Key takeaways
- The two-year warranty under SIA 118 covers defects, not wear.
- The natural ageing of exterior coatings is in no case a contractual defect in execution.
- A documented failure to carry out maintenance releases the contractor from his obligations to rectify the work free of charge.
- Handing over a maintenance log countersigned at acceptance blocks abusive claims when the period expires.
Delimiting the scope of the two-year warranty against natural ageing
In finishing work in French-speaking Switzerland, delivery of a façade envelope triggers the statutory and contractual warranty periods. Where the works contract incorporates SIA 118, a two-year warranty period starts from the acceptance record. During this two-year period, the client may report defects at any time without losing his rights. However, this contractual provision protects the work against installation defects, material defects or non-compliance with the recognised rules of the trade, and not against natural physical changes resulting from weather exposure.
| Building element | Defect covered by the warranty | Normal evolution not covered |
|---|---|---|
| Render on external wall insulation | Through-cracking with detachment of the reinforcing mesh | Superficial micro-crazing without water ingress and biological soiling linked to the microclimate |
| Ventilated timber cladding | Pull-out of a fixing under normal wind due to under-sizing | Uneven greying under drip edges and natural resin bleeding |
| External joinery installed in the reveal | Water ingress at the sill junction due to failure of the seal | Gradual loss of elasticity of uncleaned EPDM seals and soiling of the guide channels |
| Slatted blinds connected to the façade | Lack of parallelism resulting from an off-axis anchorage in the box | Wear of the pull tapes and soot deposits requiring brushing |
Under Swiss law, the Code of Obligations completes this framework. Under art. 371 CO, the limitation period for the client's rights in respect of defects in an immovable structure is five years. This five-year limitation period concerns latent defects, that is, those that could not have been detected during a customary inspection at delivery. Apparent defects not reported immediately are deemed accepted under the Code of Obligations, whereas SIA 118 grants this two-year notice period. On the other hand, the contractor is never liable for damage caused by extreme wind exceeding the load assumptions, by settlement of third-party ground or by external mechanical action exerted by users.
Formalising the mandatory maintenance and recording the written instructions at handover
The non-load-bearing envelope requires periodic work to maintain its driving-rain tightness and its air permeability. The contractor's warranty is strictly conditional on the owner observing the maintenance cycles. If water ingress occurs because the drainage slots of an aluminium flashing are blocked by dead leaves, the origin of the damage lies in operation. To set this technical reality against the client when defects are notified, the site foreman must have handed over a detailed maintenance protocol at acceptance.
- Compiling the as-built fileGather the technical data sheets of the profiles, the technical approvals of the render-on-insulation systems, the installation drawings of the rain barriers and the exact reference of the perimeter sealants.
- Drafting the user and maintenance manualSpecify in writing the inspection frequency of the expansion joints, the annual dust removal from blind guide channels and the obligation to clean the lower window drainage with clean water without aggressive solvent.
- Having the record of handover of the instructions countersignedAnnex the maintenance log to the acceptance record. Have an explicit discharge signed stating that the absence of preventive maintenance voids claims for wearing parts.
- Proposing a preventive maintenance agreementOffer the client a two-yearly visit contract to check the tightness of the ironmongery, the suppleness of the sealing and the condition of the rodent grilles at the foot of the ventilated cladding.
In accordance with art. 367 CO, the client checks the condition of the work as soon as he can and reports defects to the contractor. If the façade contractor proves, with photographs, that the window sills were covered with roof gravel blocking the drains, or that the façades were washed with a rotating-nozzle high-pressure cleaner damaging the render, the warranty claim lapses. The refusal to intervene is then legally founded on non-compliance with the manufacturer's rules and the instructions formally handed over.
Joint inspection at the end of the two years: on-site sorting method
As the two-year claims period provided for by SIA 118 draws to a close, the client generally requests a joint inspection visit. The technical challenge for the façade contractor and the installer of external joinery is to separate, unequivocally, faults arising from defective installation or a non-compliant component from the direct effects of climatic ageing or neglected maintenance. The contractor relies on the end-of-works file and the maintenance log handed over at acceptance to substantiate each finding.
For each element inspected — reveal-mounted windows, junction seals, ventilated cladding or renders on external wall insulation — the examination must be carried out under standard visual conditions, without artificial raking light and at an observation distance representative of normal use. Any claim relating to uniform aesthetic alteration or surface soiling must be compared with the operating requirements signed at acceptance.
| Envelope element | Typical finding on site | Technical classification | Attribution and responsibility for costs |
|---|---|---|---|
| External joinery (timber or timber-metal) | Sash rubbing on the keep, resistance to pivoting | Lack of periodic adjustment and no lubrication of the ironmongery | Routine maintenance at the operator's expense; warranty claim rejected |
| Sill or reveal sealing junction | Detachment of an airtightness strip or ingress under driving rain | Initial adhesion defect or installation stress not released | Defective workmanship; full rectification under warranty |
| Ventilated solid timber cladding | Non-uniform greying depending on exposure to rain and UV | Natural evolution of the material exposed to the weather | Normal climatic ageing; no intervention |
| External wall insulation with render | Soiling by run-off below flashings due to blocked drip edges | Neglect of periodic cleaning of the water-shedding parts | Proven failure to carry out maintenance; refusal to rectify under warranty |
| Slatted blind connected to the frame | Mechanism jammed by accumulated dust and foreign bodies | No dust removal or inspection of the guide channels | Use not in accordance with the maintenance manual; claim rejected |
Closing the two-year warranty and managing the regime for latent defects
Under SIA 118, for two years from the acceptance of the work the client has a claims period allowing him to report defects that appear at any time, without having to comply with the obligation of immediate inspection and notice. Once this term has expired, the work is deemed definitively accepted for all defects that were recognisable or that appeared during this period. The contractor is from then on released from any claim relating to superficial deterioration, apparent defects not contested in due time and the consequences of deficient operation.
After these first two years expire, only latent defects can still be claimed, until the end of the statutory limitation period. Art. 371 CO provides a limitation period of five years from acceptance for the client's rights in respect of defects in an immovable structure. A latent defect is technically defined as a fault that already existed at the time of delivery but remained undetectable during an ordinary examination, such as the internal failure of a non-visible thermal bridge, the omission of a substructure fixing hidden by the cladding, or the inverted installation of a non-ventilated rain barrier.
- Drawing up an end-of-warranty record for the two years summarising the points inspected, the findings accepted and the claims expressly rejected on grounds of ageing or lack of maintenance.
- Reminder of the conditions excluding the contractor's liability, based on CO, where the client has neglected the formal notices and the maintenance instructions handed over at the start of operation.
- Filing in the company's technical file the dispatch notes and signed receipts for the supply of the maintenance manuals, evidence that is indispensable in the event of a later dispute over an alleged latent defect.
- Immediate written notification confirming the final release of the financial or bank guarantees linked to the two-year execution phase.
Rigorous formalisation of this closure protects the façade contractor lastingly. By showing that the critical interfaces were examined jointly and that the faults reported stem from the action of the environment or from the omission of periodic maintenance work (greasing of ironmongery, cleaning of weep holes and drip edges, checking of flashings), the company defuses any attempt to reclassify wear as a latent defect.
Handling disputes at two years: contesting the classification as a defect
When the client sends a list of reservations at the end of the two years that includes wear-related faults, the works manager must immediately sort the claims. Soiling of window drainage slots, a sash jamming for lack of greasing of the ironmongery, chalking of an aluminium sheet under intense sun exposure, or uneven greying of untreated timber cladding are not defective workmanship within the meaning of SIA 118. These phenomena strictly arise from the natural ageing of materials and a lack of maintenance.
To defuse the dispute, the contractor relies on the documents handed over at the acceptance of the work. The formal handover of the maintenance and operating plan, countersigned or attested in the delivery record, serves as material proof. Under CO, the client's rights for defects in the work are excluded where the defective execution is personally attributable to him, which includes deterioration caused by non-compliance with operating instructions or refusal to maintain the exposed components.
- Convene a joint on-site visit with the representative to examine each contested point closely and compare the condition found with the initial delivery tolerances.
- Remind in writing of the cleaning frequencies prescribed for the powder-coated profiles and the sealing gaskets, demonstrating the absence of any traceability of maintenance operations.
- Record the state of soiling of the water drainage openings in the frames to establish that standing water results from neglect in operation.
- Request a joint technical report or an examination by a neutral expert under art. 367 CO where technical disagreement persists over the origin of the damage.
In the event of persistent refusal to release the security or to sign the end-of-warranty record for the two years, the reply must be formalised by registered letter. In it the contractor details, point by point, the history of the maintenance instructions provided, formally rejects the classification as a defect for wear phenomena and gives site management formal notice to validate the closure of the period on pain of default interest on the amounts retained.
Frequently asked questions
Can the client demand cleaning of the flashings and profiles under the two-year warranty?
No. Regular cleaning of atmospheric deposits, dust and dirt is routine maintenance under the operator's sole responsibility. The two-year warranty governed by SIA 118 covers only material defects and installation defects. If the build-up of corrosive deposits degrades the powder coating through lack of the annual washing recorded in the instructions handed over at delivery, the claim must be formally rejected as a failure to carry out maintenance.
What is the legal value of maintenance instructions handed over without signature at acceptance?
Handing over written instructions creates a presumption of clear information addressed to site management. Even without a separate signature on the notice, the mention of its transmission in the acceptance record is sufficient to set it against the client. This traceability proves that the contractor defined the conditions of normal use, depriving the owner of any claim based on ignorance of the actions required to preserve the façade components.
How to distinguish abnormal chalking of aluminium lacquer from discolouration due to ultraviolet?
Surface degradation is measured by comparison with a sheltered area not exposed to the sun, such as the undersides of canopies or interior rebates. A uniform loss of colour intensity without blistering after two years under intense solar radiation constitutes standard climatic ageing. By contrast, film flaking, underlying blistering or loss of adhesion reveal an adhesion defect of the powder coating applied in the workshop, attributable to the façade contractor.
What to do if site management blocks the retention money over blackened silicone joints?
The appearance of surface mould on a sealant results from ambient humidity and the stagnation of micro-organisms, which is a routine maintenance phenomenon. The contractor contests the financial block by registered letter, recalls the consumable nature of junction seals exposed to external pollution, and demands full release of the retention money or of the bank guarantee deed that has reached its contractual term.
Texts and standards cited
- norme SIA 118General Conditions for the execution of construction work
- CO art. 367after delivery, the client checks the condition of the work as soon as he can and reports defects to the contractor; for an immovable structure, he has 60 days to report them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2)
- COexclusion of the client's rights for defects in the work where the defective execution is personally attributable to him (orders given contrary to the contractor's formal notices or any other cause)