🧱 CFC 221Measured performance and building envelope acceptanceChapter 8 of 10 in the section

Envelope work file: product data sheets, test records and maintenance manual

This chapter guides you step by step through gathering, filing and handing over the key documents of the work file for your ventilated facades and external joinery. You will know how to structure the data sheets of the components actually installed, record the test reports for watertightness or pull-out tests, and write a clear maintenance manual setting the service intervals essential to preserve the envelope's warranties.

Key takeaways

  • Collect the exact technical data sheets for each delivered batch as soon as the pallets are received on the construction site.
  • Always attach the pull-out test reports for the anchors and the water tightness checks.
  • Specify the preventive maintenance intervals to preserve the validity of the legal warranties on the work.
  • Hand over the complete work file at acceptance of the work to fix the traceability of the materials installed.

Gather the data sheets and test reports as installation progresses

On a lightweight facade or external joinery construction site (CFC 221), the work file is not written the day before the keys are handed over. A decade after acceptance of the work, the profile labels have disappeared, the rainscreen adhesive tapes are hidden behind the ventilated cladding and the original references can no longer be found. The technical documents must therefore be collected as the work progresses, as soon as each batch of materials is delivered.

CFC 221 envelope components and supporting documents required for the work file
Building elementTechnical document requiredKey data to record
Rainscreen and dust-proof membranesProduct data sheet and suitability certificateUV resistance, Sd value, adhesive compatibility
External thermal insulation (stone wool, PIR)Data sheet and declaration of performanceLambda conductivity, reaction to fire, absorption class
Window connection sealing tapes (compressed tapes, membranes)Product data sheet and validated field of applicationDriving-rain tightness range (Pa), Sd value
Brackets and profiles of the cladding substructureAlloy certificate and sizing calculationGrade of aluminium or stainless steel, corrosion class
Fixing anchors in masonry or concreteTechnical approval and on-site pull-out test reportPermissible load per anchor (kN), actual anchorage depth
Thermal insulating glazing installed in the revealCertificate of origin and spacer markingUg value, solar factor g, sound reduction Rw

Test reports are the second pillar of the file. For window fixing brackets or cladding substructure angles, the contractor records the static pull-out tests carried out in situ with a dynamometer in the masonry or concrete substrate. These measurements confirm that the substrate's resistance matches the calculated wind loads. Likewise, the water tightness inspection reports for threshold connections and metal flashings, carried out by targeted spray testing before the cladding is closed, must be appended with the date, the precise location by facade and the site foreman's signature.

Writing the maintenance manual and archiving the file for operation

A building envelope remains watertight and durable only if routine maintenance operations are rigorously documented for the client. The maintenance manual specifies the permitted actions, the compatible cleaning products and above all the inspection intervals. It draws a clear line between what is normal wear of a sacrificial component and what is a possible initial installation defect.

Maintenance work prescribed for joinery and ventilated facades
Component inspectedMinimum intervalMaintenance operation required
Pressure-equalisation chambers and drainage nozzles of windowsSix-monthly (spring / autumn)Removal of dust and plant debris, check of the flap
Tilt-and-turn fittings and hardware in the rebateAnnualLubrication of keeps and rollers with acid-free technical oil
Elastomer (EPDM) perimeter sealing gasketsAnnualCleaning with clean water, application of a silicone care agent
Rodent-proof grilles at the base and top of the claddingAnnualCheck of free air circulation, removal of dead leaves
External claddings (timber boards or composite panels)Every 2 to 3 yearsLow-pressure washing of soot deposits, check of fixings
External expansion joint sealantsEvery 5 yearsAdhesion test on the flanks, detection of cracking

Archiving of the work file follows the requirements of standard SIA 118, which prescribes handing over complete documentation on operation and maintenance at acceptance of the work. This file, now also handed over in a structured digital format, protects the contractor. The Code of Obligations (CO) governs the exercise of these rights: art. 367 CO provides that after delivery, the client must inspect the state of the work as soon as is practicable and notify the contractor of any defects, the client having 60 days to notify them for an immovable structure, any shorter contractual period being void. In addition, art. 371 CO sets the limitation period for the client's rights in respect of defects in an immovable structure at five years against the contractor. Handing over a detailed maintenance manual makes it possible to prove, beyond these periods or in a dispute, whether a deterioration found results from a defect in execution or from a manifest lack of maintenance by the owner.

As-built consistency and supporting documents: data sheets and test reports

Ten years after acceptance of the work, the people on the construction site have changed and only the technical documentation proves which materials were actually installed on the building envelope. The work file tolerates no generic sheet taken from a commercial catalogue: it requires the exact data sheets of the products installed, including batch numbers, declarations of performance and conformity reports. In the event of water ingress or premature deterioration of a ventilated facade, the court-appointed expert or the technical manager first examines the documented chemical compatibility between the backing rods, polymer sealants, vapour barrier membranes and the powder-coated aluminium or timber claddings. Exhaustive traceability protects the facade contractor against unjustified claims of liability.

Supporting documents and critical parameters to include in the CFC 221 work file
Envelope packageTechnical document to fileKey parameter recordedTest evidence required
Windows installed in the revealWorkshop fabrication sheet and marking labelThermal insulation value Uw and sound reduction RwTest report for air tightness and driving-rain tightness
Connection sealing membranesManufacturer's declaration of performance and safety data sheetVapour permeance Sd and permissible temperature rangeCompatibility report with fixing adhesives and primers
External thermal insulationInsulation board data sheet and batch certificateThermal conductivity lambda and fire behaviourFire protection approval certificate
Cladding substructureData sheet of fixing brackets and load-bearing profilesCorrosion resistance class and thermal breakTest report of anchor pull-out tests on the substrate

Test reports are the second pillar of the technical file. They cover the tests carried out in the workshop on prefabricated joinery as well as the destructive and non-destructive checks carried out on the construction site. For anchoring the secondary framework of a ventilated cladding in lightweight aggregate concrete or porous masonry, the facade contractor must record the in-situ tensile test reports, stating the calibrated measuring device, the tightening torque and the failure load recorded. Likewise, air tightness measurements by anemometer or smoke generator at threshold and lintel connections must be appended to the partial acceptance record before the linings are closed.

Maintenance manual, cycle intervals and archiving for operation

The maintenance manual handed over to the client distinguishes the normal ageing of components from damage attributable to a lack of maintenance. Under art. 371 CO, the client's rights in respect of defects are subject to a limitation period of five years for defects in an immovable structure. Failure to carry out the periodic checks defined in the technical manual releases the contractor from its warranty obligations where the failure of a wearing part causes water damage. The maintenance manual must give unambiguous instructions: cleaning methods for powder-coated profiles using clean water and neutral detergent, absolute exclusion of abrasive pads or ketone solvents, and instructions for greasing the linkages.

  • Annual check of the drainage and pressure-equalisation openings: clearing the water drainage slots of the frames with an air gun or plastic rod and clearing the rodent-proof grilles at the base of the cladding.
  • Twice-yearly maintenance of the hardware: lubrication of the locking rollers, checking of the perimeter clearance of the sashes and retightening of the hinge fixing screws with a torque screwdriver.
  • Three-yearly examination of the sealant joints and sealing tapes: visual inspection of adhesion on the edges, detection of surface oxidation cracking and elasticity testing with a portable durometer.
  • Archiving in a durable digital format: handing over two bound paper sets and a secure digital copy to the site management on closing of the accounts in accordance with standard SIA 118.

Archiving of the work file finally conditions future conversion or selective deconstruction work. The file must specify the exact composition of the cladding panels, the alloy types of the profiles, the concealed fixing scheme by clips or rivets, and the safe access procedures for replacing a broken insulating glass unit. A rigorously compiled file safeguards the heritage value of the building and preserves the integrity of the envelope throughout its life cycle.

Handling documentary disputes and maintenance failures

When a loss occurs several years after acceptance — water ingress at a window threshold connection, detachment of a rainscreen behind an open-joint cladding or premature deterioration of powder-coated aluminium profiles — the absence of probative documents in the work file immediately weakens the facade contractor's position. If the company cannot prove the exact designation of the sealing tapes installed, the adhesion check reports or the actual handover of the maintenance log, the presumption of non-compliant installation or installation defect is almost automatic.

If the client refuses to sign the acceptance record because the file is incomplete (missing insulation data sheets, non-compliant declarations of performance or absence of cleaning instructions for drainage), the contractor must respond in writing. A joint summary schedule should be drawn up listing the batches actually installed, retroactive certificates of conformity should be obtained from the suppliers for the batches concerned, and the formal transmission of the documents should be recorded with an acknowledgement of receipt.

Under art. 367 CO, the client must inspect the state of the work as soon as is practicable and notify the contractor of any defects; for an immovable structure, the client has 60 days to notify them. Where defects notified late result from a lack of maintenance clearly documented in the work file handed over at acceptance, CO applies: acceptance of the work discharges the contractor, except for defects that could not be detected during the regular inspection or that were intentionally concealed. The rigour applied to the initial archiving is the company's only technical and contractual shield against operating claims.

Frequently asked questions

How should you react if an installed sealing component does not match the original data sheet?

When a substitute product has been installed on the construction site, the contractor must immediately add to the work file the data sheet of the actual material and the modification approval form accepted by the site management. It attaches the manufacturer's compatibility certificate guaranteeing equivalent performance for air permeability and driving-rain tightness.

What proof should be kept to certify that the maintenance manual was handed over to the client?

The maintenance, servicing and inspection manual must be covered by a specific transmission slip, signed jointly by the site management and the client at acceptance. Keeping a time-stamped, signed digital copy in the company's definitive archive is the only proof that can be relied on in a dispute over premature wear attributable to a lack of cleaning.

Which internal test reports must absolutely be attached to the file for windows?

The file must contain the self-inspection records for the adjustment of the opening sashes, the checks on compression of the closing gaskets and the air tightness reports around the perimeter of the sub-frames. If pressurised spray tests were required by the specification or by standard SIA 118, the countersigned reports signed with the site management must be included.

Why record the colours and references of paints or powder coatings on external profiles?

Ten years after acceptance of the work, repairing a scratch from the construction site, replacing a transom cover damaged by impact or changing a glazing unit requires knowing the profile manufacturer, the exact colour chart and the surface finish (gloss, matt, satin or textured). The work file thus ensures compliant resupply without any visible aesthetic mismatch on the facade.

Texts and standards cited

  • CO art. 367after delivery, the client must inspect the state of the work as soon as is practicable and notify the contractor of any defects; for an immovable structure, the client has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); either party may request an examination by experts (para. 2)
  • COacceptance of the work: the contractor is discharged, except for defects that could not be detected during the regular inspection or that the contractor intentionally concealed
  • norme SIA 118General conditions for the execution of construction work