Survey the opening before ordering: dimensions, plumb and installation clearances

This chapter details the rigorous method for measuring a raw masonry opening before manufacture is launched. You will be able to apply the systematic three-point survey, determine the deductions for sealing clearances according to the permitted tolerances, and formally identify the structural work defects that justify halting an order.

Key takeaways

  • Systematically measure each opening at three separate points for the width, the height and the diagonals.
  • The SIA 414 standard governs the permissible deviations on raw structural work before installation.
  • Deduct the peripheral installation clearance to ensure continuous sealing and allow for frame expansion.
  • Report in writing any excessive out-of-plumb or out-of-square condition before approving manufacture.

Take the raw dimensions and check the geometry of the opening

The manufacture of external joinery is based on the actual geometry of the raw opening. On the construction site, no concrete or masonry wall is perfectly straight or perfectly square. The classic mistake is to take a single measurement in the middle of the opening and launch production in the workshop. This practice inevitably leads to joinery that is too large and jams during insertion, or too narrow to ensure compliant and durable sealing.

The professional protocol requires a three-point survey for each dimension. For the width of the opening, the façade installer systematically measures at the bottom (100 mm from the sill), in the centre and at the top (100 mm below the lintel). For the height, the measurement is taken 100 mm from the left jamb, in the centre, then 100 mm from the right jamb. The manufacturing dimension never uses an arithmetic average: it is established exclusively from the smallest of the three measured values, for both width and height.

  1. Measuring widths and heightsTake the dimensions with a rigid tape measure or a calibrated laser distance meter at three spaced points per axis. Record the minimum dimensions on the cutting sheet.
  2. Checking the diagonalsMeasure both diagonals of the opening from corner to corner. A difference between the two values reveals an out-of-square condition of the structural work.
  3. Checking levels and plumbCheck the level of the masonry sill and the plumb of the reveals using a two-metre straightedge fitted with a spirit level or a rotating laser level.
Dimensional tolerances of structural work applicable to openings according to SIA 414
Nominal dimension of the openingRaw opening tolerancePermissible out-of-plumb deviationMax. difference between diagonals
Up to 1.00 m± 10 mm6 mm8 mm
From 1.01 m to 3.00 m± 12 mm8 mm10 mm
More than 3.00 m± 16 mm12 mm15 mm

Determine installation clearances and reject a non-compliant substrate

The peripheral installation clearance is the free space left between the window frame and the raw masonry. This gap fulfils three essential technical roles: absorbing the thermal expansion of the profiles (particularly pronounced on aluminium and dark PVC), allowing three-dimensional adjustment of the frame during mechanical fixing, and housing the sealing system. This system comprises the backing rod with elastomeric sealant or the impregnated pre-compressed tape.

As a general rule, the side and head installation clearance must be 10 to 15 mm on concrete or regular brick substrates. A clearance of less than 8 mm prevents the application of a compliant sealing bead or the proper expansion of the pre-compressed tape, compromising watertightness against driving rain and airtightness. Conversely, a clearance greater than 20 mm weakens the holding of fixing screws without plugs and causes excessive crushing under wind loads.

When the survey reveals an out-of-plumb condition exceeding the SIA 414 tolerances, a pronounced batter or a lintel showing deflection, the deviation is prohibitive. Reducing the size of the frame to work around a masonry defect is a fault: the visible profile would be asymmetrical and the standard cover strips would no longer cover the insulation.

Under art. 365 CO, if the ground designated or the material supplied by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately. In our practice, this obligation takes the form of a written notice of defects sent to the site management before any manufacture is launched. The report records the measured dimensions, sketches the out-of-plumb conditions and requests that the mason make good or chip back the concrete. The production order remains suspended until the corrected geometry has been approved.

Three-point survey method and setting the manufacturing axes

Taking the dimensions of a raw masonry or reinforced concrete opening cannot be improvised with a single central measurement. To ensure the manufacture of a perfectly fitted frame that absorbs the tolerances of the structural work without forcing the sash, the operator applies a systematic three-point survey on each axis of the opening.

  1. Width surveyUsing a rigid tape measure or a calibrated laser distance meter, measure the raw width at three separate places: 100 mm from the lintel (top), at mid-height of the opening (middle), and 100 mm from the flashing or masonry sill (bottom). Record every millimetre without rounding.
  2. Height surveyMeasure the raw height at three vertical points: 100 mm from the left reveal, at the exact centre of the opening, then 100 mm from the right reveal. Identify the absolute minimum value, which will dictate the maximum permissible overall height.
  3. Checking squareness using the diagonalsTake both diagonals from corner to corner on the inner face of the opening. A divergence between the two measurements immediately indicates a parallelogram or warping of the structural work.
  4. Checking plumb and levelsUsing a 2-metre spirit level or a laser level, check the verticality of the jambs and the horizontality of the sill and of the underside of the lintel. Record the maximum out-of-plumb observed in millimetres per metre.
Minimum clear dimension retained
The most restrictive value recorded among the three width or height measurements, from which the peripheral installation clearances are deducted to fix the final manufacturing dimension of the frame.

The site foreman records the six main dimensions and the two diagonals on a standardised cutting sheet. The calculation of the manufacturing dimension never uses an arithmetic average: only the smallest measured dimension serves as the basis for subtraction. In the event of a significant batter of the concrete towards the outside or inside, the dimension retained must correspond to the most prominent narrowing over the entire depth of the opening.

Calculating the peripheral installation clearance and handling prohibitive deviations

The peripheral clearance left between the window frame and the masonry meets strict physical requirements. It must allow free thermal expansion of the profiles (particularly pronounced on aluminium or dark foil-clad PVC profiles), ensure the continuous insertion of the airtightness and driving-rain sealing tapes, and leave the space needed for the passage of fixing brackets or frame screws without direct rigid contact.

Determining the installation clearance according to the material and the window size
Frame materialMaximum bar lengthNominal side installation clearancePermissible joint range
Natural timber / Timber-metalUp to 2.50 m10 to 12 mm8 to 15 mm
Natural timber / Timber-metalFrom 2.50 m to 4.00 m12 to 15 mm10 to 20 mm
White PVCUp to 2.50 m12 to 15 mm10 to 18 mm
Tinted / Foil-clad PVCUp to 2.50 m15 to 18 mm12 to 22 mm
Thermally broken aluminiumUp to 3.00 m12 to 15 mm10 to 20 mm

When the deviation measured on the construction site leads to an installation clearance below the minimum permissible threshold (generally less than 8 mm) or above 25 mm, the situation becomes prohibitive for the installer. If the clearance is too narrow, the pre-compressed sealing tapes cannot be inserted without being sheared, and expansion risks crushing the frame against the concrete, causing the sashes to jam in the warm season. If the clearance is excessive, the mechanical holding of the fixings working in shear is compromised, and watertightness against driving rain can no longer be guaranteed over time.

As soon as a structural work defect outside the SIA 414 tolerances is recorded, the contractor suspends the launch of manufacture. In accordance with art. 365 CO, if the ground designated or the material supplied by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client. This formal written notification stops the manufacturing lead time and requires the client either to have the reveals of the opening made good by the masons, or to explicitly approve in writing compensating frame extension profiles before the order is sent to the workshop.

Handling geometric non-conformities and blocking the launch of manufacture

The discovery of an opening outside tolerances during the survey requires the ordering process with the workshop or factory to be stopped immediately. External joinery cannot be adapted on the construction site by planing or twisting the frame: the prefabricated frame requires regular clearances to ensure airtightness, water drainage and expansion of the profile.

The contractor who notes these defects applies art. 365 CO: if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor informs the client. This notification takes the form of a written report of the dimensional deviation, sent to the site management before any shop drawings are sent for manufacture.

Technical decision when faced with a non-compliant opening
Anomaly observedImpact on the joineryPrior corrective measure
Out-of-plumb greater than 10 mmPinching of the peripheral clearance, jamming of the tilt-and-turn sashesReveal reworked by chipping or reinforced make-good by the mason
Diagonal difference greater than 8 mmTwisted frame, water ingress through uneven crushing of the jointsStraightening of the splay before re-setting the manufacturing dimensions
Concrete sill not level (> 5 mm)Impossible to adjust the load-transfer shims of the glazingExecution of a waterproof levelling screed under the flashing

Until the rectified substrate has been the subject of a counter-survey approved jointly on the construction site, the machining order remains on hold. In the case of a tight schedule, any additional costs for modifying profiles or frame extensions must be covered by an addendum approved in writing by the principal.

Frequently asked questions

Can an out-of-plumb opening of 15 mm be compensated by reducing the manufacturing dimension of the window?

No. Reducing the size of the frame to make up 15 mm creates an excessive lateral gap on the opposite side, reaching up to 30 mm. The pre-compressed sealing tapes lose their controlled decompression capacity and the mechanical fixings work in bending. The façade installer must refuse to manufacture until the masonry has been straightened by make-good or reprofiling.

How should the rejection of a non-compliant substrate be documented before production is launched?

The foreman draws up a written anomaly notice accompanied by the three-point survey record. This document details the measured dimensions, the deviations from the SIA 414 standard and photographs of the levels. It formally suspends workshop manufacture until the opening has been put right by the structural work contractor responsible.

Who bears the cost of the frame extensions made necessary by an opening that is too wide?

If the structural work has an opening that does not comply with the architect's drawings, the addition of extension profiles is an unforeseen adaptation measure. The material cost and the additional labour must be reported to the site management. They are charged to the trade package responsible for the execution error or settled via an addendum before the order is placed.

Why is it forbidden to manufacture a window on the basis of the architect's theoretical drawings?

The execution tolerances permitted for concrete or brick according to SIA 414 range between 5 and 12 mm. Manufacturing a rigid element without measuring the actual opening exposes you to a frame that is too large for the opening or to leaking side clearances. Only a joint physical survey allows the cutting dimensions to be adjusted.

Texts and standards cited

  • SIA 414Dimensional tolerances in building construction
  • CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3)