Skip to content
Website
🧱 CFC 221Ventilated cladding: framing, air gap and fixingsChapter 2 of 10 in the section

Secondary framing: adjustable brackets, battens and compensation for the substrate

This chapter details the installation of the secondary framing for ventilated cladding on masonry or concrete. You will learn how to size the adjustment range of the brackets to compensate for structural work defects, how to determine spacings according to the chosen cladding, how to neutralise point thermal bridges and how to validate overall flatness before installation.

Key takeaways

  • The adjustment range of the brackets absorbs the flatness deviations of the concrete substrate.
  • Thermal insulation requires a break pad to limit the residual point thermal bridge.
  • The spacing of the battens depends on the cladding material, its format and the wind loads.
  • Checking flatness with a straightedge and a string line validates the installation before the cladding is fitted.

Compensating structural work tolerances and limiting thermal bridges

The raw concrete or masonry substrate commonly shows out-of-plumb areas, hollows or bumps that exceed the tolerances admissible for the final cladding. The role of the secondary framing, whether made of timber uprights or metal profiles, is to recreate a rigorously regular plane while leaving the thickness needed for the insulation and the ventilated cavity. This function relies on the adjustable cladding bracket, fixed to the substrate with suitable anchors.

Adjustment range
Maximum amplitude, measured in millimetres in the slotted holes of the façade bracket, allowing the distance of the supporting profile from the raw substrate to be adjusted to compensate for alignment defects.

Each bracket has slotted holes in its projecting leg. These slots allow a sliding play of the order of 30 to 50 mm depending on the length of the leg. During design and setting out, the installer chooses a bracket whose nominal position lies in the middle of the usable range. If the structural work shows an inward or outward out-of-plumb, the fitter absorbs the drift by sliding the fixing of the batten or profile, without having to resort to makeshift shims under the bracket heel.

The presence of metal brackets passing through the insulating layer causes localised heat losses. The point thermal bridge associated with each fixing bracket degrades the overall coefficient of the wall if no thermal break is installed. The systematic insertion of an insulating thermal pad in polypropylene or elastomer between the mineral substrate and the bracket heel clearly reduces this heat transfer. This thermal break limits the local cooling of the interior concrete and ensures compliance with the thermal requirements of standard SIA 180.

Determining spacings and checking flatness before installing the cladding

The spacing of the vertical battens or supporting profiles is dictated by the nature of the exterior cladding, its thickness and its own stiffness. A composite panel, a solid timber board or a fibre-cement sheet do not allow the same span without risking visible warping under the wind loads calculated according to the SIA standards. The spacings of the secondary framing are most often aligned on grids of 400 mm, 500 mm or 600 mm, dictated by the joints of the cladding.

Indicative spacings of the secondary framing according to common claddings
Cladding familyUsual thicknessMaximum recommended spacingType of framing
Solid timber boards19 to 24 mm500 to 600 mmTreated timber battens
Fibre-cement sheets8 to 12 mm600 mmAluminium profiles or planed timber
Composite panels4 mm400 to 500 mmSpecific metal profiles
Terracotta or stoneware15 to 30 mmAccording to modular formatSuitable metal uprights

The vertical spacing between the brackets supporting a single upright depends directly on the self-weight of the cladding and the wind suction. For a typical façade in French-speaking Switzerland, the vertical spacing varies between 800 mm and 1200 mm. The layout alternates fixed points, taking the self-weight and horizontal loads, and sliding points to allow free thermal expansion of the upright without bowing.

  1. Setting up the end reference pointsInstall the two outermost uprights of the façade plumb using a laser or a plumb line. Carefully adjust their distance from the planned finished face.
  2. Stretching the reference string linesStretch two nylon string lines perfectly taut horizontally between the edge uprights, at the top and at the bottom of the façade.
  3. Aligning the intermediate framingAdjust the position of the intermediate uprights within the adjustment range of the brackets, bringing them flush with the string line without ever pushing it or creating any deflection.
  4. Systematic checking with a straightedgeApply a 2 metre or 3 metre metal straightedge diagonally and horizontally to detect the slightest local misalignment.

The installer applies the general prevention rules defined in art. 82 LAA to organise his workstations when handling the uprights and the checking tools. In addition, according to art. 3 OPA, the appropriate protective measures must be effective throughout the alignment and screwing operations on the façade in order to prevent accidents.

Adjustment range of the brackets and thermal break at the substrate

Mineral structural work shows plumb and flatness deviations that regularly exceed the direct absorption capacity of façade claddings. The ventilated secondary framing, built on a timber or mixed substructure, is therefore supported on adjustable metal brackets, commonly called angle brackets or anchor brackets. These elements absorb out-of-plumb conditions thanks to slotted holes machined in their leg perpendicular to the wall. In practice, a standard bracket offers a usable range of the order of 30 mm to 50 mm to vary the projection of the rafter or batten relative to the raw face of the concrete or masonry.

Each perforation of the insulating envelope by a metal bracket constitutes a localised heat loss quantified by its point thermal transmittance coefficient (Chi value, denoted χ). To limit the impact of these point thermal bridges on the overall energy balance of the building, interposing a rot-proof thermal insulation pad made of composite material or polypropylene between the bracket and the supporting wall is essential. This thermal pad breaks the direct contact between the aluminium or galvanised steel and the masonry, significantly reducing the heat loss flow and preventing surface condensation on the interior side.

Thermal and mechanical behaviour according to the type of anchor brackets
Type of framing bracketAssociated thermal breakImpact on the Chi value (χ)Installation on the construction site
Standard aluminium bracketWithout insulating padHigh (clear thermal bridge)Direct fixing to concrete, not recommended under modern energy standards
Aluminium bracket with thermal breakPolypropylene or rigid EPDM baseModerate to lowPad clipped on or slipped onto the back before mechanical anchoring
Stainless steel bracketSpecific insulating thermal padVery low (reduced conductivity of stainless steel)Controlled tightening to avoid excessive crushing of the thermal break
Composite / glass-fibre bracketBuilt in by the nature of the materialNegligibleCareful handling when tightening, no galvanic corrosion

Distribution of spacings and flatness checking protocol

The spacing of the battens and the vertical pitch of the brackets are not chosen arbitrarily. They result from a direct compromise between the stiffness of the chosen cladding, the admissible wind loads and the pull-out resistance of the anchors in the structural work. Thick solid timber boards allow wider spacings of the supporting profiles than thin fibre-cement or composite sheets, which require a closer spacing to prevent any bulging or vibration under suction.

  • Large-format sheet cladding (fibre-cement, high-pressure laminate): rafter spacing of 500 mm to 600 mm, bracket pitch between 800 mm and 1000 mm depending on wind exposure.
  • Solid timber boards laid horizontally: vertical battens spaced at 500 mm to 650 mm depending on the species, the profile and the minimum thickness of the boards.
  • Interlocking composite or metal boards: spacing set according to the manufacturer's technical specifications, usually 400 mm to 600 mm.
  • Double substructure (counter-battening for vertical installation of the cladding): strict sizing of the first network of rafters to take the increased pull-out moment.
  1. Setting out the guide reference pointsMark out the framing lines at the ends of the façade and set up two corner reference profiles, perfectly adjusted with an optical laser level and a heavy plumb line.
  2. Stretching the reference string linesStretch two high-strength horizontal nylon string lines between the corner profiles, one at the top and one at the bottom, positioned at the theoretical outer face of the battens.
  3. Adjusting the range of the intermediate bracketsPosition the intermediate rafters and work the bracket-to-batten connecting screws in the slotted holes to bring them flush with the string line without ever touching it or deflecting it.
  4. Final tightening and mechanical lockingLock all the fixings with the tool suited to the recommended torque, then check that no local buckling has been induced during screwing.
  5. Checking with a mason's straightedgePass a 2 m to 3 m aluminium straightedge diagonally and vertically over three adjacent profiles; the gap under the straightedge must not exceed the play allowed by the type of cladding planned.

Managing structural work deviations and thermal trade-offs on the construction site

On the construction site, theoretical flatness often runs up against the real deformations of the structural work. When an alignment survey with a theodolite or a straightedge reveals an out-of-plumb exceeding the usable range of the adjustable brackets, the installation team must under no circumstances force the slotted holes or shim in a makeshift way with offcuts from the construction site. If the nominal range of 30 mm or 40 mm is no longer enough to make up the hollow in the wall, the façade installer must record the measurements and consult the site management.

Two technical solutions remain in accordance with good practice: replacing the brackets with a model with a deeper leg, or interposing certified thickness shims under the original thermal break. Adding an unplanned overhang shifts the centre of gravity and increases the bending moment on the anchor. This modification systematically requires validation of the load path by the façade engineer or the system supplier, checking the admissible tensile force at the substrate.

Thermal and mechanical impact depending on framing adaptations
Condition foundMechanical consequenceCorrective action requiredThermal bridge impact
Range exceeded by < 15 mmModerate increase of the lever armRot-proof thickness shim under the thermal breakNegligible local increase of the chi value
Range exceeded by > 15 mmCritical bending moment at the anchorageReplacement by a long-leg bracketWider thermal break and revised thermal calculation
Excessive spacingDeflection of the profile under wind suctionInstallation of additional intermediate bracketsMultiplication of point heat losses

According to CO, if the site designated or the material supplied by the client is defective, or if a circumstance compromises the proper execution of the work, the contractor informs the client. This formal notification protects the façade installer before the final cladding conceals the alignment defects or the abnormal stresses undergone by the battens.

Frequently asked questions

How do you compensate for a masonry hollow larger than the slot of the bracket?

Never grind out the slotted hole of the adjustable bracket. The solution is to order brackets with a longer heel for the affected area or to insert flat thickness shims made of rot-proof material behind the thermal break. The added thickness requires a longer fixing anchor in order to retain the structural anchorage depth prescribed in the concrete or masonry.

What alignment tolerance should be aimed for on the rafters before installing the cladding?

The misalignment between two neighbouring profiles or battens must not exceed 1 mm at the junction of the façade panels. Over a two-metre straightedge swept across the substructure, the general out-of-plumb must remain below 2 mm. Any greater deviation produces unsightly cast shadows on the joints and may generate destructive shear stresses on the cladding fixings.

What is the real impact of metal brackets on the overall energy balance?

Each aluminium bracket passing through the insulation constitutes a point thermal bridge characterised by its chi coefficient. Multiplied by several hundred pieces on a large ventilated façade, this effect can degrade the overall U-value of the wall by 15 to 30 %. The systematic use of a composite thermal break pad behind the bracket considerably limits these parasitic heat losses.

Why adapt the bracket spacing to the nature of the cladding?

The spacing of the fixings to the substrate responds directly to the self-weight of the cladding and the suction loads due to wind. Dense fibre-cement or ceramic cladding requires closer vertical spacings on the supporting profiles to limit deflection. Conversely, a light aluminium board allows longer spans, provided the manufacturer's charts and the local suction stresses are respected.

Texts and standards cited

  • COmaterial and site: the contractor is responsible for the proper quality of the material he supplies; if the material supplied by the client or the site designated by him is found to be defective, or if another circumstance compromises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).

In the same section