trees or a watercourse, the concentration of spores and organic nutrients in the air increases considerably. These organic elements settle on the finishing layer. If the façade remains damp for several consecutive hours in the early morning because of night-time condensation, the germination of unicellular algae and filamentous fungi inevitably begins.
Exposure to prevailing rain-bearing winds and the lack of direct sunshine reinforce this phenomenon on north and west orientations. A vegetation screen less than five metres away prevents the thermal wind from drying the render and maintains a permanent zone of shade. In addition, trees shed pollen, resins and micro-droplets that form an ideal nutrient substrate for biomass. The façade contractor must note these particularities from the tender phase or during the preliminary technical visit, because no biocidal treatment in the render withstands a continuous input of liquid water indefinitely.
| Exposure factor | Physical effect on the façade | Biological risk level | Recommended preventive measure |
|---|---|---|---|
| North orientation without solar radiation | Very slow drying after dew condensation | High | Thick mineral render with high absorption capacity or a colour with low albedo |
| Dense vegetation within 3 m | Continuous shading and heavy spore fallout | Critical | Sanitary pruning or clearing of a peripheral ventilation corridor |
| Blind façade without eaves | Direct run-off of rainwater from above | Major | Coping sheet with a projecting drip edge of at least 30 mm |
| Proximity to an agricultural or wet area | Frequent morning fog and nitrogen-laden dust | High | Water-repellent siloxane finishing paint with reinforced protection |
The absence of a roof overhang is the main amplifier of this fouling. On contemporary flat-roof buildings, an attic storey without a setback directly exposes the top of the thermal system to precipitation and to radiative losses towards the sky. Rainwater runs down a render whose surface has cooled below the dew point during the night. Atmospheric soiling clings to the roughness of the grain of the organic or mineral render, creating the characteristic dark vertical streaks visible below poorly protected parapets.
Duty to inform and framing of warranties towards the client
Biological colonisation of an insulated façade is a natural process of surface fouling and not a defect within the meaning of Swiss contract law. However, an uninformed client equates the greenish or blackish discoloration with a failure of execution by the façade contractor. If the contractor has not documented this hygrothermal behaviour before the start of the construction site, he is exposed to unjustified payment withholdings or to contentious proceedings at the acceptance of the work under the SIA 118 standard.
To protect himself against abusive claims, the contractor applies the duty to notify provided for in art. 365 CO para. 3 by notifying site management in writing of the risks inherent in the absence of constructional protection or in the immediate proximity of tall-stemmed trees. This notification must specify that external insulation drastically reduces the heat flow coming from the inside, keeping the external render at very low temperatures that favour reaching the dew point.
- State explicitly in the tender and in the works contract that biological soiling constitutes an aesthetic alteration of environmental origin and not a material defect.
- Remind the client that the rights for defects in the work under art. 368 CO do not cover the natural accumulation of particles or micro-organisms resulting from the weather conditions of the site.
- Hand over a periodic maintenance plan recommending gentle low-pressure cleaning with hot water every three to five years, followed by the application of a no-rinse preventive sanitising agent.
- Propose a façade maintenance contract from the outset to schedule the washing cycles and renew the finishing layer before the micro-organism becomes embedded in the binder.
By formalising this protocol from the tender, the site manager turns a potential technical dispute into a predictable maintenance service. The client understands that the exceptional energy performance of his building requires a maintenance routine similar to that of a roof or a technical installation, ensuring the durability of the investment without legal recourse.
Fouling dispute: how to respond to the client's complaint
When greenish or blackish traces appear two to three years after acceptance of the work, the client almost systematically alleges a material defect or an application fault in the mineral or synthetic render. The façade contractor's first reaction determines the entire outcome of the case: rejecting the complaint outright without a physical explanation antagonises the client, whereas admitting a fault in execution creates a heavy financial precedent. According to CO, the client notifies defects to the contractor after delivery. Faced with this notification, the site manager must absolutely arrange a joint inspection record on site before setting up any scaffolding or carrying out any chemical treatment.
- Survey of the microclimate and special featuresSystematically check the orientation of the façade section in question, the immediate proximity of dense plantings keeping humidity high within five metres, and the absence of a protective roof overhang. Carefully check the condition of the parapet copings, drip edges and window sill flashings in order to rule out any concentrated run-off of dirty water from poorly installed sheet-metal work.
- Microscopic examination of the surfaceTake an adhesive-tape sample from the greened area in order to characterise the cryptogamic colonisation. Check with a workshop magnifying glass that the finishing render film shows no crazing, blistering or detachment of the reinforced base coat, proving that the system retains its full mechanical cohesion.
- Verification of maintenance evidenceCompare the situation of the work with the maintenance protocol formally handed over at acceptance. If the client refused the recommended periodic cleaning, CO applies to dismiss his claims where the aesthetic damage results directly from failure to follow the usage recommendations provided at handover of the work.
- Amicable remediation protocolPropose a suitable curative protocol comprising the controlled spraying of a certified biocide, a sufficient residual period, then manual brushing or rinsing with tempered water at a pressure strictly limited to less than 30 bar, absolutely avoiding destruction of the surface texture of the render.
Frequently asked questions
Is high-pressure cleaning acceptable for removing algae from a façade render?
An industrial high-pressure cleaner is strictly prohibited on external insulation with a thin render. A rotary nozzle or a pressure above 30 bar destroys the surface grain, tears out the binding resin and creates microcracks that promote future liquid ingress. The proven method consists in spraying a residual algicidal biocide solution, leaving it to act according to the technical data sheet, then rinsing gently at low pressure with a soft brush.
Do so-called water-repellent or beading paints permanently prevent greening?
No façade paint or finish provides permanent protection. Silicone resins or beading-effect paints reduce the adhesion of surface water and slow the rate at which micro-organisms settle. However, the encapsulated biocidal fillers degrade under ultraviolet rays and are gradually leached out by driving rain over five to eight years. Without regular preventive maintenance or management of the surrounding moisture, spores inevitably recolonise north façades.
What distance should be kept between vegetation and the façade to limit fouling?
A minimum distance of three to five metres between the insulated façade and tree crowns or dense shrub beds is technically recommended. Plants maintain a very high relative humidity through evapotranspiration, block the circulation of drying air and throw cryptogamic spores at every gust of wind. Pruning branches that are too close and removing climbing plants growing directly on the wall lets sun and breeze speed up the evaporation of condensation.
Does the colour of the finishing render have a direct impact on algae formation?
Yes, the colour plays a key thermal role. Dark colours have a low solar reflectance index and store more energy during the day, which delays condensation at dusk but increases mechanical stresses. Conversely, a very white render absorbs little daytime heat and undergoes faster night-time undercooling, favouring the presence of liquid water on the surface. The façade contractor must find a colour compromise that respects the prescribed light reflectance value.
Texts and standards cited
- COafter delivery, the client checks the condition of the work as soon as is customary in the ordinary course of business and notifies defects to the contractor; for a work on an immovable, he has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2).
- COexclusion of the client's rights for defects in the work where the defective execution is personally attributable to him (instructions given contrary to the contractor's formal warnings or any other cause).