🧱 CFC 224Roof covering: tiles, slates and installation on battensChapter 3 of 10 in the section

Fixing tiles: which rows, which zones, and what the wind requires

This chapter details the mechanical fixing rules for small-element roof coverings according to SIA 232/1. You will be able to identify the zones subject to wind suction, define the proportion of tiles to be fixed in the field of the roof as well as at the verges, and select the appropriate fastening method according to the pitch and the battening.

Key takeaways

  • SIA 232/1 requires a fixing pattern suited to wind exposure.
  • Verge, ridge and eaves zones systematically require reinforced mechanical anchoring.
  • The field of the roof is fixed in a mixed pattern or in full, depending on the calculated suction.
  • The choice between a stainless steel clip and a wood screw depends on the tile model.

Identifying suction zones and determining nailing or clipping ratios

On a pitched roof, the wind does not act as a uniform direct push, but mainly as suction caused by the eddies created at the edges. SIA 232/1 defines the rules of the trade for preventing the uplift of clay or concrete roof coverings. The roofer never lays a covering at random: each roof slope is broken down into geometric zones with distinct aerodynamic stresses, namely the side verges, the eaves line, the ridge and the central field of the roof.

Verge suction zone
Peripheral strip of a roof slope subject to maximum turbulence during wind events, where the suction acting on the roof covering elements is the strongest on the slope.

The width of the verge strip depends on the geometry of the building, in particular its height and its overall width. In these peripheral strips and along the break or ridge lines, uplift by local suction is critical. The basic rule therefore prescribes full mechanical fixing of all the pieces laid at the outer limits of the slope: verge tiles, eaves tiles and the top row under the ridge are systematically fixed individually.

Indicative distribution of fixings according to the slope zone
Slope zoneStandard exposure levelHigh exposure (ridge, altitude)Recommended fastening method
Verges and corners100% of tiles fixed100% of tiles fixedCorrosion-resistant screws or dedicated clips
Eaves and ridge100% of tiles fixed100% of tiles fixedScrews to the batten or ridge clips
Standard field of the roof1 tile in 3 to 1 in 2100% of tiles fixedSuitable side-lap clips

In the field of the roof, the proportion of elements to be fastened varies continuously. A sheltered roof on the Swiss Plateau with a moderate pitch may tolerate unfixed laying in the central area if the weight per unit area is sufficient to offset the suction. As soon as the pitch increases, the structure exceeds the reference heights or it is located in an exposed area such as a lakeshore or a Jura ridge, fixing every third tile, every second tile or every tile becomes mandatory to ensure the stability of the structure.

Selecting clips and screws in line with the mechanical stresses

The suction loads are transmitted from the tile to the battening by means of specific metal connections. Ordinary smooth nails are prohibited on modern roofs in favour of treated wood screws or clips made of stainless or hot-dip galvanised steel wire. The choice of fittings depends directly on the shape of the interlock, on whether or not the tile manufacturer has pre-drilled nail holes, and on the thickness of the batten.

  1. Checking the lug and the interlockCheck the side profile of the tile in order to choose an eyelet clip, a side clip or an under-batten clip that is compatible without forcing the fit.
  2. Installation on cut tilesAt valleys, hips and penetrations, drill the triangular offcuts with a carbide bit and screw without over-tightening to avoid breaking the clay.
  3. Fitting side-lap clipsDrive or staple the clip into the side of the batten, then hook it onto the side lap of the upper tile, observing the direction of interlock.

Screwing remains the preferred fastening method on accessory tiles. Verge tiles with a return have an oblong hole intended to receive a stainless steel screw with an integrated neoprene washer. The screw must penetrate at least 25 mm into the timber without splitting the verge edge or creating brittle stress in the ceramic element. For plain tiles laid with a full or double lap, clips nailed to the top edge of the batten prevent vertical slipping under the combined effect of wind and self-weight.

As regards responsibilities on the construction site, the contractor remains bound to comply with the technical rules of his trade. If the design of the structure proves manifestly non-compliant with the exposure requirements, or if the choice of fixings does not provide the required holding strength, civil law governs the contractual relationship between the client and the professional. Under art. 365 CO, the contractor must notify the client of any circumstance compromising the proper or timely execution of the work, failing which he bears the consequences.

Installing fixings at verges, ridges and eaves according to SIA 232/1

On a pitched roof slope, the uplift loads due to wind are not transmitted uniformly. Geometric singularities cause airflow separation, which locally multiplies the uplift forces. SIA 232/1 sets the anchoring rules for these particularly exposed peripheral strips, where the mere self-weight of the clay or concrete is no longer enough to ensure the mechanical stability of the structure.

At the eaves, the first row directly takes the upward thrust of the air compressed against the façade, compounded by the turbulence generated by the gutter. Each eaves tile must be mechanically secured to the first batten or to the eaves board. Two solutions prevail on the construction site: direct screwing through the nail hole provided by the manufacturer, or the use of a specific metal bracket fixed to the edge of the timber. Screwing requires a sealing washer under the head so as not to split the lug when tightening.

The side verge lines are another critical zone. Whether with verge tiles with a return or with a connection under a metal verge flashing formed by the plumber, the anchoring is complete. Each verge element receives at least one stainless steel wood screw or one hot-dip galvanised ring-shank nail penetrating at least 30 mm into the verge rafter or the reinforced counter-batten. Finally, the top row under the ridge or hip absorbs the suction vortices at the crest: it must also be fixed piece by piece before the ventilated closures and mechanical ridge tiles are fitted.

Site organisation and densification of fixings in the field of the roof according to exposure

Beyond the peripheral lines treated at 100%, the roof covering in the field of the slope requires an anchoring plan proportionate to the topographical situation and the geometry of the roof. On sheltered lowland, the roofer often lays the field tiles loose on the battening. However, as soon as the pitch exceeds 45°, altitude increases or the building stands at the edge of a forest, on a hilltop or on a lakeshore, aerodynamic suction requires regular nailing or clipping in alternating patterns.

Recommended fixing pattern according to wind exposure and roof configuration
Roof zoneNormal exposure (sheltered lowland)Medium exposure (pitch > 45° or wind corridor)Severe exposure (Jura ridges, Prealps)
Eaves line and verge row100% fixed (screws or clips)100% fixed (stainless screws)100% fixed (screws with EPDM washers)
Roof corners (verges × ridge)100% fixed over 1 m to 2 m100% fixed with hip reinforcement100% fixed (structural anchor screws)
Under-ridge row100% fixed to the top batten100% fixed to the top batten100% fixed with metal brackets
Field of the slope (central zone)Loose laying (unless local requirements apply)1 tile in 3 (regular staggered pattern)1 tile in 2 or 100% clipped
  1. Marking out the edge zones on the battensMark out in chalk on the counter-battening and battens the extent of the corner and verge zones. The width of this strip depends on the height of the building and its footprint dimensions, in accordance with the project's engineering data.
  2. Choosing the mechanical fastener suited to the battenMatch the type of clip to the tile profile and to the batten section (commonly 24 × 48 mm or 30 × 50 mm). Slope clips hook onto the side or are driven into the edge of the timber without raising the interlock of the upper tile.
  3. Staggered laying and checking the rhythmApply the prescribed distribution in the field of the slope from the first standard rows. For a pattern of one tile in three, alternate the fixings on each row to avoid forming unsecured bands vulnerable to uplift by wave effect.

For collective safety, these elements are installed in compliance with the access and fall-arrest requirements. According to art. 41 OTConst, appropriate measures to prevent falls must be taken from a fall height of more than 2 m, by means of a roofer's catch platform or a guardrail suited to the slope pitch. Finally, when roof tile bundles are temporarily stored on the roof before fixing, the foreman ensures that the loads are spread evenly over the rafters so as not to distort the supporting structure.

Handling anchoring non-conformities and working in high winds

On a pitched roof, an anchoring failure or an uneven distribution of fixings endangers the mechanical stability of the structure against suction forces. As soon as battening shows excessive play, screws spin freely in the roof timber or slope clips prove unsuited to the actual lap, the foreman must have work stopped on the section concerned. In accordance with art. 365 CO, if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance compromises the proper or timely execution of the work, the contractor informs the client. The written notice must state the exact location of the exposed slopes and the deviation found from the structural assumptions.

  • Immediate pull-out check on doubtful batten sections: verification of the tightening torque and of the effective anchorage thickness.
  • Replacement of stripped screws with a larger diameter or re-fixing at an offset position with a compliant spacing in sound timber.
  • Recording in the site diary of the verge and corner zones requiring full clipping not initially planned.
  • Placing of temporary weighted tarpaulins over unsecured rows before work is interrupted.

During storms or unforeseen gusts occurring while laying is in progress, collective safety takes priority. Access to unprotected slopes is stopped. The ordinance on construction work requires work stations to be secured against falling objects or materials. Bundles of tiles supplied onto the battens must be brought back down immediately or strapped with flat straps directly to the rafters. Where tiles have been lifted on a completed slope, corrective work requires a lifting platform or the reinstatement of a compliant working scaffolding.

Frequently asked questions

How to react if the existing battening is too thin for the screw depth?

SIA 232/1 requires reliable mechanical anchoring in the supporting timber. If the counter-battening or batten does not offer the thickness required for the thread to penetrate, the screw risks going through the sub-roof membrane. Fit battening of a suitable section, or go through it to anchor the fixing directly in the supporting rafter, ensuring the required local sealing.

Can a zinc-plated slope clip be replaced by a stainless steel clip on an alpine construction site?

At altitude or in highly exposed areas, the combined stresses of wind suction and dense snowmelt call for increased resistance to corrosion and tension. Replacing zinc-plated wire with stainless steel of a suitable grade avoids premature failure through mechanical fatigue, provided that its section and profile match the installed tile model exactly.

What to do when the verge tiles have no factory nail holes?

Drilling by hand with a hammer or chisel weakens the clay and creates invisible micro-cracks that burst at the first frost. Use a drill without hammer action fitted with a diamond or carbide bit suited to the material, water-cooled if necessary, then fix the piece to the verge with a stainless steel screw fitted with a neoprene sealing washer.

What solution to apply if a gust displaces tiles in a field-of-slope zone?

This failure points to a local underestimation of aerodynamic suction or to an insufficient fixing density compared with SIA 232/1. The foreman must record the incident, remove the destabilised rows and recalculate the anchoring plan. The repair requires moving from partial fixing to systematic clipping of every second tile, or even of every element, in this critical zone.

Texts and standards cited

  • norme SIA 232/1Pitched roofs: design and execution rules for small-element coverings and their fixing.
  • CO art. 365Defective material and ground: obligation to inform the client immediately if circumstances compromise the proper or timely execution of the work.