🧱 CFC 221Ventilated cladding: framing, air gap and fixingsChapter 4 of 10 in the section

Fixing the cladding: exposed screws or clips, and the expansion gap to be left

This chapter details the rules for the mechanical fixing of ventilated façade cladding, whether visible or concealed. You will learn how to set out fixed and sliding points, how to size the expansion gaps at the ends according to the materials, and how to set the tightening torque to prevent buckling, cracking and aesthetic defects.

Key takeaways

  • Create a single fixed point per element to direct the expansion towards the sliding points.
  • Drill the slotted or enlarged holes to the required diameter to allow sliding without stress.
  • Always disengage the screw gun clutch to compress the EPDM washer without ever crushing the cladding.
  • Maintain a minimum gap at the ends to absorb seasonal thermal and hygrothermal variations.

Define the fixed point and arrange the sliding points according to the material

Every cladding panel or board undergoes unavoidable dimensional variations caused by sunshine and the relative humidity of the air. If the cladding is mechanically blocked at both ends, the internal stresses cannot be relieved. They result in warping of the panel, shearing of the screws or cracking failure around the holes. The fundamental rule of the ventilated façade therefore requires each element to be designed with a single fixed point, supplemented by a series of sliding points.

Cladding fixed point
Mechanical fixing whose drilled hole diameter in the panel is identical to the diameter of the fixing shank. It anchors the element to the framework and determines the direction in which the dimensional expansion occurs.

The fixed point takes up the component of the self-weight and stabilises the panel in its plane. It is generally positioned at the geometric centre of large fibre-cement or resin panels in order to distribute the expansion symmetrically towards the perimeter. On horizontal timber or aluminium boards, the fixed point is placed on the central upright or at one of the ends depending on the direction of overlap. All the other fixings are sliding points.

Pre-drilling diameters for fixed and sliding points (5 mm shank screws)
Type of claddingFixed-point drillingSliding-point drillingType of bit or guide
Fibre-cement (8 mm thick)Ø 5.5 mm centredØ 8.5 mm to 9.5 mmRemovable centring ring
Compact laminate (HPL)Ø 6.0 mm centredØ 8.0 mm to 10.0 mmStepped drill guide
Extruded aluminium boardRound hole Ø 5.2 mmSlotted hole 5.2 x 10 mmSlot milled at the factory
Aluminium composite panelØ 5.5 mm centredØ 8.5 mm slidingShouldered sliding washer

Adjust the tightening and respect the expansion gaps at the ends

The freedom of movement at the sliding points only works if the fixing head does not press the cladding too hard. Self-drilling screws with a vulcanised (EPDM) sealing washer must be driven with a screw gun fitted with an adjustable mechanical depth stop. Using electronic torque alone is not enough: the physical stop nose ensures that the neoprene washer is compressed by about 30% to seal and dampen vibrations, without ever clamping the panel against the metal profile or the timber batten.

  1. Calibrating the mechanical stopSet the depth stop on an offcut of framework and cladding until the EPDM washer makes firm contact without deforming the metal flange.
  2. Drilling with a guide sleeveUse a shouldered drill bit or a sleeve matched to the sliding-point diameter to ensure that the hole is perfectly perpendicular and concentric to the framework.
  3. Installing the visible fixingInsert the stainless steel screw at the exact centre of the oversized hole, without forcing it at an angle, to leave an equal range of movement in all directions.
  4. Manual check of slidingCheck by applying lateral pressure that the panel retains its sliding play under the fixing head before leaving the work position.

At the ends of the elements, whether interlocking boards or panels laid edge to edge, the joint gaps must be scrupulously respected. For solid or thermally modified timber, hygrothermal shrinkage requires an end gap of 3 to 5 mm to prevent contact in damp periods. For composite or aluminium panels, the thermal expansion coefficient requires a minimum spacing of 8 mm to 10 mm between large-format panels. At the bottom of the cladding and under the roof edge, a gap of at least 20 mm ensures both mechanical expansion and the minimum cross-section required for ventilation of the air cavity.

The recognised technical rules require an installation that guarantees the durability of the work without harmful deformation due to foreseeable climatic stresses.

norme SIA 118

Choosing the fixing method according to the cladding: visible screws or concealed clips

The mechanical and hygrothermal behaviour of a ventilated façade depends directly on the suitability of the match between the outer skin and its retaining system. Aluminium composite panels, fibre-cement, high-pressure laminate (HPL) boards and solid timber cladding boards do not react to the same climatic stresses. An unsuitable fixing turns seasonal dimensional variations into shear stresses that pull out the screws or crack the panels around the holes.

Exposed fixing with lacquered-head screws or rivets on a timber or aluminium framework provides direct transmission of wind suction forces. For solid timber or fibre-cement, it requires rigorous guidance: systematic pre-drilling of the panels to a diameter larger than the fixing shank to allow sliding, except at the fixed point. Conversely, concealed systems using metal clips, hanging rails or stapled brackets on the underside eliminate through-holes. They transfer the load to peripheral grooves or plugged inserts on the back of the material, which frees the surface expansion while requiring millimetre-precise alignment of the secondary framework.

Suitability criteria of fixings according to the type of façade cladding
Cladding materialPreferred fixing methodManagement of slidingMechanical sensitivity to restraint
Fibre-cement and lightweight aerated concreteVisible screws with EPDM washer or rivetsOversized drilling on sliding points, centring sleeve mandatoryVery high: star cracking from the fixing hole if overtightened
Aluminium composite panels (ACM)Concealed clips on the edges or hanging cassettesFree sliding in the horizontal and vertical interlocking profilesMedium: thermal blistering of the sheet and loss of flatness
Compact HPL laminatesWide lacquered-head screws or concealed staplesMinimal annular gap around the screw shank, single fixed point at the centreHigh: warping, edge splitting and banging noises
Solid timber profiles (larch, Douglas fir)Exposed stainless steel screws on the visible face or stainless steel clips in the grooveDifferential shrinkage and swelling compensated by the elasticity of the assembly gapMedium to high: axial splitting along the grain in case of blocked double screwing

Controlling the gap at the ends and preventing defects on the construction site

The joint between two lengths of cladding or the connection at a building corner concentrates all the accumulated linear deformations. If the boards or panels are butted tight without a clear gap, the summer temperature rise generates axial compressive forces that lead to buckling of the profiles, lifting of the edges or outright shearing of the edge fixings. In French-speaking Switzerland, the annual temperature range on a south- or west-facing façade can reach 80 kelvins on a dark surface.

For profiled timber boards laid horizontally or vertically, the gap at the end of the board must allow for longitudinal dimensional variations as well as air access to avoid standing water. A free space of at least 5 millimetres at the ends allows moisture to drain and protects the cut ends from premature rot. This gap must be increased to 10 millimetres against window frames, flashing sills or plinth stop profiles.

  1. Checking the drilling gaugeCheck with a gauge or a standard drill bit that the sliding-point holes have the diametral clearance prescribed by the manufacturer (often 8 to 10 mm for a 5 mm screw shank), centred precisely on the substructure upright.
  2. Using a depth stop or controlled clutch disengagementSet the cladding screw gun with its specific driving nose so that screwing stops as soon as the sealing washer makes contact, without compressing the seal or deforming the panel.
  3. Fitting removable spacers at the endsInsert spacers of calibrated thickness between the ends of successive elements during mechanical fixing, then always remove them before moving on to the next bay so as not to block movement.
  4. Checking the axial freedom of the clipsMake sure by hand, with a light lateral push, that each clipped element retains its ability to slide on its rail before finally locking the alignment.

On the construction site, rigorous installation engages the responsibility of the installation team. In accordance with the Code of Obligations (CO), the contractor is liable for the good quality of its work and the careful execution of the work under art. 364 CO. Cladding blocked through negligence when screwing, or ends cut too tight, constitutes a clear execution defect that requires the whole façade to be redone in order to restore the indispensable freedom of expansion.

Managing expansion damage: diagnosis and remedial work on the construction site

On a ventilated façade, overtightening or the absence of a gap at the ends quickly shows itself under the effect of temperature swings: cracking at the fixings, splitting of the edges of composite panels, or cupping of aluminium and timber profiles. As soon as abnormal deformation is noticed, the team leader must identify the kinematic cause before any intervention: blocked slide, crushed EPDM ring or restraint at the head of the profile.

  1. Tightening audit and release of stressesPartially unscrew a series of fixings in the deformed area. If the element regains its flatness by instant relaxation, restraint from screwing is confirmed. Replace the crushed neoprene washers and set the screw gun to the required disengageable torque.
  2. Checking the torque of the fixed point and sliding pointsCheck the drilled hole diameter in the cladding. For a sliding hole, the diameter must exceed the screw shank by the calculated thermal tolerance. Re-ream the slotted holes or enlarge the circular holes to the prescribed size without altering the single fixed point.
  3. Rectifying tightly butted endsWhere two consecutive boards or panels are butted edge to edge, neatly recut the element in place with a plunge saw fitted with a guide and a depth stop to restore the minimum expansion gap at the ends.

If the client makes a complaint about an aesthetic or functional defect, the façade contractor relies on the usual contractual framework. Under standard SIA 118, the contractor carries out a joint examination of the reported defects. The technical record documents the condition of the joints, the drilling measurements and the conformity of the fixing methods with the cladding manufacturer's guidelines.

Frequently asked questions

How do you correct a composite panel that blisters between two uprights?

Blistering results from thermal expansion restrained by screws tightened fully or by holes that are too narrow. Remove the perimeter fixings to check whether only one fixed point was respected. Make sliding holes with the required gap at the centre of the slots. Refit the fixings using a depth stop or a centring sleeve to guarantee sliding without crushing the panel.

What should you do if two metal cladding boards butt against each other?

The absence of a gap at the ends generates axial stresses that deform the profiles and shear the fixings. Remove the nearest end fixing, mark out the necessary gap according to the length of the board and the installation temperature, then recut the end with a nibbler or a suitable circular saw. Treat the cut against corrosion before refitting the sliding clip.

Can a fixed point be converted into a sliding point without replacing the panel?

Yes, if the cladding is not cracked. Remove the fixing from the surplus fixed point. Using a step drill or a cutter suited to the material, enlarge the hole to obtain the sliding diameter prescribed by the system. Fit a new screw with a stop ring or a soft, uncompressed sealing washer, taking care to keep a single true fixed point per panel.

How do you set the screw gun precisely to avoid overtightening?

Always use a cladding screw gun fitted with a depth-setting nose or a disengageable mechanical torque limiter. Carry out a test on an offcut of cladding and framework. The screw head or elastomer washer must make firm contact against the cladding without compressing it or marking the surface, thus allowing lateral movement under the expansion force.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work (procedure in case of defects and complaints from the client)