Key takeaways
- Position the first fixing between 100 and 150 mm from the inner corner of the window frame.
- Observe a maximum spacing of 700 mm for aluminium and PVC, and 800 mm for timber.
- Check the cohesion of the masonry or concrete substrate before using mechanical or chemical anchoring.
- Transmit the wind loads and the weight of the glazing without residual bowing of the frame.
Position the frame fixings according to SIA 331 and wind loads
Fixing a window frame is not limited to holding it temporarily in place. The frame acts as the element that directly transmits the mechanical forces applied to the envelope to the primary structure of the building. In accordance with SIA 331, the fixing system must fully absorb the pressure and suction exerted by the wind, the repeated operation of the sashes and the self-weight of the glazed unit. While the lower support takes most of the vertical loads transmitted by the glazing blocks and the setting blocks, the perimeter fixings on the jambs and the head transom absorb the loads perpendicular to the plane of the façade. Underestimating the wind force causes alternating bending of the frame, leading to premature failure of the perimeter sealing strips, jamming of the hardware and infiltration of air or driving rain.
| Frame material | Distance from corners | Maximum spacing, jambs | Maximum spacing, transoms |
|---|---|---|---|
| Solid or glulam timber | 100 to 150 mm | 800 mm | 800 mm |
| Thermally broken aluminium | 100 to 150 mm | 700 mm | 700 mm |
| Steel-reinforced PVC | 100 to 150 mm | 700 mm | 700 mm |
| Mixed timber-aluminium systems | 100 to 150 mm | 700 mm | 700 mm |
Observing the corner distance of 100 to 150 mm meets a precise geometric and structural requirement. An anchor placed too close to the inner corner, less than 100 mm away, restrains the natural thermal expansion of the window profiles. This restraint generates excessive internal stresses at the mitre joints and risks cracking the weld beads of the PVC or the metal assembly corner cleats. Conversely, a fixing too far away, beyond 150 mm, leaves the corner free to vibrate under gusts, creating a continuous gap that ruins the airtightness of the joint. In addition, every mullion or intermediate transom must always be secured by two fixings located 150 mm either side of its axis in order to neutralise the torsional moment transmitted by the differential pressure on the adjacent glazing.
Check the load-bearing substrate and select the appropriate anchoring method
The best anchor bracket offers no resistance if the host masonry is friable, heterogeneous or poorly assessed. Before the frame is installed, the façade installer carries out a careful examination of the load-bearing substrate in the reveal or rebate. Solid reinforced concrete offers optimum mechanical strength, allowing direct use of frame screws without plugs or metal anchor bolts. Hollow fired-clay bricks or aerated concrete blocks, on the other hand, require specific fixings with suitable expansion or form-locking, combined with rotary drilling without hammer action to preserve the integrity of the internal walls of the masonry.
- Mechanical testing and preparation of the revealCheck the flatness, plumb and surface strength of the structural work. Remove dust from the opening to eliminate concrete laitance and formwork residue that could distort the packing.
- Choice of connection systemSelect the direct frame screw for installation in the reveal with reduced clearance, or the reinforced adjustable angle bracket where the window is set flush with the outer face within the thermal insulation.
- Drilling and observing edge distancesDrill perpendicular to the substrate, maintaining a minimum distance of 50 mm from the free edge of the concrete or masonry facing, in order to rule out any risk of spalling or localised bursting.
- Fixing and packing to transfer the loadTighten the screws without deforming the profile. Place incompressible spacer packers directly opposite each fixing in order to transmit the pressure and suction forces without warping the frame.
Metal anchor brackets, whether flat, bent or fitted with three-dimensional adjustment jacks, remain indispensable where the thickness of the external insulation sets the window out beyond the load-bearing face. These fittings must have sufficient cross-section and stiffness to resist buckling under wind action and shear generated by the weight of the glazed unit. Screwing the bracket to the frame requires self-tapping screws in stainless or treated steel, which must penetrate the internal tubular steel or aluminium reinforcements of the frame.
Installing brackets and frame screws according to geometric constraints
Transferring wind loads and self-weight to the structural work requires rigorous positioning of each connection point. SIA 331 sets out the guiding principles for windows and French windows, notably the obligation to ensure a continuous mechanical fixing capable of absorbing pressure and suction without deforming the frame profile. Two main techniques are used on the construction site: direct screwing through the frame using plugless frame screws (turbo screws) and indirect connection by galvanised or stainless steel fixing brackets.
For direct through-screwing, the pilot holes in the PVC or aluminium frame must allow sufficient thermal clearance to avoid restraining axial expansion. In masonry or concrete, drilling is carried out without hammer action in hollow fired-clay bricks or aerated concrete, in order to preserve the internal walls of the load-bearing material. The effective anchoring depth of the frame screw depends directly on the mechanical strength of the substrate.
| Frame material | Maximum distance from inner corner | Maximum distance from intermediate jamb/transom | Maximum spacing between standard fixings |
|---|---|---|---|
| Solid timber or glulam | 150 mm | 150 mm | 800 mm |
| White PVC | 150 mm | 150 mm | 700 mm |
| Tinted or foil-faced PVC (dark) | 150 mm | 150 mm | 600 mm |
| Thermally broken aluminium | 150 mm | 150 mm | 700 mm |
Twist anchor brackets or brackets screwed onto the outer face of the frame are required where the external thermal insulation projects well over the reveal or for surface-mounted installations with a splayed reveal. Each bracket must have a minimum thickness of 1.5 mm to resist buckling stresses under negative wind load (suction). The bracket is anchored to the frame by at least two self-drilling screws suited to the metal reinforcement of the profile, then plugged into the structural work in the sound area of the substrate, strictly observing the edge distances prescribed by the plug manufacturer.
Combined transfer of sash weight and wind, and integral mechanical packing
A fixing never works in isolation: it forms an inseparable system with the seat and perimeter packing. While the screws and brackets mainly take the horizontal loads perpendicular to the plane of the glazing (wind pressure and suction), the weight of the glazed sashes and the service loads must be fully transferred to the substrate by rot-proof support blocks (polypropylene or reinforced polyamide). No frame must rest directly on its bottom transom without levelling blocks, nor rely solely on the shear of its screws to carry the glazing masses.
- Support (seat) blocks: placed under the jamb carrying the hinges and under the fixed vertical jambs, never at the centre of a bottom transom so as not to block the drainage of infiltrating water.
- Sealing or lateral spacing blocks: positioned in the plane of the hardware to transmit the opening forces and prevent twisting of the frame during operation.
- Corner blocks: placed opposite the anchoring points to absorb the tightening torque without warping the frames.
- Anchor screws without residual stress: screwing must never bow the frame; the use of self-drilling double-thread screws or rigid temporary packing before tightening guarantees the straightness of the jambs.
- Dimensional check and cleaning of the substrateCheck the plumb, level and flatness of the masonry opening. Remove laitance and mortar splashes, and clear dust from the bearing surfaces before offering up the frame.
- Placing the seat blocks and offering up the framePlace the levelling seat blocks at the corner positions and under the central jambs. Position the frame, check the diagonals and insert the temporary spacing blocks.
- Drilling and plugging the primary pointsDrill the lower and upper fixing points at 150 mm from the inner corners. Insert the structural fixings without overtightening to allow millimetre adjustment.
- Installing the intermediate fixings and final packingDistribute the intermediate fixings, observing the prescribed spacings. Place the sealing blocks at the hinges and strike plates. Tighten all the fixings and check that there is no deflection of the jambs.
On the construction site, the strength of an external window affects the safety of the building in use. Careful execution of the anchorings guarantees flawless transfer of climatic forces to the load-bearing structure. Under art. 229 CP, anyone who, in directing or carrying out a construction or demolition, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence of up to five years or a monetary penalty. Strict observance of the technical anchoring rules provides lasting protection for installers and users.
Fixing failures and remedial work on the construction site
Several critical failures compromise the fixing of a window: a screw without a plug spinning freely in a hollow brick, a piece of concrete spalled by drilling too close to the edge of the reveal, or excessive deflection of the frame under a gust. As soon as an anchor does not develop the nominal resisting torque or the load-bearing material deteriorates under the tightening torque, the transfer of horizontal forces perpendicular to the glazing is no longer ensured. The neighbouring fixings then suffer a direct load transfer that can start a chain pull-out effect along the rebate. A non-functional anchor must never be concealed behind a sealing bead or covered by the thermal insulation.
- Offsetting the through-drillingDrill a new hole in the frame profile at a distance of at least 50 mm from the faulty hole, while maintaining the required distance of 100 mm to 150 mm from the inner corners.
- Installing an offset fixing bracketWhere the substrate has steel reinforcement or a friable bedding layer in the reveal, fix a zinc-plated steel bracket at least 2 mm thick on the outer side of the frame profile, plugged into a sound area of the masonry.
- Chemical anchoring in hollow substrateIf the fired-clay brick bursts as the self-tapping screw passes through, drill without hammer action, insert a mesh sleeve and inject a hybrid resin to anchor a threaded rod without creating expansion stress.
Art. 229 CP provides that anyone who, in carrying out a construction, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence of up to five years or a monetary penalty. Anchoring failure of a window exposed to wind suction poses a real risk of the unit falling onto public land or onto occupants. The compliance of the fixings, observance of SIA 331 and the prior remediation of non-load-bearing substrates must be recorded in the construction site reports.
Frequently asked questions
How is the fixing spacing determined on a large PVC window?
According to the installation guidelines and SIA 331, the maximum spacing between two fixing points on a PVC frame must not exceed 700 mm. For dark-coloured profiles, which are exposed to greater thermal expansion, this spacing should be reduced to 600 mm. Corner fixings must always be located at a distance of between 100 mm and 150 mm from the inner edge of the frame.
Can direct-fixing frame screws be used in all types of masonry?
No. Continuous-thread frame screws work best in solid concrete, natural stone and dense calcium silicate brick. In hollow masonry such as hollow fired-clay brick or aerated concrete, the absence of solid material prevents the thread from anchoring mechanically. In this case, offset metal anchor brackets must be installed or a chemical injection anchor with mesh sleeve must be used.
Why must the frame be mechanically packed at the fixings?
Tightening a frame screw or a bracket without incompressible packing causes geometric deformation of the frame towards the masonry reveal. This bowing jams the hardware and prevents the transmission of wind loads. Rot-proof adjustment packers must therefore be positioned opposite each anchoring point in order to take the thrust forces without bowing the jambs, while leaving the clearance needed for thermal expansion.
Which wind load mainly governs the sizing of window fixings in Switzerland?
Although frontal wind pressure applies a direct force on the glazing, it is generally suction that puts the mechanical fixings most to the test. This force tends to pull the window outwards from the building, particularly at façade corners and on upper floors. The anchoring must therefore take the combination of this critical tensile force and the self-weight of the sash.
Texts and standards cited
- SIA 331Windows and French windows
- CP art. 229breach of the recognised rules of construction: anyone who, in directing or carrying out a construction or demolition, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence of up to five years or a monetary penalty; if through negligence, up to three years or a monetary penalty.