Key takeaways
- A flat accessible threshold requires continuous drainage in front of the frame to compensate for the absence of an upstand.
- The bottom weather seal must combine a low striking gasket and an automatic door bottom.
- The protective canopy reduces the direct water load but never dispenses with the drainage channel.
- The continuity of the liquid-applied waterproofing under the bottom rail remains imperative down to structural work level.
Reconciling minimum water upstand and step-free passage under Swiss standards
The design of a modern building entrance imposes a major physical contradiction on joiners and façade builders. On one hand, the rules for barrier-free construction require a floor threshold edge that is as flat as possible, in principle limited to a very small maximum step, often rounded or chamfered. On the other hand, the Swiss rules on building envelope watertightness have historically required a water upstand of several centimetres above the level of the finished external covering to prevent infiltration through backflow or accumulation of rainwater.
In a conventional configuration, the heel of the joinery frame forms a direct mechanical barrier against wind pressure and run-off. Lowering or recessing this profile into the floor removes this watertight stop. Without a compensating measure, any water driven by a gust crosses the watertightness line and enters directly under the interior screed or into the floor's thermal insulation.
To resolve this contradiction on construction sites in French-speaking Switzerland, the contractor must implement a strategy of several successive barriers. The protection relies on liquid-applied or bituminous waterproofing turned up against the body of the metal floor profile, necessarily backed by a linear run-off drainage system placed directly in front of the threshold.
| Configuration | Accessibility (PRM) | Behaviour under driving rain | Compensating measures required |
|---|---|---|---|
| Threshold with conventional upstand (> 50 mm) | Non-compliant without ramp | Excellent mechanical barrier | No complex measures other than a flashing |
| Reduced chamfered step (≤ 20 mm) | Compliant under conditions | Moderate resistance | Slotted channel or drainage grating |
| Threshold flush with finished surface (0 mm) | Optimal accessibility | Total vulnerability without drainage | Connected channel, canopy and active seals |
Technical devices: linear drainage, movable sealing and roof overhang
The absence of a vertical barrier on the frame shifts the entire hydraulic load onto the ancillary works. The central component of this system is the drainage channel with grating or slot. Placed immediately against the threshold profile, it must have sufficient collection capacity and be connected to the rainwater drainage network or to an effective drainage layer of the external slab. This grating must remain removable to allow the seasonal maintenance needed to remove leaves and gravel.
- Positioning the channelAlign the drainage grating flush with the finished surface, with minimum spacing from the frame, to collect the water running off the door leaf.
- Connecting the sub-threshold flashingMechanically fix a drainage sheet under the threshold and bond the underlying waterproofing membrane in continuity with the tanking or the vapour barrier.
- Packing the thermal profileEnsure the accessible (PRM) threshold is seated on a high-strength sub-frame profile to eliminate any deflection under the repeated passage of users.
On the door leaf itself, stopping air and driving-rain infiltration requires specific mechanical components. A simple entry-level brush strip is not a watertight barrier: it holds back dust but lets through moisture driven by the wind. The proven technical solution consists in integrating a mechanically triggered automatic door bottom fitted with a silicone lip, combined with a magnetic seal or a low striking profile with drained baffle.
- Automatic threshold door bottom
- Device recessed in the low rebate of an opening leaf, whose internal mechanism drops under the pressure of a lateral plunger when the leaf is fully closed, compressing a watertight elastomer lip against the floor without creating friction when opening.
Finally, the overall architectural protection determines the reliability of the assembly. A canopy or projecting porch roof is the first line of defence of the envelope. This structure deflects most of the driving rain and limits the amount of water directly striking the entrance door. Although the canopy never dispenses with the floor channel, it drastically reduces the water pressure loads on the bottom seal.
Coordination at the interfaces: concrete base, waterproofing connection and profile installation
Executing a flush entrance door threshold tolerates no deviation in alignment or level. From the preparation of the structural work, the slab rebate recess must include the full thickness of the finished build-up: the interior screed, the thermal insulation profile under the threshold, the flexible waterproofing strip and the upper level of the tiled or paved external covering. If the bearing height is poured too high by the mason, the joiner is forced to create a stop that exceeds the permitted limit for free passage; if it is too low, spot packing creates a thermal bridge and weakens the mechanical support of the frame under traffic loads.
Mechanical fixing of the bottom rail requires adjustable anchor brackets or a thermally broken composite support profile, plugged into the concrete at a strict centre spacing. This base under the frame carries the horizontal thrust of the heavy leaf during repeated closing and the self-weight of the leaf when open. The gap under the bottom rail receives the liquid-applied waterproofing or the synthetic flashing in absolute continuity with the damp-proof barrier of the slab or basement wall. This connection must be executed and checked before the external works close off the area.
| Trade interface | Technical element concerned | Installation tolerance or requirement | Consequence of a defect |
|---|---|---|---|
| Structural work / Joiner | Finished level of the concrete recess | Level tolerance of ± 2 mm | Unintended creation of a step or settlement under traffic |
| Waterproofing / Façade builder | Flexible flashing under threshold profile | Continuous connection without folds or perforations | Water infiltration under the interior screed and rotting of the insulation |
| Locksmith / Parquet layer-Tiler | Alignment of guide rail or strike plate | Strict levelling to the finished level | Wheelchair wheels catching or premature wear of the seal |
| External works | Paving fall and grating level | Minimum fall of 1.5 % away from the façade | Driving rainwater pushed back towards the compression seal |
Installing linear drainage, dynamic seals and façade protection
The absence of a high masonry upstand requires transferring the hydraulic load to an immediate collection system placed at the external face. The slotted channel or grating must run along the full width of the opening and extend at least 15 cm beyond either side of the masonry reveals. This linear drainage collects façade run-off before it accumulates in front of the door leaf. A direct connection of the channel to a drain pipe leading to the rainwater network is essential; a simple filtering gravel bed clogs during violent storms and floods the low profile.
- Installing the drainage channelInstall the channel body against the threshold profile, inserting a rot-proof thermal insulation strip. Adjust the metal grating so that its top is perfectly flush with the outer edge of the aluminium frame, without creating a dip that could cause tripping.
- Adjusting the automatic door bottomAdjust the drop pressure of the automatic brush seal concealed in the low rebate of the leaf. The lateral push button on the hinge side must trigger the lowering of the flexible elastomer seal along its full length in the last millimetre of closing travel.
- Treating the canopy and the reveal returnsCheck the projection of the protective canopy or porch roof. The roof overhang must extend at least 60 cm beyond the vertical projection of the threshold to deflect direct rain, complemented by an effective drip profile on the underside to break the capillary path.
Managing interface non-conformities and recourse on the construction site
On the construction site, the conflict between lowered threshold and watertightness arises as soon as the masonry tolerances do not match the finished dimension of the profile. When the concrete base recess shows an incorrect level or a dimension that is too high, preventing the minimum water upstand, the installer of external joinery must not force the mechanical adjustment. Art. 365 CO provides that if the material supplied by the client or the ground designated by the client is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, the contractor must immediately inform the client. In French-speaking Swiss practice, this notification takes the form of an immediate notice of work stoppage to site management.
- Joint inspection record of levelsMeasure the actual structural work levels with a laser level against the general metric level mark (+1.00 m) and notify the deviations found in the site minutes.
- Checking the liquid-applied waterproofing connectionCheck the continuity of the waterproofing sheet or resin under the threshold flashing before fitting the frame.
- Validating channel drainageCarry out a low-pressure water-jet test on the floor grating to ensure there is no backflow towards the movable seal.
When the client demands step-free access without a roof projection or functional drainage system, the risk of infiltration of wind-driven rainwater becomes certain. Art. 369 CO recalls that the client's rights in respect of defects in the work are excluded where the defective execution is personally attributable to the client, in particular through orders given contrary to the contractor's formal warnings. The façade builder must record this warning in writing before the finishing elements are installed.
Frequently asked questions
How should a threshold channel that backs up during heavy rain be dealt with?
Backflow indicates saturation or undersizing of the drain pipe connected to the rainwater network. The installer must stop the threshold sealing work and report the anomaly to site management. The silt basket under the grating should be checked, the trap cleaned out and a compliant flow cross-section demanded before finalising the connection of the bottom gasket.
What should be done if the waterproofing under the bottom rail was perforated during fixing?
Any mechanical penetration of the bituminous or synthetic sheet under the door support destroys the water barrier. The contractor must unscrew the fixing brackets concerned, clear the contaminated area and rebuild the assembly cold using a polyurethane resin reinforced with a compatible non-woven fabric. No standard silicone sealant compensates for a perforated membrane subjected to splash water.
What solution should be adopted if the drop-down seal does not press evenly on the floor?
A poorly adjusted automatic drop-down seal creates an air and water path under the leaf. The flatness of the metal threshold counter-profile must be checked with a rigid straightedge. The craftsman adjusts the travel of the lateral plunger on the hinge side to set the mechanical drop of the elastomer profile, then checks the uniform compression of the lip across the full width of the opening.
Does the absence of a canopy justify refusing to install a flat threshold?
The absence of a protective projection on a weather-exposed façade multiplies the water load on the bottom rebate. The joiner does not refuse the installation, but formalises a written reservation on the risks of residual infiltration. He requires the installation of a slotted channel with increased flow capacity and checks the compatibility of the dynamic watertightness of the leaf according to the recognised rules of the trade.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by the client is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he must immediately inform the client, failing which he bears the consequences (para. 3).
- CO art. 369exclusion of the client's rights in respect of defects in the work where the defective execution is personally attributable to the client (orders given contrary to the contractor's formal warnings or any other cause).