Key takeaways
- Always schedule the intermediate airtightness test before the interior cladding and linings are fitted.
- Seal the ventilation openings rigorously while leaving the sealing gaskets of the external windows intact.
- Distinguish the overall air change rate n50 from the surface air permeability q50 relative to the envelope.
- Track down air leaks at window connections under a continuous negative pressure of fifty pascals.
Define the phasing of the Blower Door test and prepare the building
A blower door test carried out only at the final acceptance stage gives a cold finding: it quantifies the overall leaks without allowing them to be repaired at the lowest cost. For the facade installer and the joiner fitting in the reveal, the connections of the airtightness barrier — adhesive tapes around the perimeter of the subframe, vapour-control membranes connected to the structural work, threshold seals under the subframe — become invisible and inaccessible as soon as the sills, plasterboard reveals or interior renders are installed. The construction site schedule must therefore include two separate test campaigns.
| Test stage | State of the works | Technical objective | Accessibility for rework |
|---|---|---|---|
| Intermediate test (on site) | Glazed windows installed, membranes bonded to the structural work, interior cladding not yet fitted | Direct location of leaks using a thermo-anemometer and artificial smoke | Full: immediate rework of adhesive tapes, sealants and sealing work |
| Final test (acceptance) | Building fully completed, finishes installed, technical installations connected | Certification of overall contractual compliance or of the targeted energy standard | None or very costly: heavy removal of linings required in case of failure |
Preparing the building for the intermediate test determines the validity of the measurements. According to SIA 180, the airtight envelope must be continuously closed. Intentional openings linked to mechanical ventilation, kitchen extractor hoods and sanitary outlets must be sealed hermetically using inflatable bladders or airtight adhesive films fixed over the vents. On the other hand, the elements within the facade installer's supply and installation scope must not be temporarily sealed: the closing gaskets of opening sashes, fixed glazing, French-window thresholds and integrated blind boxes must be tested in their final configuration of use.
- Checking windows and hardwareCheck the mechanical adjustment of the sashes. A sash that is not properly compressed against its perimeter gasket distorts the overall result. Lock all windows with the handle.
- Neutralising temporary openingsTemporarily seal the passages of temporary electrical conduits or pipes crossing the external walls that are not yet fitted with their final airtight sleeves.
- Setting up the blower doorInstall the adjustable frame and the Blower Door sheet in an external door or an opening leading outdoors, ensuring that the frame is perfectly sealed against the door frame.
Read the permeability values and classify the defects
The device depressurises and then pressurises the interior volume at various pressure steps generally graduated between ten and sixty pascals. The software plots a characteristic curve from which the leakage flow rate at a pressure difference of fifty pascals is extracted (V50, expressed in cubic metres per hour). To analyse this flow rate, two reference quantities are used in accordance with the requirements of SIA 180 and Swiss construction standards.
- Air change rate n50 [h⁻¹]
- Quotient of the air leakage flow rate at 50 Pa (V50) divided by the heated interior air volume (V). It indicates how many times per hour the complete air volume of the building is renewed by parasitic infiltration at this pressure difference.
The n50 rate serves as the main indicator for the whole thermal volume. For mechanically ventilated buildings, SIA 180 sets strict limit values, commonly between 1.0 h⁻¹ and 1.5 h⁻¹ depending on constructional complexity, while high-performance labels often require an n50 of less than or equal to 0.6 h⁻¹ or 0.8 h⁻¹ for new buildings. However, for the external joinery and facade company, the surface ratio q50 (leakage flow rate relative to the envelope surface AT) or qL50 (flow rate relative to the length of window joint) is often more representative for judging the quality of the reveal installation.
| Indicator | Unit | Usual target range (building with mechanical ventilation) | Finding for the facade / windows package |
|---|---|---|---|
| Rate n50 | h⁻¹ | ≤ 1.0 to 1.5 | If n50 > 1.5: immediately check the subframe-masonry connections and the opening thresholds. |
| Permeability q50 | m³/(h·m²) | ≤ 0.6 to 1.2 | Allows the intrinsic airtightness of the facade surfaces to be measured independently of the interior volume. |
| Minergie-P requirement (reference) | h⁻¹ | ≤ 0.6 | Requires impeccable airtightness of every flashing connection, blind box and glazing joint. |
During the phase of constant negative pressure at fifty pascals in the intermediate test, the team leader inspects all the external windows with a cold smoke generator or a hot-wire anemometer. The recurring critical points are concentrated under the window sills (failure of the lower connection seal), at the upper corners of the subframes (poor pressing-on of the preformed sealing tape) and at the junction between the blind box and the lintel. If the works show an execution defect attributable to the contractor, art. 366 CO allows the client to demand the necessary repairs during the works. Immediate rework with compatible hybrid sealant or re-bonding of a connection sleeve can thus be carried out without demolishing the interior fittings.
Investigation under negative pressure: tracking down infiltration at windows and membranes
Measuring the overall leakage flow rate with the blower door gives only a raw quantitative result. For the facade installer and the joiner, the operational value of an intermediate test lies in the qualitative phase: keeping the volume under a constant negative pressure of 50 Pa in order to identify, point by point, every parasitic air path before the plasterboard linings, interior sills or reveal cladding conceal the interface with the masonry or concrete.
- Maintaining the stable negative pressure stepThe fan is set manually or by software to 50 Pa of negative pressure. This value is sufficient to overcome natural thermal draughts and create an inflow of air that is easily perceptible on the airtight envelope without placing excessive stress on the temporary site bonding.
- Inspection with smoke puffer and fog generatorThe technician applies a thread of cold smoke along the adhesive beads connecting the frame to the structural work, at the subframe corners and at the installation shims. Any deviation or instant dispersion of the smoke shows a local break in the vapour barrier film or a lack of compressible sealant.
- Spot speed measurement with a thermal anemometerA hot-wire anemometer makes it possible to quantify the local air speed at integrated blind guides, French-window thresholds or profile corner junctions. An infiltration speed exceeding 0.5 m/s indicates an assembly defect or a detached membrane connection.
- Coupled infrared thermographyIf the temperature difference between inside and outside reaches at least 5 to 10 K, the thermal camera immediately reveals the tongues of interior cooling caused by the suction of cold outside air along the frame bases or under the window sills.
| Location of the defect | Manifestation at 50 Pa | Execution cause on the construction site | Corrective action required |
|---|---|---|---|
| Lower corner frame / masonry | Thread of smoke drawn in under the interior sealing membrane | Poorly pressed-on fold of the adhesive tape or lack of adhesion on dusty concrete | Cleaning, application of an adhesion primer and fitting of a preformed corner sleeve |
| Threshold of lift-and-slide French window | Clear linear temperature drop and air flow at floor level | Discontinuity of the sealant under the adjustment shoe or failure of the sealing strip | Targeted pressure injection of a hybrid polymer and rework of the sealed connection |
| Junction of upper transom and blind box | Sweep of cold air entering the cladding slot | No airtightness seal between the back of the box and the lintel soffit | Fitting of a backing rod and extrusion of an elastomer sealant with bonded vapour-control tape |
| Electrical cable passage for blind motor | Localised air jet through the supply conduit | Corrugated conduit crossing the envelope without an airtight cable sleeve | Fitting of an EPDM cable grommet with elastic clamping or an interior sealing plug |
Treatment of interfaces and remediation protocols before cladding
As soon as the intermediate report reveals an air change rate that does not meet the project requirements or the reference values of SIA 180, the intervention must be strictly limited to the building elements of the facade installer and the joiner. Any attempt at sealing by third parties that would mask the defects without durability must be formally excluded.
- Traceability of rework: Any correction to a vapour-control membrane or adhesive tape is recorded by precise photographic marking with the window reference number before covering.
- Chemical compatibility of components: The exclusive use of solvent-free adhesives and tapes certified airtight in accordance with the window manufacturers' instructions prevents premature detachment under thermal stress.
- Checking the installation of fixing brackets: Heavy metal anchors passing through the sealing plane must each be covered by cut adhesive pieces or coated with an airtight paste.
- Removal of test seals: The temporary seals made for the purposes of the test (ventilation plugs or covered air vents) must be removed with care so as not to tear off the adjoining membranes.
The airtightness layer must be planned and executed continuously over the entire thermal envelope of the building. The connections between the different building elements must be designed to withstand durably the foreseeable mechanical and climatic stresses.
Norme SIA 180
The formal lifting of airtightness reservations is carried out by a targeted retest under pressure difference. Once compliance has been validated by the measurement report, the site manager transmits the formal approval for cladding to the other trades. This technical milestone releases the external joinery company from responsibility for the integrity of the airtightness barrier before the plasterers and painters intervene, in accordance with the general rules of the Code of Obligations (CO) on the inspection of the work.
Management of air-tightness non-conformities and rework protocol before lining
When the raw result exceeds the limit value set by the project or by SIA 180, the immediate stop of interior cladding work is required. Discovering non-compliant permeability at the finishing stage turns a simple rework into a major loss: the lining hides the leaks without ever blocking the air. If the airtight envelope remains accessible, the measured result is not a definitive failure but the starting point of a methodical locating phase.
- Diagnosis under sustained pressure differenceThe technician stabilises the blower door at a constant negative pressure of 50 Pa. The facade installer and the joiner go over all frame perimeters, thresholds and vapour-control connections with a hot-wire anemometer or a smoke puffer to make the air streams visible.
- Classification and attribution of infiltrationThe leaks are mapped on the plan: bonding defects on masonry, penetrations by other trades, omitted corner sealant on subframes or insufficient compression of the closing gaskets on sashes. Each defective singular point is marked directly on the substrate.
- Mechanical and chemical treatment of discontinuitiesRework excludes any surface filling with plaster. The joiner readjusts the sash hardware. The facade installer applies sealing sleeves suited to the through-sleeves, re-bonds peeled adhesive tapes using an adhesion primer and injects a continuous bead of elastomer adhesive under the detached strips.
- Immediate validation countermeasureA second pressure sweep is carried out straight away, before any removal of the measuring equipment, to validate that the air change rate has dropped below the contractual threshold.
In the event of a dispute between trades over the origin of the leaks, art. 367 CO governs the inspection of the work and the notice of defects. The contractor requires an intermediate report recording the intermediate n50 values before authorising the plasterers to close the partitions.
Frequently asked questions
What should be done if the final test fails although the intermediate measurement was compliant?
This discrepancy indicates a subsequent alteration of the airtight barrier. Finishing work carried out after the provisional test is a frequent cause: puncturing of the vapour-control layer by electricians, fixing of plasterwork rails without an airtight resilient strip or damage to the window seals in the reveal. The building must be put under negative pressure again to target the recent penetrations and to require restoration by the trades that intervened.
How can a leak at the subframe be distinguished from an intrinsic defect of the window?
The investigation is carried out at 50 Pa with a smoke generator and a local negative-pressure bell. If the smoke escapes between the frame and the masonry, the connection membrane or the perimeter bead shows a discontinuity attributable to installation. If the infiltration appears at the corners of the sashes, at the glazing beads or at the glass-profile junction, the defect relates to the manufacture of the frame, the adjustment of the espagnolettes or the crushing of the sealing gaskets.
Which ventilation elements must absolutely be sealed during preparation?
In accordance with the measurement protocol, only the intentional openings linked to air renewal are sealed: kitchen extraction vents, hygienic supply air, combustion air supply ducts of stoves and primary ventilation openings of waste-water stacks. All external doors and windows remain closed but not masked with adhesive tapes. Floor traps must absolutely be filled with water to avoid residual false air entries.
What is the impact of a result expressed in q50 rather than n50 on the acceptance of the envelope?
The n50 value expresses the hourly air change rate relative to the net interior volume of the building in cubic metres. The q50 value divides the leakage flow rate by the total surface of the thermal envelope in square metres. In large buildings or industrial halls with a large volume, n50 sometimes masks severe local leaks on the facades. SIA 180 favours a cross-reading adapted to the type of construction.
Texts and standards cited
- SIA 180Thermal protection, moisture protection and indoor climate in buildings
- CO art. 367after delivery, the client checks the state of the work as soon as it is able to and notifies the contractor of the defects; for an immovable structure, it has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2).