Key takeaways
- Spraying always starts at the bottom rail before working progressively up towards the transom.
- The SIA 331 standard sets the performance requirements for external windows and French windows.
- The interior visual check looks for water paths at the mitre corners and under the flashing.
- The joint inspection record signed on site logs the time, the exact location and the nature of the leaks.
Carry out methodical spraying from bottom to top in accordance with the rules of the trade
On an external joinery construction site in French-speaking Switzerland, waiting for the first autumn storm to check watertightness against driving rain is a professional fault with serious consequences. Once the reveals have been insulated and the interior sills fitted, the slightest water path contaminates the thermal linings and plasterwork. The purpose of a spray test on installed joinery is not to reproduce a differential-pressure test in a laboratory chamber, but to test the resistance of the perimeter sealing joints and the proper working of the mitre drainage against continuous run-off.
Windows and French windows must prevent any unwanted penetration of water into the interior of the building under the service conditions provided for by the project and according to their local exposure.
norme SIA 331
The fundamental rule of testing on the building envelope is that the water jet moves upwards progressively. If the operator sprays the lintel directly, the water runs down the whole opening, masking the exact origin of a seepage noticed at the threshold. The test uses a hose fitted with a calibrated spray head or a nozzle bar delivering an even film of water without any mechanical stripping effect. The supply pressure at the nozzle must not exceed 2 to 3 bar, simulating rain driven by the wind without tearing out the sealants or dislodging the pre-compressed tapes.
- Phase 1: Flashing connection and bottom rail (10 minutes)Spray the junction between the external metal sill, the flashing and the bottom rail of the frame. The nozzle stays pointed upwards at an angle of about 30 degrees to wet the underside and test the watertight barrier under the sill.
- Phase 2: Vertical jambs and side seals (10 minutes)Move the spraying zone up along the vertical jambs, targeting the reveal connection joint, the vapour-permeable sealing tapes and the rebate of the main sash.
- Phase 3: Head rail and lintel (10 minutes)Finish with the lintel and the upper connection, including the blind box or the return of the external insulation. The total run-off then covers the entire frame.
Detect interior water paths and record the joint inspection record
Throughout the external spraying, a second technician works inside the building, equipped with an inspection lamp and white absorbent paper. Infiltrations do not always show up as a visible puddle on the floor. They often travel by capillary action behind the flashing, along the through-fixing screws of the frame, or come out as micro-droplets at poorly drained glazing blocks. The observer pays particular attention to the lower corners of the frame, a critical point where the structural-work joint and the profiled mitres meet.
| Interior symptom | Probable technical origin | Interface responsibility |
|---|---|---|
| Water standing under the interior sill | Defective side upstand of the flashing or puncture of the membrane under the sill | Facade contractor / Joinery fitter (CFC 221) |
| Seepage along the jamb in the reveal | Break in continuity of the sealing tape or sealant not bonded to dirty concrete | Joinery fitter (CFC 221) |
| Drops between the sash and the frame | Insufficient contact pressure of the keeps or gasket mitre cut not bonded | Manufacturer / Joinery fitter (CFC 221) |
| Dampness on the raw lintel | No drip on the lintel or no water shedding at the head of the reveal | Concrete structural work / Rendering |
The test has legal weight only if it is formalised immediately in the form of a joint inspection record. Under art. 367 CO, after delivery, the client checks the condition of the work as soon as he can and notifies the contractor of any defects. The technical spray test record gives technical substance to this check. To be indisputable before the site management or the insurer, the document must unambiguously identify the opening tested, the floor, the orientation to the wind, the exact start and end time of each spraying sequence, and the indicative mains pressure.
If the test reveals satisfactory watertightness, the record discharges the fitter for the installation stage concerned, before the external insulation or plastering contractor encloses the reveal connection. If an infiltration is proven, the exact nature of the recorded defect determines the corrective measure: adjusting the compression of the hardware, localised repair of the butyl membrane under the sill, or complete replacement of the failed seal without unnecessary damage to the surrounding works.
Classifying water paths and the requirements of the SIA 331 standard
The water test of an installed window has value only if the exact origin of the infiltration can be identified. The SIA 331 standard defines the requirements for air permeability and watertightness against driving rain for windows and French windows, setting the technical framework of fitness for service against the weather. When a drop beads on the warm side, the first reflex on site is often to blame the seal between the frame and the masonry. Yet water can enter through the corner joint of the sash, through a glazing gasket pinched during blocking, or through obstruction of the pressure-equalisation vents in the bottom rail. A hasty diagnosis leads to pointless rework on the perimeter sealing joint, leaving the structural defect of the joinery untouched.
| Water reappearing inside | Probable physical path | Element involved |
|---|---|---|
| Drop at the nose of the interior upstand | Insufficient slope of the meeting-rail profile or backflow from the pressure-equalisation chambers | Machining of the bottom rail or faulty non-return flap |
| Dampness on the connection tape in the reveal | Break in continuity of the external sealing membrane or poorly compressed Compriband | Interface connection between structural work and joinery |
| Run-off along the plaster splay | Infiltration at the metal sill flashing without watertight side ends | Sill flashing or external insulation connection |
| Standing water in the hardware groove | Insufficient compression of the central gasket or incorrect positioning of the keeps | Compression hardware or sash geometry |
Continuous monitoring of the interior face during spraying avoids confusion over the origin. An infiltration that appears after two minutes under the spray bar reveals a clear discontinuity: torn sealing tape, no sealant bead under the prefabricated sill, or no corner connection. On the other hand, a delayed seepage that appears only ten to fifteen minutes after spraying has stopped points rather to slow saturation of the drainage rebates. In that case, the lower water outlets cannot discharge the flow to the outside, causing capillary overflow towards the interior finishes.
Drafting the joint inspection record and enforceability of reservations
To have full evidential value before the site management and the various trades, the spray test must lead immediately to a dated joint inspection record. In Swiss construction law, prompt formalisation of the check conditions the handling of claims. Art. 367 CO provides that the client checks the condition of the work as soon as he can and notifies the contractor of any defects; for a building work, he has 60 days to notify them. The spray test record drawn up on the spot fixes the material reality before the plasterboard linings are closed up or the facade finishes are applied.
- Recording the test parametersEnter the precise start and end time, the outside temperature, the water mains pressure and the location of the facade according to the architect's plans.
- Graphic location of defectsMark on an elevation diagram the exact point of entry and the point of emergence on the interior side, with clear photos including a millimetre tape or a moisture marker.
- Qualifying the origin of the leakWrite a neutral description of the facts observed, clearly distinguishing whether the water escapes from the frame structure itself or from the perimeter sealing joint.
- Joint signature on the construction siteObtain the signatures of the head fitter, the site manager and the representative of the site management before any dismantling of the test set-up.
The original copy of the record, countersigned by all parties involved, serves as an enforceable basis for demanding rectification in accordance with the rules of the art. If the defect comes from the installation, the joinery company works on its gaskets, membranes or sill blocking. If the water enters through a factory assembly defect or a hardware defect covered by the criteria of the SIA 331 standard, the record allows the contractor to pass the warranty claim on immediately to the window manufacturer with irrefutable technical proof.
Handling recorded infiltrations and steps in the event of disagreement
When the water test reveals water infiltration on the interior side, the foreman or site manager must act without haste. The first step is to identify the exact path of the water: penetration through the glazing rebate, a watertightness defect under the flashing, a blocked drainage vent, or failure of the perimeter joint connecting to the structural work. The dated joint inspection record logs the precise facts, supported by photographs and an interior-side diagram. Art. 367 CO provides that the client checks the condition of the work as soon as he can after delivery and notifies the contractor of any defects. This enforceable document serves as the sole technical basis for the next steps.
In the event of disagreement over the origin of the damage — in particular if the site management blames the installation while the joinery has an assembly non-conformity from the workshop —, each party may request an examination by experts under art. 367 CO. This neutral technical expert report makes it possible to qualify the actual performance according to the SIA 331 standard before heavy removal works are undertaken. The installing contractor thus preserves his rights by demonstrating the conformity of his watertight barriers with the approved execution plans.
- Dry out the interior linings immediately and fit a temporary catch film to limit damage to the finishes.
- Record the exact time the first drop appeared, the spraying stage under way and the precise area of water entry.
- Notify in writing by registered letter the reservations made during spraying if the other party refuses to sign the record.
- Plan a targeted repair after complete drying, necessarily followed by a new check spray test of the same duration.
Frequently asked questions
What should be done if the site management refuses to sign the joint inspection record after the water test?
If the client's representative refuses to countersign the spray test record, the contractor immediately records this refusal on the document. He sends the complete test report, together with the time-stamped photographs and the flow readings, by registered letter the same day. This formal dispatch secures the date of the finding and makes the observations enforceable for the purposes of applying the rules of the Code of Obligations on the checking of the work.
What water pressure and flow rate should be applied on the construction site to remain representative without damaging the work?
The construction site spray test is carried out without direct mechanical pressure on the joints, using a calibrated nozzle or a low-pressure spray bar. The water flow rate is set between one and two litres per minute per linear metre of joint tested. Spraying water at high pressure is a technical fault: it artificially forces the pressure-equalisation barriers and distorts the assessment required by the SIA 331 standard.
How long should an installed window be sprayed to validate its watertightness against driving rain?
The proven method requires methodical spraying of at least fifteen minutes per zone tested, progressing strictly from bottom to top. Start with the lower flashing and the sill connection, then the vertical jambs, and finish with the upper lintel. This duration allows the water to soak into any capillary cracks and travel as far as the interior sealing plane if a barrier has a discontinuity.
Is a drainage vent that discharges water to the outside during the test a defect?
No, this discharge proves that the drained and ventilated rebate principle prescribed by the SIA 331 standard is working properly. Water that infiltrates under the external glazing bead must be collected by the drainage channel and then discharged freely to the outside via the vents. A defect exists only if this water overflows the rebate and enters the interior side of the joinery or wets the insulation of the reveal.
Texts and standards cited
- SIA 331Windows and French windows: requirements for the design, manufacture and installation of external joinery.
- CO art. 367Checking of the work by the client after delivery, notification of defects and examination by experts.
