🧱 CFC 221Blinds, shutters and solar protectionChapter 1 of 10 in the section

Blind box: the recess is decided before the structural work, not after

A missing blind box recess blocks the installation of the window frames and causes major extra costs on the structural work. This chapter specifies the critical dimensions to pass to the civil engineer before concreting, the thermal management of the lintel soffit and the clearances essential for maintaining fabrics and motors without damaging the façade.

Key takeaways

  • Pass the stack heights and depths to the civil engineer as early as the formwork drawings.
  • Provide a minimum clearance of 130 to 160 mm in depth, depending on the product selected.
  • Place a high-performance rigid insulation at the back of the rebate to stop the thermal bridge.
  • Ensure a removable soffit access without damaging the render or the reveals during servicing.

Recess dimensions and coordination with the structural work in the schedule

A blind box cannot be improvised once the concrete slabs have been poured. If the recess is not included in the reinforced-concrete execution drawings given to the formwork crews, the façade contractor and the joiner face a penalising choice: chipping out a load-bearing lintel to house the mechanism set back — an operation that destroys the cover to the reinforcing steel and requires a calculation note from the civil engineer — or falling back on a visible box fixed on the surface of the render. This solution spoils the architectural line and reduces the glazed area accordingly. Anticipating the exact dimensions is therefore an unavoidable technical requirement during the final design phase. The sizing of the box depends directly on the type of slats, their thickness, the stacking method and the total developed height of the window.

Coordination between trades means locking in the choice of blind supplier well before the elements are actually ordered. Each manufacturer has different stack dimensions for an identical opening height. Fixing unverified average dimensions exposes the construction site to unsuitable end stops or to slats compressed in a box that is too narrow.

  1. Definition of the solar-shading modelFinalise the product precisely (linked-slat blinds, blackout slats or screen fabrics) and calculate the actual stack height from the manufacturer's charts for the opening height concerned.
  2. Issue of the detailed recess drawingsSend the site management and the civil engineer a detailed section specifying the rough built-in dimensions: depth, recess height and reveal returns.
  3. Check of the transfer to the formwork drawingsCheck the accuracy of the rebates, drops and lintel heads on the civil engineer's drawings before the reinforcement is fixed and the masons pour the concrete.
  4. Geometric acceptance on the raw slabCheck the dimensions with a laser distance meter as soon as the façade elements are stripped, so as to correct any misalignment before the insulation work begins.
Usual rough recesses for external façade blinds
Type of solar shadingStandard opening heightUsual stack heightMinimum recess depth
Linked slats 80 mmUp to 2500 mm220 to 260 mm130 mm
Blackout slats 90 mmUp to 2500 mm260 to 300 mm140 mm
Fabric blind with zip guideUp to 3000 mm110 to 150 mm120 to 150 mm
Aluminium roller shutterUp to 2400 mm180 to 210 mm160 to 180 mm

Controlling the thermal bridge and preserving maintenance access

Hollowing out a recess in the structural work reduces the thickness of the concrete and brings the cold outer surface closer to the heated interior space. Without a compensating measure, this reduction in thickness creates a major linear thermal bridge at the junction between the lintel and the window frame. The physical consequences are immediate: lower interior surface temperature, winter condensation and mould growth behind the linings. To meet the thermal protection requirements of standard SIA 380/1, the back of the recess must receive a rigid insulation board of high thermal performance, most often polyurethane or phenolic foam, with a minimum thickness of 30 to 50 mm.

Preserving maintenance access is the second design imperative. Tubular motors, guide bearings and slat fixings wear over time and must be removable without damaging the render or cutting façade profiles. The underside of the box must be closed by a sheet or aluminium profile that can be removed from below. The fixing screws of this soffit must remain visible and accessible with a screwdriver or magnetic bit, and must not be covered by a return of façade render or by a waterproofing flashing.

  • Do not apply mineral or synthetic render to the removable soffit of the box.
  • Keep a continuous vertical clear space under the recess to extract the shaft and the complete stack.
  • Ensure airtightness with a compressed flexible seal that does not adhere to the removable faces.
  • Run the electrical connection conduits outside the drilling zones of the support brackets.

Consequences of a missed recess: reworking the lintel or switching to a surface-mounted box

The absence of an integrated recess approved before the slab or lintel is poured puts the site management in a constructional dead end. Once the reinforcement and concrete are in place, creating a recess afterwards requires heavy structural intervention. Sawing or chipping reinforced concrete on the lintel soffit directly affects the load-bearing steel and the required cover, which requires the formal agreement of the civil engineer and weakens the thermal insulation of the upper junction. Such rework generates disproportionate masonry repair costs and delays the installation of the external joinery.

If structural sawing is ruled out to preserve the static integrity of the structural work, the only alternative is to abandon the recessed box in favour of a surface mounting on the exterior or under a lintel with no recess. This change in execution alters the appearance of the façades approved at the public inquiry and disturbs the coordination of the envelope layers: the metal box then encroaches directly on the visible glazing opening or requires an additional thickness of external insulation not provided for in the execution file.

Comparison of remedial solutions if the recess is omitted in the structural work
Remedial optionImpact on the clear openingThermal bridge and envelopeMaintenance constraint
Rework by sawing the concretePreserved (transom height kept)High risk of linear thermal bridge; residual insulation thickness greatly reducedCompliant access from the soffit depending on the geometry of the recreated box
Installation under the lintel in the revealReduction of 180 to 280 mm depending on the height of the slat stackContinuous insulation kept on the façade, but a thermal adaptation profile is needed on the frameDirect removal of the solar shading from the external reveal without a dedicated hatch
Surface mounting on the façadePreserved (box placed above the lintel, projecting)Break in the flatness of the render or cladding; thermal bridges at the bracket anchoragesDirect access through a removable front face, increased exposure to the weather

Prescribing the interfaces in the schedule and slab inspection protocol

The approval schedule tolerates no slippage. The detailed recess drawings must be sent to the civil engineer and the masonry contractor before the final issue of the formwork drawings. The façade contractor and the joiner must fix the usable recess depth according to the solar shading selected (linked-slat blinds, zip fabric blinds or aluminium roller shutters), adding a tolerance allowance for the base render and any insulation board under the lintel. Under art. 365 CO para. 3, if a circumstance attributable to the data supplied jeopardises the proper or timely execution of the work, the contractor informs the client.

  1. Setting-out check of the concrete provisionsOn the stripped slab, check the setback of the concrete nosing from the outer alignment of the raw façade, the seating level of the lintel and compliance with the rough recess depth.
  2. Check of the rear thermal barrierMake sure that the rigid insulation at the back of the box is present and continuous before the window frames are installed, to prevent any interior condensation along the lintel.
  3. Validation of the maintenance clearancesCheck that the free space on the underside allows the winding shaft to be lowered or the motor mechanism to be unhooked without having to tear out the finished reveal or the ventilated façade cladding.
  4. Marking of cable routesMark the exit of the airtight electrical conduit in the upper corner of the recess, outside the pivoting range of the slats and the supporting brackets.

Preserving maintenance access remains the condition for a durable structure. Any box recessed under external thermal insulation (ETICS) or behind a ventilated cladding must have a removable soffit of a width equal to the rough recess. In the event of a seized tubular motor or a broken fabric tape, the technician must be able to reach the linkage from the outside with simple hand tools, without damaging the waterproofing system or breaking the render returns.

Handling non-conformities: technical decisions and recess rework

When the concrete is poured without the required recess or with an insufficient size, the façade contractor immediately records the geometric deviation during the joint inspection on the slab. Wild picking or chipping of reinforced concrete is strictly prohibited: any modification of a load-bearing lintel affects the tension or shear reinforcement and absolutely requires the formal prior opinion of the civil engineer. If the latter refuses sawing for structural safety reasons, the site management must quickly decide between an aesthetic compromise on the façade and an adaptation of the closure system.

Treatment options in case of a non-conforming recess
Remedial scenarioTechnical impactArchitectural and financial consequences
Lintel rework by sawingCivil engineer's approval required; reinforcement checked with a cover meter.High cost of structural rework; original alignment of the blinds maintained.
Switch to surface mounting under the lintelFixing in the reveal or on an enlarged frame; reduction of the residual insulation thickness.Net loss of clear opening (100 to 160 mm); aluminium band visible on the façade.
Change of mechanismReplacement of the linked slats by a vertical fabric blind or flat slats.More compact folded stack; change in blackout and wind-load performance.

In the event of a switch to a surface-mounted box under the lintel, the geometric change directly affects the external joinery. If the frame has not yet been machined in the workshop, the estimator adjusts the overall height of the frame by inserting an upper extension profile to fix the box without cutting into the glazing. If the window is already manufactured or installed, the box inevitably encroaches on the clear opening, creating a visual break inside. Thermally, the absence of a recess often eliminates the insulation at the back of the recess; applying a thin insulation board based on resol foam or aerogel remains the only solution to limit the linear thermal bridge and prevent corner mould.

Frequently asked questions

Is chipping out a concrete lintel with a chisel permissible to recess the blind?

No, unauthorised chipping of a reinforced concrete lintel is strictly prohibited. The shear forces and bending moment at the openings engage the bottom reinforcement and the stirrups located a few centimetres from the formwork face. Only the civil engineer responsible for the structure may authorise core drilling or partial sawing after recalculating the residual steel sections. Any uncertified weakening endangers the stability of the façade.

What tolerance margin should be allowed on the rough recess depth?

The rough recess depth must exceed the nominal width of the blind stack by at least 20 mm. For a 90 mm linked slat requiring 130 mm of usable depth, allow a rough recess of at least 150 mm. This clearance absorbs the execution tolerances of the structural work and preserves the space required for the rear insulation board at the back of the box, which ensures the continuity of the building's thermal envelope.

How should the thermal bridge be treated if the insulation thickness at the back of the box is reduced?

When the recess depth is insufficient to house standard mineral wool, replace it with a material of very low thermal conductivity such as vacuum panels or silica aerogels. A thickness of 20 to 30 mm of this type of high-performance insulation thermally compensates for 60 mm of conventional insulation, avoiding a lowering of the dew point on the inner face of the lintel and the risk of winter condensation.

Who bears the adaptation costs if the structural work omits a recess?

The financial burden depends on the contract documents and the approved schedule. If the blind contractor sent the recess drawings within the agreed deadlines and the masonry company omitted the recess, the adaptation costs fall on the structural work. Art. 97 CO provides that the debtor is liable to compensate the damage resulting from non-performance of an obligation, unless he proves that no fault is attributable to him.

Texts and standards cited

  • CO art. 97non-performance of the obligation: the debtor is liable to compensate the damage, unless he proves that no fault is attributable to him.