Key takeaways
- Standard protective films baked by ultraviolet rays become impossible to peel off after three months.
- Any fresh mortar or mineral render splash is removed immediately with plenty of water, without rubbing.
- Chlorinated solvents, acetone and metal scrapers irreparably damage coatings and glass.
- The joint inspection record at acceptance before removal protects the joiner against damage caused by third parties.
Controlling film exposure time and neutralising mortar
On an external joinery construction site in French-speaking Switzerland, a powder-coated profile or an aluminium cover scratched by a heat gun cannot be repaired invisibly on site: the damaged element has to be replaced. The factory protection applied to subframes, fixed frames and opening sashes serves only to protect the metal or polymer against micro-scratches during transport and lifting. As soon as the element is installed in the reveal, this adhesive tape becomes an operational trap if it is exposed to weather and direct sunlight beyond the manufacturer's tolerances.
| Type of protection | Permitted substrate | Maximum UV exposure | Behaviour on removal |
|---|---|---|---|
| Transparent or blue factory film | Raw aluminium, PVC profiles | 4 to 6 weeks | Tearing if overheated, adhesive residues |
| UV-resistant building adhesive tape | Powder coating, anodised | 3 to 6 months according to data sheet | Clean removal leaving no marks |
| Waterproof polythene sheet on timber frame | Painted or glazed-stained timber joinery | Undetermined (if ventilated) | Risk of overheating and trapped condensation |
Splashes of levelling mortar, mineral base render for external insulation and screed cement have a strongly alkaline pH of between 12 and 13. On contact with an anodised or powder-coated surface, the alkalinity chemically attacks the oxide layer or the polyester varnish, creating permanent discolouration stains in less than 24 hours. At the same time, the quartz sand contained in these binders acts as a destructive abrasive if a worker makes the mistake of rubbing the splash dry or with an ordinary sponge.
- 1. Abundant rinsing without mechanical pressureImmediately flood the mineral splash with clean water using a gentle jet or a low-pressure sprayer to soften and dissolve the binder without displacing the silica grains.
- 2. Lifting off perpendicularlyRemove the softened crust by lifting it with a flexible plastic spatula or a microfibre cloth saturated with water, never scraping the surface parallel to the profile.
- 3. Chemical surface neutralisationClean the affected area with diluted pH-neutral soap to stop any residual alkaline attack, then dry with a clean microfibre cloth.
Selecting the cleaning chemistry and securing the joint acceptance
End-of-construction-site cleaning requires strict compatibility between the chemistry used and the nature of the façade coatings. Powder-coated aluminium profiles require strictly pH-neutral products, between 5.5 and 8. Aromatic solvents, pure ketones, acetone, trichloroethylene and turpentine are expressly prohibited by industry guidelines: they soften the powder coating and destroy the seal of elastomer jointing sealants. To remove stubborn adhesive traces, only pure ethanol or isopropanol may be used, after a prior test on a concealed area.
Mechanical removal tools must be kept out of the hands of cleaning crews. The use of razor blades, uncertified metal glass scrapers, steel wool or abrasive pads creates micro-scratches visible in raking light, both on heat-treated float glass and on coatings. A surface scratch on toughened or laminated glazing is a major aesthetic defect that is not acceptable when the work is handed over to the client.
- 1. Methodical removal of protective strips and filmsPull the films at a constant angle of 90 degrees to the substrate, at an ambient temperature above 10 °C, to avoid the adhesive being torn off.
- 2. Gentle cleaning with demineralised water and microfibreWash the glazing and frame members with a neutral biodegradable detergent free of ammonia, followed by manual squeegeeing with a flawless soft rubber blade.
- 3. Drawing up the joint acceptance inspection recordCheck the integrity of the joinery in the presence of site management, record the condition of the surfaces in writing and photograph any damage caused by third parties before the scaffolding is dismantled.
This joint inspection record, drawn up as soon as the building is made weathertight and before the secondary finishing trades come in, formally closes the installation work. If chips or scratches attributable to third parties are found, the cost of replacing a complete sash is in the order of CHF 1200 to 3500 depending on the acoustic or thermal performance of the element, an amount that must be charged immediately to the insurance of the responsible company in order to protect the margin of the joinery package.
Degradation of adhesive films under UV and removal without mechanical damage
Factory-applied protective films on powder-coated or anodised aluminium profiles, as well as on PVC, are intended exclusively for transport and brief handling phases. As soon as the element is installed on the construction site, exposure to solar radiation starts photodegradation of the adhesive mass, generally based on water-phase acrylic resin. Under the combined action of heat and ultraviolet rays, the polymer chains break and then cross-link: the adhesive migrates into the microstructure of the varnish or the pores of the anodising. Exceeding the permissible duration turns the film into a brittle skin that crumbles in small shreds and leaves an indelible sticky deposit.
The behaviour of masking tapes applied during façade connections or rendering work demands even stricter vigilance. A paper tape or an entry-level polyethylene film tolerates no more than 48 to 72 hours under direct sunlight before this adhesive transfer begins. Only specific tapes with UV-stabilised synthetic rubber adhesives can stay in place for up to six weeks outdoors. When the façade contractor applies the reinforcing mesh or the finishing render on the external insulation, the tapes must be removed immediately after the coat is applied, before the cementitious matrix has fully dried.
| Type of protection | Permitted substrate | Maximum UV exposure | Method of residue removal |
|---|---|---|---|
| Factory polyethylene film (acrylic adhesive) | Powder-coated aluminium, PVC coloured throughout | 6 to 12 weeks depending on orientation (south/west critical) | Soaking with warm soapy water, plant-ester-based solvent, nylon squeegee |
| Cloth-backed paper tape for rendering (orange/blue) | Render beads, anodised aluminium thresholds | 1 to 3 weeks according to manufacturer's data sheet | Diluted isopropyl alcohol or neutral plant emulsion, wiping with microfibre |
| Adhesive-free stretch film (electrostatic adhesion) | Insulating glazing, interior faces | Not exposed to high heat (risk of coalescence) | Continuous manual peeling at 45°, washing with demineralised water using a glass wetter |
Attack by alkaline binders and joint protocol before final removal
Mortar discharges, fresh concrete and mineral render runs have a strongly alkaline pH of between 12 and 13.5. On contact with mixing water, the free calcium hydroxide attacks the surface aluminium oxide by chemical etching. On an anodised frame, this reaction dissolves the protective anodic layer, creating permanent matt whitish halos. On a powder coating, the organic binder undergoes saponification, which dulls the gloss and alters the colour. As soon as a splash reaches a profile or glazing, cleaning must be carried out without delay with plenty of water, without excessive pressure and by continuous running water, in order to dissolve and remove the binder before setting begins.
Direct mechanical rubbing of a grain of mortar or siliceous sand on a coated or glazed surface produces irreversible micro-scratches. It is strictly forbidden to use scouring powders, abrasive sanitary sponges, strong mineral acids such as hydrochloric or phosphoric acid to remove laitance, as well as chlorinated or aromatic solvents such as acetone, toluene or trichloroethylene. The cleaning protocol prescribes pH-neutral aqueous solutions (between 6 and 8), formulated with non-ionic surfactants. On glass, stubborn lime residues are treated with a soft felt pad soaked in acetic or citric acid diluted to a low concentration, followed by abundant rinsing.
- Visual check through the filmInspect the general condition of the installed elements through the transparent protective films before plasterers, painters or façade contractors begin work, in order to document any prior impacts.
- Securing risk areasSupplement the factory protection with non-adhesive interposition strips on the fixed frames receiving render stop profiles or plinth flashings.
- Coordinated removal of the filmsPeel off the protective films at a continuous angle of 45 to 90 degrees, without mechanical jerks, immediately after the end of the dirty, high-risk phases.
- Preliminary non-abrasive cleaningWash all visible faces with clear water and a neutral detergent, then rinse abundantly before any natural drying.
- Official joint inspection recordCarry out the visual conformity check according to the surface evaluation criteria for joinery, then record the results in a protocol signed jointly with site management.
Under standard SIA 118, the contractor's work must be carefully examined at the time of handover. In accordance with art. 367 CO, after handover the client examines the condition of the work as soon as is customary in the ordinary course of business and notifies the contractor of any defects. If the installer removes their films without arranging a prior joint inspection record with site management, they bear the risk that damage caused later by other finishing trades will be attributed to them. Conversely, leaving the protective films in place after acceptance in order to shift this responsibility transfers custody of the work without a clear contractual basis, risking a complex dispute under art. 368 CO if the adhesive finally proves impossible to peel off.
Managing claims: surface damage and acceptance disputes
On a construction site in French-speaking Switzerland, the discovery of a powder coating pitted by laitance or laminated glass scratched by a scraper immediately triggers an interface conflict. As soon as surface damage is found, the foreman stops all cleaning operations on the affected element to freeze the situation. Any further rubbing aggravates the damage and ruins any claims.
- Freezing operations and formal notificationImmediately stop peeling off tapes or scraping off render crusts. Summon site management and the adjacent trades (plastering, rendering, masonry) for a joint inspection record on site.
- Methodical survey and traceabilityPhotograph the profiles and glazing in raking light, measure the extent of the splashes and record the precise condition of the remaining peelable films in the site diary, noting the orientation and the date of installation.
- Technical expert assessment of the substrateCall in the aluminium system supplier or the insulating glazing manufacturer. The assessment determines whether micro-scratches on glass can be polished with cerium oxide or whether the alkalinity of the mortar has corroded the anodising sub-layer.
Under art. 367 CO, after handover the client examines the condition of the work as soon as is customary in the ordinary course of business and notifies the contractor of any defects. For building construction, this notification period is 60 days. Unilateral removal of the films without a prior record transfers the burden of proof to the installer: without a joint inspection record, the client will systematically attribute scratches to your crews.
If replacing a frame under warranty proves unavoidable following indelible chemical staining, the cost of remedial work (removal of the external insulation, air-tightness connection, new joinery) is charged to the party responsible for the splashes on the basis of the initial joint inspection record, in accordance with standard SIA 118.
Frequently asked questions
How should you react if a protective film has baked in the sun and will not peel off without tearing?
Never use a metal scraper, cutter blade or heat gun, which damage the frame's varnish. Soak the film with a specific adhesive-residue cleaner based on natural oils, let it work under a damp cloth, then peel the strip at an angle of 45 degrees with a flexible Teflon spatula without forcing.
A rendering company has splashed mortar onto raw aluminium profiles: what is the emergency treatment?
Rinse immediately and abundantly with clean neutral water without rubbing, to dissolve the mineral binders by water saturation. Sand grains must never be wiped off dry, as this would scratch the aluminium. If the mortar has hardened, apply compresses of citric acid diluted to a low concentration to neutralise the alkalinity, then rinse abundantly with water.
Which cleaning products are expressly prohibited on treated glass and powder-coated frames?
Aromatic solvents such as acetone and toluene, nitrocellulose thinners, as well as strong acids and highly alkaline detergents (caustic soda, potash) are strictly prohibited. Likewise, scouring powders, steel wool and abrasive sponges irreversibly scratch the coating and destroy the pyrolytic or magnetron layer of selective glazing.
Who must bear the financial cost of the final cleaning of the protection on external joinery?
Under the usual award rules for Swiss finishing work, the installer delivers their joinery with clean, intact factory films. Removal of the adhesives and end-of-construction-site cleaning are the responsibility of the company designated by the site management contract, generally during a joint protocol drawn up before the building cleaners start.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work
- CO art. art. 367 COExamination of the condition of the work by the client and notification of defects within the legal period