Key takeaways
- Place the anemometer outside sheltered zones so that it picks up the real gusts before they reach the facade.
- Set the delay and the retraction threshold according to the wind resistance class.
- Carry out the mechanical safety test during the joint acceptance of the work.
- Hand over the maintenance documentation and state the physical limits of the sun protection system.
Aerodynamic siting on the facade and calibration of the trigger thresholds
An awning fabric or a linked-slat blind deployed during a gust of wind is subjected to instantaneous uplift forces of several hundred newtons per square metre. On a ventilated facade as on external thermal insulation, the anemometric automatic control is the sole mechanical safeguard of the whole system. Its effectiveness depends entirely on its exposure to the real airflow. Fixing the sensor in a window reveal recess, under the soffit of a cornice or in the aerodynamic wake of a balustrade creates a shielding effect that delays its activation. When the gust goes around the obstacle to hit the fabric, the emergency command intervenes too late to prevent the articulated arms from breaking or the guide rails from being torn out.
- Wind retraction threshold
- Critical airflow speed value, expressed in kilometres per hour or metres per second, whose sustained exceedance triggers the priority, irreversible raising of the sun protection fabrics until they are fully secured in the box.
The installer must place the anemometer housing or cup sensor at the highest point of the envelope concerned, ideally on the parapet or on the upper third of the cladding exposed to the prevailing winds. The support arm must offset the measuring mechanism by at least 200 to 300 millimetres from the raw surface to escape the laminar boundary layer running along the cladding. On complex facades with setbacks or deep loggias, a single central anemometer is insufficient: provide sensors for each orientation to handle local venturi effects.
| Type of sun protection | Usual permissible resistance | Recommended set threshold | Exceedance validation delay |
|---|---|---|---|
| Articulated-arm awning (drop-arm) | Up to 38 km/h (Beaufort 5) | 30 to 35 km/h | 2 to 3 continuous seconds |
| Vertical guided fabric blind | Up to 49 km/h (Beaufort 6) | 40 to 45 km/h | 3 to 5 continuous seconds |
| Linked-slat blind (CFC 221) | Up to 60 km/h (Beaufort 7) | 50 to 55 km/h | 5 continuous seconds |
Joint test procedure at acceptance and handover of the instructions
Checking the wind protection device cannot be limited to a visual inspection when the brackets are installed. In accordance with the duty to inspect under art. 367 CO, the client or its representative must be able to verify the proper functioning of the safety devices from delivery. The installation team must carry out an active simulation of the anemometric signal in front of the site management. This intervention validates the whole alarm chain: mechanical detection, transmission of the signal to the control cabinet (or the radio receiver) and the absolute priority of the raise command over the user's manual commands.
- Full deployment of the blindsLower all the fabrics or slat blinds to the maximum protection position using the remote control or the individual control.
- Simulation of the wind flowTurn the sensor cups by hand or use a portable air generator to exceed the calibrated threshold for the prescribed delay period.
- Checking the safety lockObserve the automatic start of the full retraction into the guide rails, then attempt a manual lowering command: the system must refuse the movement as long as the alarm cycle remains active.
- Checking the re-arming delayTime the calming delay (generally 12 to 15 minutes) before the automatic control gives control back to the users to redeploy the blind.
The installer must record this test in the acceptance report in accordance with standard SIA 118. The next step concerns the direct user. A blind fitted with an anemometer is not invulnerable: downdraught storm gusts have a descending attack front that strikes the fabric surface before reaching the sensor located on the roof or in the transom. The user manual handed over at the handover of the work must state formally that the automatic control is an operating aid and not an all-risks insurance policy.
Aerodynamic siting on the envelope and calibration of the retraction thresholds
The physical siting of an anemometer on the envelope tolerates no geometric approximation. To measure faithfully the dynamic load on the fabric, the sensor must absolutely emerge from the boundary layer of the building. Fixed on a ventilated facade or on rendering over external thermal insulation, it must be offset by at least 20 to 30 centimetres by means of a rigid bracket, outside the zones of aerodynamic turbulence generated by projecting corners, parapets or balcony returns. A position under an eave or in a re-entrant corner artificially shelters the device, distorting the detection of the upward gusts that tear out cantilevered fabrics. The mechanical fixing passes through the insulation build-up to the solid substrate by means of thermally broken anchors, guaranteeing the stability of the sensor without impairing the airtightness of the envelope.
The calibration of the retraction threshold depends directly on the structural strength of the installation and its type of guidance. An articulated-arm awning offers considerable wind resistance and must retract as soon as the mean wind reaches the limit values of its resistance class, whereas a vertical blind guided by rails withstands much higher pressures. The automatic control must not react to an isolated half-second gust, otherwise it generates endless opening and closing cycles that prematurely fatigue the tubular motor. Control units therefore integrate the measurement over time: the wind must exceed the threshold for several consecutive seconds to validate the roll-up command.
| Type of blind | Wind resistance | Recommended retraction threshold | Wind validation delay |
|---|---|---|---|
| Articulated-arm awning (projection > 2.50 m) | Class 1 (Beaufort 4) | 28 km/h to 35 km/h | 2 to 3 continuous seconds |
| Reinforced awning or compact model | Class 2 (Beaufort 5) | 38 km/h | 3 to 5 continuous seconds |
| Vertical blind with simple guide rails | Class 2 to 3 | 38 km/h to 48 km/h | 4 to 6 continuous seconds |
| Zip-guided blind (sealed screen system) | Class 3 (Beaufort 6) | 50 km/h to 65 km/h | 5 to 8 continuous seconds |
Inspection protocol at delivery and documentation handed to the operator
Acceptance of the installation requires a methodical check of the safety device in order to certify its effectiveness before final commissioning. Under art. 367 CO, after delivery, the client inspects the state of the work as soon as it is practicable and notifies the contractor of defects; this joint examination phase must necessarily include the weather-responsive automatic control. The installer carries out the dynamic test on site in the presence of the site management or the operator, ensuring that the control chain reacts instantly to emergency commands.
- Simulation of a wind overloadActivate the test mode of the control unit or mechanically spin the cup anemometer (using a calibrated airflow or a controlled manual drive) to exceed the set threshold.
- Checking the absolute priorityCheck that the retraction command immediately overrides any local manual command, wall switch or sun-tracking command in the course of lowering, forcing the complete closing of the fabric.
- Checking the post-alarm lockObserve the activation of the lockout delay (generally 10 to 20 minutes) preventing any manual redeployment until the lull is confirmed.
Handing over a complete, annotated user manual is the last indispensable step of the intervention. This document must record precisely the threshold value programmed at commissioning, the logic of the safety delays and the maintenance operations that fall to the user. The installer draws particular attention to winter conditions: frost, rime or accumulated foliage can block the rotation of the anemometer cups, completely paralysing the alarm transmission. The user must be instructed on the six-monthly visual check of the sensor and on the need to retract textile blinds without fail during snow or frost, conditions for which standard automatic controls are not calibrated.
Storm damage and dispute: expert assessment procedure and responsibilities
When a gust of wind bends the articulated arms or tears the fabric of a sun protection, the client's first reaction is to blame a failure of the anemometric sensor. For the facade installer and external joiner, handling this loss requires a rigorous methodology in order to establish the exact technical cause without rushing.
- Immediate securing of the siteAs soon as the damage is reported, neutralise the risk of components falling onto the public road or the terraces below. Remove the deformed projecting profiles or temporarily hang them with approved lashing straps pending full dismantling. Have the motor power supply isolated by the electrician of CFC 232.
- Joint technical surveyExamine the anemometer or the oscillation sensor before any third party intervenes. Check whether the cups turn freely or whether a foreign body is blocking them. Check for new aerodynamic obstacles that have appeared since acceptance, such as a neighbouring awning, an added canopy or potted plants that have altered the airflow at the sensing element.
- Extracting the data from the control unitDownload the event log of the automatic control. This time-stamped file shows whether the prescribed wind threshold triggered the retraction command, whether a priority manual command blocked the raising or whether a loss of radio signal between the sensor and the motor placed the system in the retracted safety position.
The comparison of the administrative documents settles the allocation of the financial burden. In accordance with art. 369 CO, the client's rights in respect of defects in the work are excluded where the defective execution is personally attributable to the client. If the commissioning report proves that the forced-air test was successful and that the manual prescribed a twice-yearly cleaning of the wind vane, mechanical blocking through fouling or deliberate disabling of the automatic control releases the contractor from any obligation to carry out remedial work at its own expense.
Frequently asked questions
Which position should be chosen for the wind sensor on a highly exposed facade?
The anemometer is installed at the point most exposed to the prevailing wind, generally on the upper third of the building or at the roof edge, at least fifty centimetres from the wall face. Never place it under a cornice soffit, in a re-entrant corner or behind deployed fabrics, because these sheltered zones systematically underestimate the real force of the gusts striking the lower fabrics.
To what value should the automatic retraction threshold be calibrated according to the wind classes?
The threshold depends on the surface area of the blind and its resistance class certified under the applicable technical standard. For a standard class one awning, set the control unit between 28 and 38 kilometres per hour. Large guided fabrics in class two allow a threshold of up to 48 kilometres per hour. Avoid higher values, which exceed the manufacturer's tolerances.
How is the joint test of the protection device carried out at acceptance?
Fully deploy the motorised blinds, then simulate a wind exceedance using an air blower aimed at the cups or by manually inducing an oscillation on the load bar fitted with an accelerometer sensor. Time the reaction of the receiver: full retraction must engage after a maximum delay of two to three seconds, recorded in the joint report.
What must the instruction manual handed to the client necessarily contain?
The document formally states that the automatic control is an emergency aid and not an absolute guarantee against violent local storms. It lists the operator's maintenance tasks: annual dusting of the vanes, visual check of the fixings on the cladding, replacement every three years of the batteries of the wireless radio probes, and the prohibition on forcing the blind out while the wind alarm remains active on the control unit.
Texts and standards cited
- CO art. 369exclusion of the client's rights in respect of defects in the work where the defective execution is personally attributable to the client (orders given contrary to the contractor's formal advice or any other cause)