Skip to content
Website
🧱 CFC 221The three barriers: air, insulation, driving rainChapter 9 of 10 in the section

Façade base: plinth, capillary break and ground clearance

At the façade base, rain splash and accumulated snow directly threaten the durability of the building envelope. This chapter details the Swiss execution rules for setting the ground clearance, fitting water-insensitive plinth insulation, forming the capillary break and installing the ventilated starter profile that guarantees the air inlet of the cladding.

Key takeaways

  • Maintain a minimum clearance of 150 millimetres above the stabilised finished ground.
  • Insert a continuous sealing strip forming a capillary break under the framing battens.
  • Use only frost-resistant, water-repellent insulation in the splash zone.
  • Install a perforated starter profile serving as a drip edge and as a rigid rodent-proof grille.

Ensuring ground clearance and a capillary break against water ingress

The bottom junction of a ventilated façade or external thermal insulation is the zone most exposed to climatic and mechanical stresses. Rainwater striking external slabs or pavements splashes back as droplets laden with dust, de-icing agents and micro-organisms. In winter, layers of snow build up in direct contact with the cladding. Without suitable ground clearance, moisture penetrates by capillary action into permeable facings, soaks timber framing or setting blocks, and prematurely degrades the thermal insulation build-up.

The recognised rule of the art sets a ground clearance of at least 150 mm between the lower edge of the ventilated cladding and the finished level of the finished external works, such as paving stones, asphalt or slabs on pedestals. If the natural ground is loose, planted or covered with loose gravel, it is customary to increase this clearance up to 300 mm to limit the risk of clogging the air cavity and to protect the facing from soil splashes. An exceptional reduction of the clearance is conceivable only if a draining grated channel, connected to the rainwater drainage and regularly cleanable, is placed along the plinth.

The capillary break completes this defence against rising water from masonry or concrete foundations. The façade installer must check that the plinth waterproofing applied by the groundworker or mason rises at least to the level of the ground clearance. Under timber substructure rafters or metal sections, fitting a bituminous separating membrane or a continuous EPDM strip prevents any transfer of moisture by direct contact with damp masonry surfaces.

  • Check the official level mark and verify the thicknesses of the external finishes shown on the architect's plans.
  • Treat the waterproofing under the metal façade brackets using elastomer insulating washers or strips.
  • Lay the capillary stop strip with a minimum overlap of 100 mm between sheets on the masonry plinth.
  • Check the overhang of the bituminous or synthetic waterproofing so that it covers the upper edge of the buried plinth insulation.

Installing the rot-proof plinth insulation and the ventilated starter profile

In the 300 mm above the finished ground and over the entire zone in contact with the soil, standard façade insulation in mineral wool or wood fibre is strictly prohibited. These materials absorb splash water and condensation, lose their thermal resistance and sag. The façade installer uses waterproof closed-cell insulation boards, mainly extruded polystyrene or cellular glass, offering almost zero water absorption and high resistance to mechanical impact.

Behaviour of insulation materials at the façade base below the ground clearance
Type of materialBehaviour with liquid waterFreeze-thaw resistanceUse at the façade base
Extruded polystyrene (XPS)Negligible capillary absorptionUnaffected by repeated cyclesExposed plinth and buried section
Cellular glassImpermeable to water and vapourTotal, no degradationHeavily stressed plinth or permanent moisture
Dense mineral woolPermeable, high water retentionFrost-sensitive when wetCladding above the 150 mm clearance
Rigid wood fibreHydrophilic, risk of decompositionRapid degradation if saturatedStandard zone above 300 mm

The plinth insulation is generally thinned by 20 to 30 mm compared with the insulation of the standard façade. This setback creates a natural overhang called a drip edge. Runoff water guided by the vertical facing thus drips to the ground without wetting the basement masonry. This setback also protects the plinth boards from knocks by lawnmowers, rubble or mechanical snow clearance along pedestrian paths.

  1. Setting out and aligning the plinthDefine the starting line with a laser, applying the approved clearance height. Mark the bottom level of the framing to ensure the first course is perfectly horizontal.
  2. Mechanical fixing of the starter profileAnchor the perforated aluminium or stainless steel metal profile to the masonry substrate at regular spacing. Insert plastic thermal spacers under the rail.
  3. Fitting the rodent-proof grilleCheck that the free perforation area meets the minimum air inlet section required for ventilation while having meshes or slots smaller than 5 mm to block rodents and insects.
  4. Connecting the façade rainscreen membraneRun the flexible rainscreen membrane down over the vertical upstand of the starter grille, then bond the junction with a waterproof acrylic adhesive tape to shed water outwards.

Careful execution of these fixing and physical protection details at the base of the building prevents any rotting of the load-bearing framing elements. By strictly observing the ground clearance, the capillary break and the free air circulation through the perforated starter profile, the non-load-bearing envelope retains its rain-tightness and thermal performance for its entire service life.

Plinth geometry, ground clearance and moisture protection

The façade base is a critical zone of the architectural envelope. Exposed to surface runoff, rain splash and standing snow, this junction requires a clear transition between superstructure and infrastructure. If the facing ran down to ground level without precautions, water would penetrate the wall build-up, wet the insulation above and cause premature damage, such as rotting of substructures or spalling of renders under frost. To prevent such defects, the ground clearance relative to the finished ground requires a minimum distance of 30 cm over bare soil or facing a lawn. This height protects the façade against splash and prevents the cladding from being buried during snowfall. Where a draining cleaning strip of washed gravel at least 30 cm wide or an effective grated channel is installed, this clearance may be reduced to 15 cm.

Layout and plinth materials according to the external surroundings
External surfaceMinimum clearancePlinth insulationDrainage provision
Topsoil or lawn30 cmXPS or cellular glassGround sloping 2 % away from the wall
Impermeable ground (asphalt, slabs)30 cmHigh-density XPS or cellular glassSlot channel or drainage grating
Washed gravel strip (16/32)15 cmXPS with rough or waffle surfaceDrainage collected at the foot of the footing

The durability of the plinth depends on the water behaviour of its insulation and on the tightness of its capillary break. In this zone subject to splash and snowmelt, permeable fibrous insulation materials are banned. The façade installer uses rigid closed-cell boards of extruded polystyrene or cellular glass, able to retain their thermal properties under temporary immersion and during freeze-thaw cycles. Behind this insulation, the capillary break blocks the migration of water from the foundation concrete to the walls above. It consists of a bituminous or synthetic membrane welded onto the reinforced concrete load-bearing wall, rising 15 to 30 cm above the finished ground, completed by a waterproofing coating under the insulation boards. This continuous arrangement prevents any capillary rise towards the standard façade.

Installing the ventilated starter profile and the capillary breaks

  1. Level survey and setting outCheck the finished ground level against the site benchmark. Mark the base line with a laser on the raw substrate to guarantee the required ground clearance.
  2. Installing the capillary breakApply the waterproofing membrane to the prepared concrete substrate, ensuring a watertight overlap above the maximum splash level.
  3. Fixing the plinth insulationLay the extruded polystyrene or cellular glass boards by bonding and mechanical anchoring, with tight joints and no thermal bridges.
  4. Fitting the starter profileMechanically fix the perforated angle profile to the substrate. Check that it is level to ensure water drainage and alignment of the cladding.

The ventilated starter profile performs a dual function: it initiates the ventilation air cavity of the lightweight façade and blocks the passage of small rodents and insects. Made of perforated aluminium sheet or folded stainless steel, it provides a free ventilation opening of at least 50 cm² per linear metre, needed to start the upward thermal draught behind the cladding. Its 3 to 5 mm perforations prevent rodents from entering without breaking the air pressure drop. This profile incorporates a metal flashing forming a drip edge, projecting at least 20 mm in front of the outer face of the plinth insulation. This geometry throws runoff water away from the waterproofing head and protects the lower edge of the cladding against direct ingress. The profile is fixed with stainless steel screws suited to the substrate, at regular spacing not exceeding 50 cm to prevent any deflection of the sheet under wind loads.

Handling non-conformities at the façade base and remedial measures

On the construction site, the façade base concentrates the major interface conflicts between the façade installer, the mason and the external works contractor. The most critical non-conformity occurs during late backfilling: the landscaper or groundworker places topsoil or gravel well above the planned level, burying the ventilated starter profile and reducing the ground clearance below the minimum threshold of 150 mm required against splash and snow accumulation. Blocking the perforations of the rodent-proof grille cuts off the low air inlet of the cavity, while direct contact of soil with a lightweight cladding or hydrophilic insulation triggers continuous capillary soaking of the wall.

When the finished ground level has been changed without consultation or the top of the concrete plinth turns out to be too low, two technical remedial measures make it possible to deal with the defect without heavy removal. The first solution consists of forming a perimeter drainage trench fitted with a removable metal grated channel, decoupled from the wall, keeping the drip edge of the profile at least 50 mm above the grating. The second solution requires cutting back the base of the framing to raise the start to the specified level, then protecting the lower zone with extruded polystyrene boards sealed by a metal flashing and an elastomeric sealant.

  1. Level survey and recording of the deviationCheck the clearance height with the laser level against the levelling pegs. If the clearance is less than 150 mm, draw up a written record with photos.
  2. Formal notification to the clientUnder art. 365 para. 3 CO, if the ground or a circumstance jeopardises the execution of the work, the contractor informs the client. This written notice suspends the installation of the facings.
  3. Rectifying the drainage and ventilationClear the materials blocking the perforated profile, restore the minimum ventilation section of 50 cm² per linear metre and connect the water-shedding flashing before approval.

Frequently asked questions

What minimum ground clearance must be observed below the ventilated starter profile?

On loose ground or topsoil, the minimum ground clearance is 150 mm between the lower edge of the starter profile and the finished ground. This distance protects the insulation and the facing from driving-rain splash and snow deposits. On a stabilised terrace or a draining gravel bed with a grated channel, this clearance may be lowered to 50 mm, provided the drip edge remains perfectly clear.

Which thermal insulation should be installed in a plinth zone exposed to moisture?

In the plinth and up to 300 mm above the finished ground, ordinary mineral wools are prohibited because of their sensitivity to water. The façade installer uses only closed-cell insulation boards, mainly extruded polystyrene or cellular glass. These rot-proof materials retain their thermal and mechanical performance in damp conditions, resist frost and suffer no structural sagging under the effect of temporary ingress or ground moisture.

How is the capillary break ensured between the concrete plinth and the rainscreen façade?

The capillary break is obtained by interposing a continuous waterproof membrane between the masonry top and the framing or façade insulation. A welded bituminous sealing strip or an EPDM elastomer sheet at least 1.2 mm thick is used. This membrane must overhang by 20 mm towards the outside to form a drip above the plinth joint, blocking any rise of liquid water towards the timber rafters, metal sections or insulation boards.

Why must the ventilated starter profile incorporate a perforated grille?

The starter profile closes the bottom of the ventilated cladding while guaranteeing permanent upward air circulation. Its calibrated perforation provides a minimum ventilation section of 50 cm² per linear metre, needed to dry out the cavity and remove condensation moisture. It also acts as a rodent and insect barrier: the openings must not exceed 5 mm in order to prevent any damage to the thermal insulation by pests.

Texts and standards cited

  • CO art. 365Material and ground: contractor's notice to the client in case of a defect or circumstance jeopardising the proper execution of the work

In the same section