🧱 CFC 221The three barriers: air, insulation, driving rainChapter 2 of 10 in the section

Airtightness continuity: treat the singular points before closing up

By the end of this chapter, you will be able to connect the vapour barrier membrane at complex singular points, treat openings for technical services using bonded elastomer sleeves, ensure the structural transitions at wall-slab and wall-roof junctions, and formalise a methodical integrity check before the installation of inner partitions or internal linings.

Key takeaways

  • Compliance with the thermal requirements of SIA 180 relies on a continuous air barrier.
  • Every opening for technical installations requires a dedicated elastomer sleeve, bonded and mechanically rolled down.
  • Wall-slab and wall-roof junctions require a bonding primer and a calculated expansion fold.
  • A visual and tactile check before closing up prevents destructive rework once the finishing work has been closed.

Treating technical openings and structural connections without breaks

Carefully laying a strip of dust-proof membrane or vapour retarder over a regular surface guarantees nothing about the overall performance of the facade if the penetrations remain open. Flows of warm, humid air escape through the points of least resistance, creating major risks of interstitial condensation within the mineral or bio-based insulation. The design and installation of the airtight barrier must meet the requirements for mass transfer and protection against moisture damage defined by SIA 180.

Choice of connection components according to the type of opening
Type of penetrationPenetrating materialPrescribed bridging systemAdhesion treatment
Electrical cables and bundlesSmooth or corrugated conduitPrefabricated multi-entry EPDM sleeveRolling down onto a clean, dust-free membrane
Ventilation and exhaust ductsRigid spiral-wound or PVC pipeFlexible elastomer collar with clampPrimer on rough substrate, stretchable tape on the duct
Metal ties and fixingsGalvanised steel or threaded rodsHigh-flexibility butyl adhesive or split cable grommetPrior degreasing of the metal with a suitable solvent
Penetrations of secondary structuresTimber profiles or attached bracketsPreformed sealing strips bonded in an envelope foldContinuous hybrid paste adhesive, with no discontinuity at corners

Junctions between vertical walls and horizontal elements in concrete or in the roof are the second recurring weak point of the closed structural work. At the wall-slab connection, the membrane must run down to the raw screed with an excess of material forming a relief loop. This accordion absorbs the shrinkage of the structural work and differential thermal expansion without subjecting the adhesive bead to direct tearing stress.

  • Mandatory application of a solvent-free bonding primer on raw concrete, masonry and porous substrates before rolling down the tape.
  • Application of an elastic MS polymer sealant from a cartridge, extruded in a regular bead 8 millimetres in diameter, without fully crushing it.
  • Continuity ensured between the vertical vapour barrier and the bituminous or synthetic flashing at the slab head or at the upstand under the slab.
  • Treatment of the wall-roof junction by maintaining a direct connection on the wall plate or the vapour barrier under the roof before the rafters are fitted.

Organising the acceptance of airtight barriers before final closing up

Once the secondary framework is hidden by plasterboard facings, composite panels or internal battening, locating and repairing a tear becomes impossible without partial demolition. The critical validation step is the responsibility of the foreman or the facade site manager: no lining fixing may begin without a documented cross-check duly recorded on the plan.

  1. Cleaning and exhaustive visual examinationSweep and vacuum the fixing areas on the floor. Visually inspect the entire length of the laid sheets to identify accidental perforations caused by self-drilling screws, missing staples or cuts from sharp tools.
  2. Mechanical and tactile probing of the bondsRun your hand along every longitudinal and transverse overlap. Check that the tape is uniformly pressed down using a roller and make sure there are no air pockets or unsealed transverse folds.
  3. Review of singular points and cornersCheck the internal and external corners of window reveals. Make sure that the preformed corner pieces or the membrane folds in a handkerchief fold are bonded onto a continuous backing bead, without tension across a void.
  4. Marking and recording in the inspection logMark the anomalies on the membrane with a high-visibility marker. Apply a repair patch extending at least fifty millimetres beyond the tear. Record the sign-off sheet clearing the reservations before signing the authorisation for lining.

Site management also involves strict coordination with electricians, plumbers and heating engineers. The rule of intervention must be clear: any opening made after the facade contractor's internal inspection must be the subject of an intervention notice for the immediate installation of an approved sleeve, failing which the envelope will not comply with the required air permeability tolerances.

Envelope junctions: wall-slab and wall-roof connection

The continuity of the airtight plane breaks almost systematically at changes of geometric plane and at the interfaces between trades. SIA 180 requires an envelope that is airtight against air transfer by convection, in order to prevent interstitial condensation and limit heat losses. For the facade contractor, these transitions tolerate no improvisation on the construction site: each bridging strip must be sized and bonded taking into account the tolerances of the structural work and differential movements.

Typical treatment of airtight connections on structural work
Singular connectionBonding substrateRecommended materialsPreparation and installation
Facade base on concrete slabRaw concrete as left by the formwork, free of laitance and dryEPDM membrane or reinforced vapour retarder with butyl adhesive tape or hybrid adhesive in a continuous beadMechanical dust removal, impregnation primer according to porosity, rolling down with a hard roller avoiding folds
Facade head against concrete slab or beamConcrete or underside of a precast elementPre-folded connection strip with textile reinforcement, solvent-free polyurethane or acrylic adhesiveInstallation of a compressed backing rod, continuous airtight sealant bead, controlled compression without interruption
Wall-roof connection (timber/concrete roof structure)Roof vapour barrier and dust-proof membrane or facade panelElastic adhesive tape with high ageing resistance, minimum width 100 mmCreation of an expansion fold of 15 to 20 mm to absorb deflection and differential shrinkage of the timber
Internal and external corners of revealsJoinery frame and masonry or sub-frameFactory-made preformed airtight corners, deformable adhesive membranesPriority installation of the corners, then overlapping of the perimeter strips by at least 50 mm with rolling down

At the junction between the wall and the roof, the facade membrane must overlap the vapour barrier laid in the roof or connect to it in a perfectly airtight manner. When two companies are involved — for example the roofer for the roof and the facade contractor for the vertical wall —, the overlap must be coordinated before the insulation is installed. Fitting a mechanical clamping batten screwed over the sealant adhesive bead guarantees the durability of the joint under wind pressures and suctions.

Technical penetrations and self-inspection protocol before closing up

Passages of ducts, ventilation conduits, electrical cables and blind fixings cross the non-load-bearing envelope. These openings are the most frequent leakage points if they are treated with simple adhesive strips cut with a cutter. The use of prefabricated EPDM sealing sleeves with a self-adhesive collar is required to match the exact geometry of the pipe.

  1. Sizing and installing the elastomer sleeveChoose an EPDM nipple diameter 15 to 20 % smaller than the actual diameter of the duct to ensure elastic tightening. Slide the sleeve onto the dust-free, degreased pipe.
  2. Bonding the collar to the substrateRemove the protective film in stages, apply the collar flat onto the membrane or the airtight panel without mechanical tension, then roll down firmly from the centre towards the edges.
  3. Securing the penetrationFit a corrosion-resistant mechanical clamp on the top of the nipple around the smooth pipe, or close the top with an airtight butyl tape for corrugated conduits.
  4. Systematic self-inspection using an inspection sheetCheck visually and by hand 100 % of the penetrations and corner connections. Record compliance in the internal report with photographs before the external cladding or the insulating lining is installed.

If an anomaly is found on a torn or poorly cut membrane, the repair is carried out with an added piece of membrane extending at least 100 mm around the slit, bonded over its entire perimeter. The use of expanding polyurethane foams to fill gaps around penetrations is strictly prohibited as a means of ensuring airtightness: these foams crack under expansion movements and do not constitute a durable airtight material within the meaning of SIA 180.

Airtightness non-conformities: managing rework and stopping before closing up

A pierced or detached vapour barrier or airtight membrane compromises the entire structure according to SIA 180. When the self-inspection reveals a torn-off bridging, an untreated penetration or an opening made by another trade after installation, the technical rule is strict: no lining, full battening or ventilated facade cladding may be closed up. As soon as a defect is found on a wall-slab connection or a technical duct, the installer records the damage with its location marked on the plan and dated photos. The team leader stops the closing up of the zone concerned.

  1. Treating accidental openingsDust the sheet with a dry cloth. Apply a piece of membrane extending at least 100 mm around the tear. Bond with a compatible hybrid sealant or roll down a dedicated acrylic adhesive tape with an application roller.
  2. Reworking penetrations without a sleeveNever inject expanding polyurethane foam as an air barrier. Cut a split elastomer sleeve, fit it to the diameter of the pipe, then close the slit with airtight tape before securing the perimeter collar.
  3. Correcting wall-slab and wall-roof junctionsIn the event of detachment on raw concrete or masonry, brush the substrate to remove laitance, apply a specific bonding primer, then press the continuous adhesive bead without crushing it completely in order to retain an elastic joint thickness.

If the designated substrate or the intervention of a third party degrades the airtight barrier, the contractor applies art. 365 CO by informing the client that this circumstance compromises the proper or timely execution of the work. Formally stopping the closing up before correction avoids costly destructive rework during the final pressurisation test.

Frequently asked questions

How should an electrical conduit passing through the vapour barrier without a prefabricated sleeve be treated?

The use of polyurethane foam is prohibited because it does not provide durable airtightness according to SIA 180. A split flexible adhesive collar with an airtight EPDM rubber cable grommet must be used, or pieces of stretchable acrylic adhesive tape must be applied in overlapping scales around the sleeve, after completely degreasing the plastic and dusting the airtight membrane.

Can an airtightness defect be corrected once the plasterboard is installed?

No. Internal linings and boards never constitute the primary air barrier defined in the technical file of the envelope. Subsequent openings for sockets or fixings create invisible leaks that cannot be located precisely without removal. The visual and tactile check of membrane bonds, wall-slab junctions and technical penetrations must absolutely take place before concealment by the internal facings.

What should be done if the adhesive tape does not stick to damp concrete at a wall-slab connection?

Surface moisture prevents the polymerisation of acrylic adhesives. Dry the area locally with a heat gun at moderate temperature, remove dust, then apply a bonding primer for porous mineral substrates. If the substrate remains saturated with water, the work must be interrupted until an acceptable moisture content is restored, because the airtight bond will delaminate under air depression.

How should the junction between the facade vapour barrier and the roof structure be sealed?

Continuity requires a minimum overlap of 100 mm between the wall membrane and the roof vapour retarder or vapour barrier. The connection is made with a certified adhesive tape or a continuous airtight adhesive bead without breaks. A deformation loop of 20 mm must be provided in the membrane to absorb the settlement of the timber without causing tearing.

Texts and standards cited

  • norme SIA 180Thermal protection, protection against moisture and indoor climate in buildings
  • CO art. art. 365 COMaterial and ground: the contractor informs the client if the material, the ground or another circumstance compromises the proper or timely execution of the work (para. 3)