🧱 CFC 221Blinds, shutters and solar protectionChapter 5 of 10 in the section

Motorisation: electrical provisions, control and coordination with the electrician

On the construction site, forgetting a wall penetration or a supply conduit for a blind means destructive rework on the linings and thermal insulation. This chapter details the geometry of conduit provisions, coordination with the electrician, the fixing of control points and the functional test protocols that are essential before the work is handed over.

Key takeaways

  • The conduit provision must pass through the airtight envelope without degrading the thermal and air barriers.
  • The location of the interior control point complies with the standard ergonomic height and access constraints.
  • The scope boundary assigns the junction box to the electrician and the motor cable to the façade contractor.
  • The temporary rotation test with a test cable validates the limit switches before any final connection.

Conduit provisions, watertight penetrations and positioning of the control point

Integrating a tubular motor into a blind box or a façade valance requires rigorous geometric marking out from the structural work and exterior joinery phase onwards. The blind's connection cable must under no circumstances be jammed against the lintel or pinched by the guide rails. The standard provision requires a draw-in tube with a minimum outside diameter of 20 to 25 mm opening into the box on the motor-head side, generally on the right when viewed from inside for linked slat blinds, unless the detail drawings specify otherwise.

  1. Defining the cable outletPosition the penetration point in the upper third of the box side cheek or in the upper part of the window frame, observing a minimum bending radius of 50 mm for the draw-in conduit.
  2. Drilling and installing the KRFWG conduitDrill the masonry or the pre-frame with a 2 % fall towards the outside to prevent any gravity-driven ingress of rainwater towards the inside in the event of condensation in the box.
  3. Watertight connection to the structural workSeal the annular space between the conduit and the concrete with non-shrink mortar or closed-cell polyurethane foam, completed by a vapour barrier strip connected to the finished reveal.
  4. Pulling the motor cablePass the UV-resistant flexible cable (type H05RR-F or flexible equivalent) from the motor to the junction box, keeping a drip loop in the box.

The wall control point, whether a momentary-contact changeover switch or a control keypad for a home automation system, is positioned according to rigorous usage logic. The axis of the flush-mounted box is usually placed at a height of between 105 and 115 cm above the finished floor, on the handle side of the glazed door so that the user does not have to reach round the open leaf. In the case of a remote individual control, the distance to the window reveal does not exceed 15 to 20 cm so as to keep a direct view of the curtain during operation.

CFC 221 and CFC 232 scope boundary, then functional check

Construction site disputes over motorised blinds almost always stem from a lack of clarity between the CFC 221 package (Lightweight façades and solar protection) and the CFC 232 package (Power installations). The contractual demarcation rule is strict: the façade/blind contractor supplies and installs the tubular motor, provides the mechanical fixing in the box or on the lintel support, and routes the motor supply cable, fitted with its watertight plug-in connector, to the provision made.

Usual split of work between façade/blind contractor and electrician
Installation itemResponsible companyWork included
Embedded draw-in conduitElectrician (CFC 232)Installation of empty conduit, draw wire, interior flush-mounted box
Penetration through lintel / cheekFaçade contractor (CFC 221)Precise core drilling, sealing sleeve, installation of the sealing collar
Motor and original cableFaçade contractor (CFC 221)Mechanical mounting on axis, cable clamping, connection plug
Link to the electrical panelElectrician (CFC 232)Pulling of lines, connection to terminal block, sub-circuit protection
Wall control deviceElectrician (CFC 232)Supply and installation of the changeover switch or bus actuator

In accordance with standard SIA 118, the contractor bears responsibility for the proper execution of its installations. For the CFC 221 package, the obligation includes the mechanical verification of the product before the electrician takes over. The installer cannot leave a mounted blind without having validated the free travel of the curtain, at the risk of being held liable for a torn fabric or jammed slats when the electrician first energises the system.

Construction site test cable
Mobile service tool comprising a single-phase mains plug, a double-pole toggle changeover switch and two clamps or a watertight female socket, allowing the blind installer to power the motor directly without using the building's permanent network.

The joint functional test follows a methodical procedure. The blind installer connects the mobile setting cable to the plug-in connector of the tubular motor. He carries out at least two complete up-and-down cycles. This operation checks that there is no friction in the guide rails, that the bottom slat is level and that the upper and lower limit switches are set exactly (micrometric screws or electronic pulse stops). The intervention ends with locking the curtain in the raised position and handing a signed self-check sheet to the foreman or to the site management.

Reveal drilling, conduit passage and envelope sealing

The penetration of a motor supply cable through the structural work or the joinery is a critical point of the façade. An improvised passage made with a hammer drill through the pre-frame or raw masonry ruins the interior airtightness and creates a direct water ingress path behind the perimeter insulation. Execution requires a rigid or corrugated watertight draw-in tube laid with a minimum fall directed towards the outside of the building. This negative slope prevents any accidental run-off from reaching the interior lining or the recessed blind box.

The draw-in tube passes through the lintel or the splay before the perimeter insulation under render or the ventilated lining is installed. The façade contractor makes the airtight connection between the conduit and the interior vapour retarder by means of an EPDM adhesive sleeve cut to the exact diameter of the conduit. On the exterior side, the outlet must open into the sheltered volume of the valance or blind box, above the drainage plane of the water-deflecting flashing. The drip loop of the motor cable at the conduit outlet remains mandatory: it forces residual condensation water to drip off before reaching the drive head or the plug-in connector.

  1. Drilling and sealing the conduitDrill the provision to a nominal diameter of 25 mm for a KR20 tube, with a fall towards the outside of 2 to 3 degrees. Clean away the drilling dust and seal the perimeter of the tube to the masonry with a flexible mastic joint or non-shrink mortar.
  2. Continuity of the air barrierPosition the self-adhesive airtight collar on the tube on the interior side of the masonry, then press the membrane onto the dust barrier or the waterproofing render before lining.
  3. Outlet into the box and drip loopCut the conduit flush at 10 mm inside the blind box. Route the motor supply cable so that it forms a bend downwards, lower than the entry point, to prevent any capillary migration.

Functional tests, scope limits and acceptance record

The contractual boundary between the lightweight façade builder (CFC 221) and the electrical installer (CFC 232) requires a strict material demarcation to avoid any shifting of responsibility in the event of a burnt-out motor or mechanical blockage. The blind fitter installs the tubular motor, engages the curtain suspensions, adjusts the levelness of the bottom bar and supplies the connection cable fitted with its standardised quick connector. The electrician powers the fixed line from the panel, installs the flush-mounted control box, connects the male-female plug and connects the changeover switch or the home automation module.

Distribution of tasks and technical responsibilities by trade
Operation on the construction siteCFC 221 (Façade contractor / Installer)CFC 232 (Electrician)Expected deliverable
Draw-in conduit in revealSupply and watertight installationChecking the outletFree tube with draw wire
Fixed wiring and controlIndication of power ratings and diagramsSupply, pulling and connectionProtected live line
Motor and quick connectorSupply, installation and mechanical adjustmentSnap-in on watertight socketCompliant plug-in connection
Initial limit switch settingSetting with the programming boxTemporary or permanent power supplyUpper and lower stops set
Joint functional testTravel and parallelism checkCheck of direction of rotation and phaseSigned inspection record

The functional test must not be postponed until the electrical installations are commissioned as a whole. The blind installer uses a standalone test case connected to the connector to validate the free movement of the curtain between the guide rails, the absence of slat jamming and precise stopping at the electronic or mechanical stops. This preventive operation protects the blind installer from any subsequent damage resulting from phase inversions or contradictory commands sent by a poorly configured building management system.

Under art. 367 CO, after delivery, the client checks the condition of the work as soon as is practicable and notifies the contractor of any defects. The joint test record signed with the site management and the electrician documents the verification of the raising and lowering direction, the correct alignment of the end stops and the condition of the curtains. Under art. 368 CO, the client may assert its rights in the event of defects in the work; the existence of a formalised test record makes it possible to show that the mechanical product delivered was free of defects at handover.

Handling provision non-conformities and arbitrating interfaces

The absence of a required conduit provision, or its outlet in the wrong place, immediately blocks the installation of the blind box. Where the interior installations supervisor omits the conduit before the slab is poured or before the plaster is sprayed, the CFC 221 closure installer must under no circumstances perforate the masonry or drill the frame in an improvised manner. Any uncoordinated through-penetration ruins the air barrier and creates a linear thermal bridge at the lintel.

Corrective measures according to the origin of the provision defect
Situation observedDirect technical impactCorrective measure requiredAllocation of costs
Conduit missing behind the valanceImpossible to pass the motor cable without a visible penetrationPrecise core drilling from the inside with EPDM sealing sleeveResponsibility of CFC 232 or site management
Conduit outlet poorly centred, hindering the windingFabric rubbing or jamming of the adjustable slatsRerouting of the cable under an extra-flat protective profileCFC 221 after written approval from the site management
Switch placed behind the leaf of a French windowControl inaccessible without passing the open leafRelocation of the box or switch to a flush-mounted radio moduleCosts borne by the specifying trade

Under CO, if another circumstance jeopardises the proper or timely execution of the work, the contractor informs the client. The façade contractor sends a written notice of partial interruption as soon as a missing conduit is found, recalling the scope limit with the electrician: the connection to the panel and the supply wiring fall under CFC 232, while CFC 221 fixes the guide rails, installs the motor and supplies the plug-in connector. A functional test before acceptance is carried out using a workshop test cable as soon as temporary power is available, so as to record the mechanical travel and the limit switches in the construction site log before the covers are finally closed.

Frequently asked questions

Who must supply and install the blind motor connection cable?

The blind manufacturer supplies the factory-fitted motor cable, often equipped with a watertight plug-in connector. The CFC 221 installer fits the blind and feeds this section into the waiting conduit. The CFC 232 electrician takes over from the junction box, provides the electrical supply, connects the conductors and installs the wall control or the receiver.

Where exactly should the control point be positioned to avoid usage conflicts?

The control point is located on the window handle side, opposite the hinges, at a standardised height of 100 to 110 centimetres above the finished floor. It must never be hidden by the opening of a swing leaf nor interfere with interior joinery boxes, radiators or the cladding shown in the architectural execution drawings.

What should be done if the electrician has not yet powered the construction site when the blinds are installed?

The façade contractor uses a mobile setting cable with a standard site plug to carry out the functional test before acceptance. This operation makes it possible to check the mechanical travel, the precise setting of the upper and lower limit switches and the absence of friction in the guide rails, and then to record these findings immediately on the installation record.

How can the airtightness of the conduit provision in the reveal be guaranteed?

The conduit passage through the masonry or the framing must receive an adhesive sealing sleeve or an EPDM cable grommet connected to the interior vapour barrier. On the exterior side, the conduit is cut flush with the facing and sealed with a non-hardening elastomer sealing paste, preventing air circulation by thermosiphon and water ingress under the box.

Texts and standards cited

  • COmaterial and ground: the contractor is responsible for the proper quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).
  • norme SIA 118General conditions for the execution of construction work