🧱 CFC 221Measured performance and building envelope acceptanceChapter 2 of 10 in the section

Finding air leaks: smoke, anemometer and thermography under depressurisation

The overall air-permeability test certifies an n50 or q50 value, but repairs nothing. To deal with airtightness non-conformities on external joinery and ventilated façades, the installer must identify the exact origin of the air paths. This chapter details the combined use of the smoke generator, the hot-wire anemometer and the thermal camera under continuous depressurisation.

Key takeaways

  • The overall BlowerDoor result qualifies airtightness but never indicates the physical position of air leaks.
  • The smoke generator reveals the air flows passing through rebates and joints.
  • The hot-wire anemometer quantifies residual air velocities to the nearest millimetre at sill connections.
  • Thermography under depressurisation reveals parasitic air entries as sharp cold infiltration patterns on the interior side.

The three tools for locating and characterising infiltration

The blower door fan maintained at a continuous pressure difference of fifty pascals is the indispensable prerequisite for any technical investigation. Without this stabilised differential applied to the whole volume, natural air transfers remain masked by internal thermal convection and external wind turbulence. The methodical search then combines three complementary tools to turn an invisible overall permeability value into a rigorous record of localised, measurable physical defects that can be repaired directly on the construction site.

Technical comparison of air-leak locating instruments
Investigation toolPressure regimeDetection modeLimit of use on site
Smoke generator or smoke bulbOverpressure or depressurisationDirect visual revelation of air paths as dense streamsRapid dispersion of the plume under parasitic general ventilation
Hot-wire anemometerStabilised depressurisationPhysical measurement of the point air-flow velocity in metres per secondStrictly point-based range requiring a millimetre-by-millimetre sweep of each gap
Infrared thermal cameraProlonged continuous depressurisationVisualisation of cooling plumes caused by cold air drawn inIneffective if the indoor-outdoor temperature difference remains below five kelvins
  1. Stabilisation under depressurisation and infrared scanningThe building is stabilised at fifty pascals of depressurisation with an indoor-outdoor temperature difference of at least five kelvins. The operator carries out a continuous sweep of the frames with the infrared camera to spot local temperature drops, shown as characteristic dark finger-like patterns along the profiles.
  2. Velocity measurement with the hot-wire anemometerThe telescopic hot-wire probe is placed flush with the identified thermal discontinuity. The instrument measures the velocity of the air being drawn in. This quantitative measurement confirms whether it is an active air leak or simply a thermal bridge by material conduction without air infiltration.
  3. Precise visualisation of the path with smokeAn injection nozzle releases a dense mist based on neutral glycol along the suspect gap. Under depressurisation, the smoke is drawn instantly into the crack; under overpressure, the plume flows back out, revealing the exact point of passage through the joinery.

Recurring leak points on joinery and envelope connections

On new-build or envelope-renovation construction sites, experience shows that most airtightness-test defects come not from the insulating glazing or prefabricated profiles, but from the installation interfaces and the connections between trades. Art. 367 CO provides that after delivery, the client must check the condition of the work as soon as is practicable and notify the contractor of any defects. A methodical self-check of the installed joinery before the reveals are lined avoids blocking reservations in the acceptance reports.

Continuous airtightness line
Continuous airtight barrier located on the warm side of the insulation, linking the masonry airtightness membranes to the window frames without interruption by means of elastic adhesive tapes and durable flexible sealants.
  • Window sill connection: perforation of the vapour barrier membrane where the load-bearing setting blocks pass through, or absence of a continuous sealant bead under the sill piece in the reveal.
  • Lower frame corners: mitre-cut sealing tapes without preformed corner pieces, creating open gaps under the effect of differential thermal movements of the structural work.
  • Blind guides and blind boxes: electrical conduits passing through the envelope without flexible airtight sleeves, and no airtight compression tape on the rear face of the guide rails.
  • Through-fixing points: frame fixing screws passing through the sealing tape without sealing adhesive under the head or an overlapping strip pressed onto the profile.
  • Sash meeting seals: insufficient compression of the EPDM seals due to poor adjustment of the espagnolette keeps or discontinuous crushing in the heat-welded corners.

Combined search protocol: coordinating smoke, anemometer and thermal camera

The overall air-permeability measurement gives a numerical value of the leakage rate at 50 pascals, but it does not reveal the physical location of envelope discontinuities. For the façade installer and the external joiner, precise location requires the methodical use of three investigation techniques while the building is kept under constant depressurisation. Each instrument serves a specific phase of the diagnosis, avoiding misinterpretations caused by natural convection movements or purely conductive thermal bridges.

  1. Depressurisation and initial thermographic scanThe blower door fan is set to induce a continuous depressurisation of 50 pascals in the inspected volume. With an indoor-outdoor temperature difference of at least 5 to 10 kelvins, infrared thermography scans the window reveals, blind boxes and base-of-façade connections. The cold outside air drawn in locally cools the interior finishes, drawing characteristic finger-like thermal plumes at the leaks, not to be confused with a simple static thermal bridge.
  2. Kinematic visualisation with the smoke generatorAs soon as a thermal anomaly or doubtful area is spotted, the operator brings the nozzle of a dense-mist smoke generator or a low-ejection-speed smoke pencil close to it. The path of the white stream instantly shows the direction of the flow: abrupt disappearance of the cloud swallowed into the gap of the connecting joint, or turbulent dispersion revealing the exact entry point of the parasitic air.
  3. Local quantification with the hot-wire anemometerThe miniature telescopic probe of the hot-wire anemometer is placed 5 millimetres from the singular point identified by the smoke. Unlike vane anemometers, which are too bulky and inert, the hot wire measures low to very low air velocities (from 0.05 m/s) in narrow gaps. This value makes it possible to rank the severity of the infiltration between two adjacent frames or at the crossing of an integrated blind rail.
Complementarity of leak-search tools on joinery and lightweight façades
Investigation toolOperating conditionsQuantity observedRole on a CFC 221 construction site
Thermography under depressurisationMinimum indoor-outdoor temperature difference of 5 KLocal surface drop in surface temperatureQuick overall identification of parasitic air-passage zones
Smoke generatorStable pressure difference (50 Pa), calm ambient airVisible path and deflection of the smoke plumeMillimetre-precise location of the faulty gap or penetration
Hot-wire anemometerProbe oriented perpendicular to the leak flowLinear velocity of the air jet (m/s) in the gapCharacterisation and ranking of the severity of the jointing defect

Treating critical leak locations and qualifying the defect

The search for infiltration reveals a typology of recurring failures that are rarely concentrated on the ordinary surface of the glazing elements, but almost systematically at installation interfaces and at connections between dissimilar materials. In external joinery and lightweight façades, identifying the exact location of the leak makes it possible to attribute the cause indisputably to the fixing method, the compression of the gaskets or the faulty continuity of the vapour barrier and airtightness membrane.

  • Lower corners of window frames: absence of a watertight overlap between the perimeter adhesive tape and the flashing under the sill, letting air rush in under the sill piece.
  • Blind box to lintel connection: frequent break in airtightness where the motor electrical conductors pass through, or discontinuity of the adhesive airtightness tape on the underside of the slab.
  • Mullion-transom junctions of composite joinery: lack of sealant or elastomer gasket in the mitre cuts and mechanical assembly pieces.
  • Sash-to-frame seals: poor compression of the seals at the upper corner opposite the hinges, requiring three-dimensional adjustment of the tilt-and-turn window hardware.
  • Penetration of external guide fixing brackets: drilling of the interior vapour barrier without a sealing gasket underlayer behind the fixing lugs.

As soon as a leak is quantified and documented with thermal images and anemometer measurements, the site foreman notifies the non-conformity to initiate the targeted rework of the connection. In accordance with art. 365 CO, the contractor notifies the client without delay of circumstances endangering the work, notably when the leak comes from the porosity of the masonry substrate or from an adjacent element installed by a third party. The employer also applies art. 3 OPA by providing teams with suitable respiratory protective equipment during intensive use of certain smoke agents in confined spaces.

Arbitration protocol and corrective measures in case of persistent non-conformity

When the detection campaign reveals an unacceptable residual leakage rate and the overall pressurisation test figure does not meet the project requirements, the façade installer must react methodically. Disputes frequently concern the interpretation of thermal anomalies or the representativeness of a flow recorded with the hot-wire anemometer. In accordance with CO, after delivery, the client checks the condition of the work as soon as is practicable and notifies the contractor of any defects. To prevent diffuse infiltration from being wrongly attributed to the external joinery, the physical marking of each leak must be the subject of an immediate joint survey on the execution drawing and in situ.

  1. Drawing up the joint surveyKeep the building at a constant depressurisation of fifty pascals. Re-examine each disputed point with the smoke generator and record the point velocity measured with the hot-wire anemometer in a report signed by both parties.
  2. Localised probing of the interfaceCarefully remove the finishing flashing or interior sill at the exact location of the air stream. This targeted dismantling makes it possible to see whether the defect comes from the adhesive connection, the compression of a pre-compressed tape or a break in the frame sealing joint.
  3. Airtight repair and counter-measurementReapply the adhesive tape on a dust-free substrate, rebuild the sealing bead or adjust the compression keeps of the sashes. Carry out a localised check with a smoke generator before refitting the finishes.

If parasitic flows remain despite the rework of the frame connections, the analysis must separate the joinery from defects specific to the structural work or the technical ducts. Where the dispute over the conformity of the work persists, a joint examination carried out according to the rules of the SIA 118 standard makes it possible to determine the real cause without multiplying destructive rework on compliant profiles.

Frequently asked questions

Can thermography under depressurisation be used in summer?

Infrared thermography requires a minimum temperature difference between indoor and outdoor air, generally set at at least ten degrees. In summer, if the building is not strongly air-conditioned, the infiltrating warm air flow does not create enough thermal contrast on the cold frames. It is then advisable to use only the hot-wire anemometer combined with the artificial smoke generator to physically qualify the air passages at the joinery.

Why does the hot-wire anemometer read zero despite a leak visible with smoke?

The hot-wire anemometer measures a very localised point velocity and is extremely directional. If the probe is not oriented exactly perpendicular to the air flow, or if the leak is diffuse along a brush seal without a constriction point, the velocity stays below the instrument's detection threshold. The smoke generator shows the overall path of the air, whereas the hot wire records the velocity only at the exact core of the infiltration stream.

At what stage of the construction site should the search for air leaks on joinery be carried out?

Leak location is carried out as soon as the airtight envelope is installed, but imperatively before the interior plasterboard linings are closed and the sills are fitted. If the test takes place after finishing, the air often infiltrates behind the finishes and comes out several metres from the real defect. Carrying out the search at the closed structural work stage makes it possible to correct the sealing tapes immediately without demolition work.

How can a frame infiltration be distinguished from a leak specific to the sash seals?

Proceed by selective masking under a depressurisation of fifty pascals. Temporarily seal the sash-to-frame meeting seal with a non-residue peelable adhesive. If the air stream detected with the hot wire or smoke persists around the perimeter, the leak is at the frame-to-structural-work connection or under the flashing. If the flow disappears, the anomaly comes from insufficient compression of the sash seals, adjustable directly on the hardware and keeps.

Texts and standards cited

  • COchecking of the condition of the work by the client after delivery and notification of defects to the contractor
  • norme SIA 118general conditions for the execution of construction works and examination by experts