🧱 CFC 221Ventilated cladding: framing, air gap and fixingsChapter 8 of 10 in the section

Fire in ventilated facades: cavity barriers and height requirements

After reading this chapter, you will be able to size and position the horizontal fire barriers in the ventilated cavity. You will identify the insulation and cladding materials permitted according to the height of the building, deal rigorously with lintels above openings, and compile the quality assurance documentation required for acceptance of the envelope.

Key takeaways

  • The continuous air cavity creates a thermal draught that sharply accelerates vertical fire spread.
  • The horizontal galvanised steel barrier interrupts the cavity at every habitable storey.
  • The height of the building requires strict reaction-to-fire classes for the insulation.
  • Thermal treatment of the lintel prevents flames from entering the rear ventilation directly.

Chimney effect and geometry of ventilation cavity barriers

In a ventilated facade, the air gap between the external cladding and the insulation layer forms a continuous duct. In a fire, the air draw produced by the heat turns this gap into a true thermal chimney. The upward draught accelerates combustion, feeds the flame front with fresh oxygen and spreads the fire over several storeys within minutes, well before the load-bearing elements fail. To neutralise this forced convection, the facade installer must divide the cavity with physical barriers that are tight against radiant heat but permeable to the residual airflow outside a fire.

Horizontal air cavity barrier
Continuous metal or intumescent device mechanically fixed to the structural work, intended to compartmentalise the ventilation cavity so as to block hot gases and flames in the event of fire.
  1. Setting out and positioning on the load-bearing wallMark the positioning line at each separating floor level. The fire barrier must be fixed directly into the solid mineral substrate before the mineral wool is installed.
  2. Mechanical fixing of the stop plateInstall a solid galvanised steel plate at least 1.0 mm thick. The expansion metal anchors or concrete screws are spaced at 300 mm maximum with controlled tightening.
  3. Adjusting the ventilated air gapAdjust the perforated flashing so as to keep a maximum residual clearance of 20 mm behind the cladding to ensure day-to-day ventilation, or install an approved intumescent strip that hermetically closes the passage from 180 °C.
  4. Treatment of joints and cornersEnsure a longitudinal overlap of the profiles of at least 100 mm and mechanically connect the joints with sealed blind rivets.

Building height, reaction to fire and treatment of openings

The Swiss fire protection regulations of the VKF/AEAI strictly categorise the use of facade components according to the geometry of the building. In medium-rise and high-rise buildings, tolerances give way to non-combustible materials. The opening reveal is the main point of failure: a flat fire passing through the glazing will immediately lick the lintel before reaching the cladding above. The framing and filling materials must form a continuous shield there to deflect the flames towards the outside of the building.

Minimum requirements for ventilated facade materials according to height
Height categoryThermal insulationSecondary framingExternal cladding
Low-rise (up to 11 m)Non-combustible or combustible RF3Timber permitted or metalRF3 permitted subject to a fire protection concept
Medium-rise (up to 30 m)Strictly non-combustible (RF1)Non-combustible metal (RF1)RF1 or certified RF2 permitted
High-rise (above 30 m)Strictly non-combustible (RF1)Non-combustible metal (RF1)Strictly non-combustible (RF1)

At windows, the lintel requires a non-combustible steel flashing covering the full depth of the insulation and closing off access to the ventilated void above. The perimeter insulation immediately next to the reveals must be mechanically secured to the structural work to prevent any thermal detachment under direct fire load. The through-fixings must retain their mechanical strength without premature collapse of the load-bearing structure.

Installing closing flashings and fire barriers at reveals

Thermal continuity and ventilation require precise openings, but fire spread turns every unprotected gap into the start of a draught. In a ventilated facade, the treatment at openings is a critical zone: a flame coming out through broken glazing attacks the lintel directly, licks the reveal and enters the air cavity if the mechanical seal is lacking when hot.

Above windows and on the jambs, combustible or semi-combustible thermal insulation must be stopped or protected by a galvanised steel plate at least 1.5 mm thick or by an RF1-classified material. This fire-stop lintel flashing is firmly fixed into the concrete or masonry structural work using metal anchors that withstand high temperatures. The use of ordinary plastic anchors for this component is strictly prohibited, because their rapid melting detaches the barrier from the very start of the fire.

To preserve ventilation in normal service while ensuring horizontal compartmentation of the air cavity when temperature rises, two techniques coexist on construction sites: the ventilated intumescent strip and the fixed perforated plate. The intumescent grille has a honeycomb network that lets air circulate; at a temperature above 150 °C, the component expands and fills the entire air gap within a few tens of seconds, stopping the chimney effect dead.

Behaviour and installation conditions of air cavity closures at reveals
Compartmentation deviceConstituent materialsBehaviour in the event of firePoints to watch during installation
Rigid lintel flashingGalvanised steel plate t ≥ 1.5 mmDeflects the flames towards the outside of the envelopeSteel mechanical fixing only, slope towards the outside, airtight joint with the solid substrate
Intumescent strip on angle bracketExpandable graphite on perforated steel angleExpands under the effect of heat (> 150 °C) and seals the air gapRespect the prescribed residual air gap (max. 50 mm), continuous installation without breaks at reveal corners
Perforated flame-stop platePerforated stainless or galvanised steel (void < 40 %)Slows the passage of embers and reduces the oxygen supplySystematic overlap of at least 30 mm between profiles, periodic cleaning of the ventilation slots

Requirements according to building height and conformity file

The VKF/AEAI fire protection regulations classify the reaction-to-fire requirements of materials according to the building height category: low-rise (up to 11 m), medium-rise (up to 30 m) and high-rise (above 30 m). As the building gets taller, access for rescue service vehicles becomes more difficult, which requires a drastic tightening of the characteristics of the thermal insulation, the windproof membranes and the cladding.

For medium-rise buildings (11 to 30 m), the use of thermal insulation of reaction-to-fire group RF3 or RF2 remains subject to the installation of continuous horizontal barriers at every storey or every second storey according to the approved construction configuration. By contrast, for high-rise buildings (> 30 m), the entire facade build-up — insulation, substructure and external cladding — must mandatorily fall within group RF1 (non-combustible, typically high-density stone wool, ceramic, certified fibre cement or metal cassettes without a combustible core).

  1. Collecting the conformity certificates of the materialsGather the declarations of performance (DoP) and the VKF/AEAI certificates for each component: facade insulation, rainscreen membranes (reaction-to-fire classification), intumescent ventilation profiles and cladding panels.
  2. Self-inspection of the work on the construction siteCheck step by step the mechanical fixing of the closing flashings, the absence of any uncompartmented open void at the horizontal joints, and the fixing to the structural work by metal expansion fixings.
  3. Preparing the joint photographic recordSystematically photograph the fire barriers, lintels and storey flashings before the final installation of the cladding panels, while these devices are still fully visible.
  4. Submitting the fire quality assurance declarationDraw up and sign the certificate of conformity of the lightweight facades (quality assurance level QSS 1 or 2 depending on the structure), countersigned by the project's fire quality assurance manager before acceptance of the work according to the SIA 118 standard.

Compiling the documentation to be placed in the project file is a strict contractual obligation. This technical file, handed to site management, contains the layout drawings of the barriers, the dated self-inspection records and the technical data sheets of the fire-resistant fixings. In the event of a non-conformity or of endangerment resulting from a deliberate defect in installing the fire barriers, art. 229 CP recalls the criminal liability borne by persons who direct or carry out a construction in breach of the recognised rules of the trade.

Managing barrier non-conformities and VKF/AEAI acceptance

On construction sites, execution deviations relating to ventilated fire barriers often appear late, during the inspection before cladding or during the visit of the fire protection authority. A perforated flashing poorly anchored in the concrete structural work, a profile interrupted by a framing bracket or an insulation replaced by a combustible product will block the issue of the occupancy permit. As soon as a geometric or material non-conformity is detected, site management must suspend the installation of the cladding in the area concerned in order to keep visual access to the void.

  • Immediate joint inspection record with the facade installer and the project's fire quality assurance manager.
  • Checking the continuity of the galvanised steel horizontal barrier plates at the framing joints.
  • Checking the direct mechanical fixing into the solid substrate, without relying solely on the load-bearing profiles.
  • Immediate replacement of any insulation panel that does not meet the requirements linked to the height of the building.

Lifting reservations requires the compilation of a rigorous project file. The contractor submits the technical data sheets of the non-combustible materials, the test reports of the intumescent strips or perforated plates, and a comprehensive photographic record of each level before the cladding is closed. Under art. 365 CO, if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor informs the client, failing which the contractor bears the consequences. This written notification protects the tradesperson in the event of a dispute over the tolerances of the structural work.

Frequently asked questions

What should be done if the metal framing prevents perfect continuity of the flashing?

The steel barrier flashing must be cut cleanly at the vertical uprights. The residual clearance between the framing profile and the closing plate must not exceed the tolerances permitted by the fire protection concept. If a larger gap remains, it must be sealed with a fitted metal piece or an approved intumescent sealant, and the detail validated with the fire protection quality assurance specialist.

Can a ventilated intumescent strip be used instead of a perforated plate?

Yes, if the fire protection concept approved for the structure explicitly provides for it. Intumescent strips keep the air cavity completely open in normal conditions to ensure thermal draught and moisture removal. Under the effect of heat, they expand rapidly to seal the air gap. The contractor must mandatorily supply the corresponding VKF/AEAI certificate of conformity before installation begins.

How should the horizontal barrier be dealt with when the insulation has large thickness tolerances?

The closing plate must mandatorily be mechanically fixed to the concrete or masonry load-bearing wall, and not simply installed under compression against the thermal insulation. In the event of excess thickness or irregularity of the facade insulation, the flashing must be adjusted to ensure the required projection into the air cavity. The residual air gap in a ventilated facade must strictly respect the prescribed ventilation cross-section without creating a free passage.

Which documents must the installer submit before the scaffolding is dismantled?

The installer must hand over to site management the declarations of performance of the insulation, the technical data sheets of the closing plates and an as-built drawing locating each fire barrier. A detailed photographic file showing the fixings and the continuity of the flashings at each storey is essential, because the fire protection authority requires this visual evidence before issuing the final occupancy permit.

Texts and standards cited

  • CP art. 229breach of the recognised rules of construction: anyone who, while directing or carrying out a construction or demolition, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons faces a custodial sentence of up to five years or a monetary penalty; in the case of negligence, up to three years or a monetary penalty.
  • CO art. 365material and ground: the contractor is responsible for the good quality of the material that he supplies; if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).