Skip to content
Website
🧱 CFC 221The three barriers: air, insulation, driving rainChapter 5 of 10 in the section

Geometric thermal bridges: corners, lintels and insulation returns

Changes of direction in the façade create increased heat loss through geometry alone. This chapter details the installation rules for insulation returns in window reveals, lintel and sill junctions, and the treatment of external and internal corners to prevent any risk of internal condensation in accordance with SIA 180.

Key takeaways

  • The geometry of corners multiplies the heat flows to the outside compared with flat walls.
  • The insulation return in the reveal must provide strict continuity with the window frame.
  • The internal surface temperature at a corner must meet the criteria of SIA 180.
  • Insulation under the window sill and lintel requires continuous sealing without any break in thickness.

Understanding the cooling-fin effect at corners and preventing internal mould growth

In an ordinary homogeneous wall, the heat flow lines pass through the envelope parallel to each other and perpendicular to the facings. As soon as two walls meet to form a projecting corner, the developed external heat-loss surface becomes markedly larger than the receiving internal surface. This physical phenomenon, often described as a cooling-fin effect, accelerates the loss of heat energy and drastically lowers the surface temperature at the internal edge of the room.

Geometric thermal bridge
Local concentration of heat loss caused by a variation in the geometric shape of the envelope, without any intrinsic change in the composition of the materials or in their thermal resistance.

This drop in temperature at projecting or re-entrant corners directly exposes the internal lining or plaster to a high risk of surface condensation. When the relative humidity of the indoor air comes into contact with a cooled surface whose temperature falls below the dew point, liquid water appears, creating conditions favourable to mould growth.

The thermal design of the envelope must guarantee a sufficient internal surface temperature to avoid surface condensation and mould formation under the design climatic conditions.

norme SIA 180
Geometric influence on the minimum permissible internal surface temperature
Wall configurationExternal/internal surface ratioCritical-point riskFaçade installer action required
Plain flat wall1.0Very low in the plain wall areaContinuous installation with tight joints
Projecting (external) cornerGreater than 1.0High at the internal edgeBond-staggering of the panels and local extra thickness if required
Internal (re-entrant) cornerLess than 1.0Medium to high depending on ventilationCheck the tightness of the insulation and the breather membrane

Forming the insulation returns in the reveal, lintel and window sill

The most sensitive point of the external envelope is the junction between the masonry structural work and the frame of the glazed window. If the face of the joinery is set back towards the inside, the concrete or brick window reveal becomes a direct escape path for heat flow unless an insulation return covers it. Indoor heat bypasses the window frame and escapes through the unprotected masonry.

  1. Checking the window openingsCheck that the width of the window frame leaves a minimum margin around the perimeter to accommodate the reveal insulation without covering the opening-sash overlap or the drainage groove.
  2. Installing the insulation in the reveal and lintelBond a rigid insulation panel of low thermal conductivity against the raw masonry, ensuring direct contact with no residual air gap against the subframe or the joinery frame.
  3. Continuity at the lintelExtend the lintel soffit insulation as far as the junction with the blind box or the upper frame, providing a drip profile to stop external run-off.
  4. Specific treatment under the metal sillInsert an incompressible, rot-proof insulating material under the aluminium sill flashing to break the thermal bridge between the concrete base and the interior, supplemented by a second-line watertight seal.

Where space is insufficient because of the window order or narrow profiles, vacuum insulation or aerogels make it possible to maintain the required performance at very small thicknesses. The façade installer coordinates this work from the frame-installation phase onwards to ensure that art. 365 CO on notifying defects that endanger the work is complied with if the openings do not allow the minimum thickness needed to meet the requirements of SIA 180 to be fitted.

Thermal continuity at the lintel and integration of blind boxes

The window lintel is a major geometric discontinuity where the internal heat flow escapes towards the external soffit and the rebate base. The recurring error on construction sites is sacrificing insulation thickness to recess the blind or roller-shutter box. When an aluminium or folded-sheet box comes directly into contact with the concrete window head without a thermal break, the internal face of the slab or lintel upstand drops below the critical dew-point temperature.

To meet the requirements of SIA 180 on protection against surface moisture and to prevent mould growth, the façade installer must ensure continuous back sealing. The upper face of the joinery frame must be covered by the lintel insulation, with no break in plane with the façade thermal barrier.

Lintel installation configurations and solutions for correcting the thermal bridge
Installation situationThermal leakage pointRecommended installationPerformance objective
Venetian blind with recess integrated in the thickness of the ventilated façadeSoffit of the concrete upstand and uninsulated back of the boxRigid high-performance insulation panel bonded at the back of the recess before mechanical fixing of the boxElimination of the linear thermal bridge Psi and continuity of the wind barrier
Window flush with the external face of the structural work with ETICSJunction between the upper frame and the underside of the lintelOverlap of the window frame by the external insulation with a pre-compressed compressible strip resistant to driving rainElimination of the cold air layer under the lintel and reduction of the geometric flow
Joinery installed mid-way within the revealInternal corner under the lintel and upper face of the window frameInsulation return bonded to the soffit with a minimum slope of 1 % towards the outside and an integrated water stopKeeping the internal surface temperature above the condensation point

Treatment of the window sill and projecting-corner junctions

The window sill combines a geometric constraint with a risk of water ingress. Indoor heat finds a preferred loss path under the window board. The external sill profile must rest on a compression-resistant insulating material, ensuring the watertight junction between the lower frame rail and the perimeter insulation.

At a projecting corner of the building, the developed external surface is markedly larger than the internal surface of the heated room. This unfavourable exchange ratio accelerates the cooling of the internal edge of the wall. To control this geometric thermal bridge, the insulation system must form an overlapping, sealed crossing with no air gap at the corner.

  1. Preparing the sill bearingPosition a rigid insulating riser under the frame. This incompressible piece supports the lower rail and breaks the heat transmission between the metal sill and the load-bearing wall.
  2. Forming the watertight sill barrierLay a continuous flexible waterproofing membrane under the flashing, turned up at the sides against the reveals, forming a tray that drains to the outside in the event of infiltration or condensation under the sheet.
  3. Crossing the panels at the façade edgeLay the corner insulation panels in a bond pattern staggered on every course to prevent the joints from opening under hygrothermal stresses.
  4. Installing the reinforced corner profilesBed a perforated corner bead with textile reinforcement into the base render coat, avoiding any metal through-fixing that would create a point thermal leak.

Handling interface non-conformities and on-site corrective work

On the construction site, geometric thermal bridges reveal their weaknesses when there are dimensional deviations between the structural work and the window frames. When the masonry tolerance encroaches on the planned opening, the thickness of the insulation return in the reveal is directly reduced. If the remaining dimension no longer ensures the thermal continuity required by SIA 180, the joinery element or the reveal insulation creates a conductive leakage line conducive to hygrothermal defects.

In accordance with art. 365 CO, if a circumstance endangers the proper or timely execution of the work, the contractor must inform the client. As soon as a raw reveal is out of plumb or narrowed so that the minimum prescribed insulation thickness cannot be installed, installation must be suspended before the frames are mechanically fixed or the perimeter panels are bonded. The notification flags the risk of condensation at the internal re-entrant corner and of resulting mould following the lowering of the surface temperature factor.

  • Joint survey of the opening dimensions: check of the reveal, the recess depth and the clearance available for the thermal lining.
  • Material substitution: use of vacuum or aerogel insulation of low thermal conductivity, approved by site management, where space is limited.
  • Shifting the installation face: repositioning the subframe or the joinery towards the outside so that the frame is overlapped by the façade insulation without constriction.
  • Checking the air barrier: continuous installation of the flexible membrane without discontinuity behind the insulation return at the lintel and window sill.

Any corrective work at a lintel or sill requires a sealed connection between the internal air-barrier membrane and the external thermal insulation. The geometric thermal bridge at the external corner worsens if warm, humid air infiltrates behind the reveal insulation panel: the dew point is then reached on the cold face of the concrete.

Frequently asked questions

What minimum thickness of insulation return should be installed in a window reveal?

According to the rules of the trade and the requirements of SIA 180, a minimum of 30 to 40 mm of standard insulation is required to avoid the thermal bridge. If the space available between the frame and the structural work is less than 30 mm, the use of materials of very low conductivity, such as aerogel or vacuum panels, compensates for the lack of space and prevents the risk of condensation at the internal corner.

How should the internal re-entrant corner prone to mould be treated?

The re-entrant corner is subject to the geometric fin effect: the external heat-loss surface exceeds the internal collecting surface. To keep the surface temperature above the critical moisture threshold set by SIA 180, the external insulation must wrap the projecting corner of the masonry without interruption, with a rigorous overlap of the window frame of at least 30 mm by the reveal insulation to stop the leakage flow.

What should be done if the blind box at the lintel creates a thermal bridge?

The lintel is a major zone of thermal weakness. The space behind the blind box must receive a rigid high-performance insulation of at least 20 to 30 mm decoupled from the masonry. The façade installer must check the continuity of the façade insulation under the soffit of the lintel up to the joinery frame, supplemented by an airtight connection to block convection flows under the box.

How should insulation be installed under a metal window sill board?

A window sill in aluminium or folded sheet strongly conducts the cold to the masonry beneath. It is essential to interpose an insulating thermal spacer of at least 20 mm under the board or to use a thermally decoupled drip profile. The metal flashing must never touch the raw concrete directly: the perimeter insulation rises against the sill piece of the window with a drained seal.

Texts and standards cited

  • SIA 180Thermal insulation, moisture protection and indoor climate in buildings
  • CO art. 365Material and site: the contractor is responsible for the proper quality of the material he supplies; if the material supplied by the client or the site designated by him is found to be defective, or if another circumstance endangers the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).

In the same section