Key takeaways
- The slope length is measured from the tilting batten nose to the bearing edge under the ridge.
- The longitudinal interlock play absorbs deviations without requiring a cut on the last course.
- The batten section depends directly on the rafter spacing and the snow load.
- Marking out with a chalk line on both sides ensures strict parallelism of the courses on the counter-battens.
Determining the useful length and calculating the spacing without cutting
Laying an interlocking roof covering requires millimetre-accurate setting out of the battens on the counter-battening. Any setting-out error at the foot of the slope inevitably results in an odd-sized course at the ridge, requiring unsightly cuts that are vulnerable to wind and costly in labour. The aim of a successful spacing is to fit the interval between each course within the permissible exposed-lap range of the chosen model, absorbing the tolerances of the structural work.
- Permissible exposed lap
- Visible length of the tile exposed to the weather, lying between a minimum value (maximum overlap ensuring weathertightness on low pitches) and a maximum value (minimum overlap required by the manufacturer to prevent water being driven back under wind pressure).
- Defining the eaves line and fixing the first battenPosition the tilting batten or the doubling-up batten at the eaves edge, allowing for the projection required in the flashing or the gutter. Raise this first bearing by a thickness equal to the tile heel so as to keep the same laying angle as the rest of the slope.
- Positioning the batten below the ridgeFix the last top batten, observing the dimension recommended below the ridge line. The top of this batten must allow the ridge tiles or ventilated under-ridge pieces to fully cover the last course without mechanically butting against the opposing tile ends.
- Measuring the useful distanceUsing a steel tape, measure the exact distance $L$ between the upper edge of the second batten (first intermediate batten) and the upper edge of the batten below the ridge. This dimension must be taken on both side edges and at the middle of the roof slope to identify any out-of-squareness of the roof space.
- Calculating the number of spaces and the average exposed lapDivide the length $L$ by the average exposed lap recommended in the data sheet. Round the result to the nearest whole number to obtain the exact number of intervals $N$. Then calculate the actual as-built exposed lap $P = L / N$. Check immediately that $P$ lies strictly between the minimum and maximum exposed lap permitted for the model and the wind zone.
Timber section, rafter spacing span and chalk-line alignment check
Battens perform a structural load-carrying function: they transmit to the counter-battening the self-weight of the roof covering, the snow load and the temporary working load of a roofer. The choice of section depends on the clear distance between counter-battens, itself determined by the spacing of the load-bearing rafters of the roof structure.
| Maximum rafter spacing | Minimum rough section | Usual use on pitched roofs |
|---|---|---|
| Up to 600 mm | 24 x 48 mm | Small exposed laps, lowland areas, moderate snow loads |
| Up to 750 mm | 30 x 50 mm | Standard size for clay tile coverings, altitude below 800 m |
| Up to 900 mm | 40 x 50 mm or 40 x 60 mm | Large spacings, pre-Alpine regions or heavy concrete coverings |
Once the actual exposed lap $P$ has been determined, marking out on the construction site is done by successive marking on the edge counter-battens. To eliminate the cumulative transfer errors caused by using a folding rule, the team transfers the dimension with the steel tape unrolled in a single run from the low point, or uses a gauge rod made in the workshop with a metal stop.
The chalk line, with blue or white chalk, is snapped between the end marks. On slopes wider than 10 metres, the line is supported by an intermediate mark at the centre to avoid a false sag caused by the line deflecting under its own weight. The battens are fixed by nailing or screwing through at least 2.5 times the thickness of the timber into the counter-batten, taking care to stagger the joints over the supports.
Marking-out method: eaves start against ridge reference
To eliminate any risk of cutting at the head of the slope or an unsightly offset under the ridge piece, the method of transfer onto counter-battens must neutralise the dimensional uncertainties of the roof structure. The roofer never lays battens by blindly stacking a gauge rod from the eaves towards the ridge: the millimetre error accumulated over twenty or thirty courses inevitably results in a floating ridge tile or a cut last course, which is prohibited for weathertightness against spray.
- Fixing the fixed point below the ridgeDetermine the position of the last upper batten according to the geometry of the ridge tile and its ventilated under-ridge piece. This head batten forms the fixed upper stop: its upper edge is marked out at the distance prescribed by the data sheet of the ridge component.
- Setting out the eaves tilting courseLay the first batten or the eaves edge board to ensure the exact overhang of the tile into the gutter or hanging gutter (generally one third of the diameter of the outlet). Double up or raise this first batten by a thickness equal to the tile heel so as to maintain the same laying pitch as the rest of the slope.
- Measuring the effective slope length between fixed marksUsing a steel tape, measure the exact dimension between the upper edge of the eaves batten (second actual course) and the upper edge of the batten below the ridge. Take this measurement on both edges and at the middle of the slope to detect any out-of-squareness of the roof space.
- Dividing and distributing the average incrementDivide the measured distance by the average theoretical exposed lap recommended by the manufacturer. Round the result up to the next whole number to obtain an exact number of intervals with no remainder. Divide the total distance again by this number of intervals to find the final as-built exposed lap, which must lie within the permissible range of the model.
- Simultaneous marking with parallel linesTransfer the calculated as-built increment onto each edge of the roof, then snap a chalk line between the marks every three or four courses in order to continuously take up local deflections of the counter-battening without deviating from the general alignment.
Setting out at singular points and execution tolerances
Compliance with the as-built exposed lap does not stop at the side edges: roof penetrations (roof windows, dormers, chimney stacks) require the batten network to be perfectly aligned below and above the obstacle. A poorly handled interruption breaks the continuity of the horizontal lines, forcing the craftsman into local adjustments that are disastrous for appearance and water run-off.
| Clay tile family | Indicative nominal exposed lap | Permissible longitudinal play | Slope-fitting strategy |
|---|---|---|---|
| Mechanical plain tile (interlocking) | 280 to 340 mm | ± 10 mm to ± 15 mm | Full absorption of roof structure tolerances over the slope length |
| Traditional plain tile (double lap) | 145 to 165 mm | No play (rigid stop) | Exposed lap varied by sliding before nailing |
| Ribbed or corrugated tile | 330 to 380 mm | ± 15 mm to ± 20 mm | Wide latitude, side interlock must be checked without fail |
| Pantile / Roman tile | 180 to 220 mm | Variable depending on overlap | Strict setting-out drawing on counter-battens to align noses and heels |
Where the battens are interrupted for the connection of a fixed frame or a metalwork flashing, the cut battens must rest on a reinforcing rafter or a doubled counter-batten. The exposed lap remains unchanged from one side of the penetration to the other: no level offset is tolerated when connecting above the trimmer. A mason's rule or a water level is used to transfer the batten line over the opening before refixing the waterproofing elements.
Managing spacing discrepancies and correcting alignment defects
On the construction site, a measurement discrepancy between the two edges or an error in marking out the exposed-lap increment immediately results in alignment drift or a course below the ridge that cannot be interlocked without cutting. If the accumulated dimensions reveal an out-of-parallelism greater than the tolerances permitted by the tile model, the foreman stops laying before half of the slope is fixed.
- Measuring the out-of-squarenessTake the exact distance between the eaves exposed lap and the centreline of the batten below the ridge at both edges and at the middle of the roof slope to quantify the difference precisely.
- Recalculating the increment by zoneCheck whether the longitudinal play of the model's interlocks allows the deflection to be absorbed without going outside the specified minimum or maximum permissible exposed lap.
- Correcting with the chalk lineRemove the incorrectly set-out timbers, snap an intermediate alignment line with the chalk line from one side to the other and refix the battens, observing the span on the counter-battens.
If the misalignment or skew results from a deformation of the underlying roof structure exceeding the absorption capacity of the permissible exposed lap, the contractor notifies the site management in accordance with the rules of the Code of Obligations (CO) on defects attributable to the work of another trade. Roofing work is suspended in the disputed area in order to determine the method of packing the counter-battens.
Frequently asked questions
How do you correct a 25 mm out-of-parallelism discovered during battening?
The correction is anticipated by distributing this out-of-squareness millimetre by millimetre over all the remaining courses, provided it remains within the permissible exposed lap of the tile model. If the pitch requires a tight or fixed exposed lap, the battens already laid on half of the slope must be unfixed, a line for overall correction must be re-tensioned and each course realigned to avoid any angled cut below the ridge.
What should be done if the last tile below the ridge turns out to be 15 mm too short?
Packing the last course with mortar or an unspecified flashing is out of the question. The compliant method consists of reworking the previous four to six courses by slightly opening the exposed lap within the technical limit permitted by the longitudinal interlock of the tile. If the maximum exposed lap has already been reached, the complete spacing of the slope must be recalculated by adding an extra course and tightening the spacings evenly.
What is the minimum batten section for a rafter span of 70 cm?
For a rafter spacing of 70 cm with counter-battens, industry practice in Switzerland requires a batten section of at least 27 × 38 mm laid on edge, or more commonly 30 × 50 mm depending on the snow load zone. An insufficient section creates a deflection under the weight of the tiles and personnel, distorts the chalk-line alignment and risks opening the transverse interlocks during frost.
Why should the horizontal alignment be systematically checked with a chalk line every five courses?
Manual gauging with a rule or with wooden gauge rods inevitably generates accumulated millimetre errors across the slope. Stretching a marking line between the two edges every five courses neutralises these discrepancies before they become visible to the naked eye. This regular check also ensures that the battens undergo no vertical deviation likely to cause capillary water ingress at the side interlocks.
Texts and standards cited
- OTConst art. 41measures to be taken at roof edges: appropriate measures to prevent falls from a fall height of more than 2 m (plumber's bridge and/or perimeter guardrail depending on the roof pitch); on roofs with a pitch of more than 60°, work only from scaffolding or a mobile elevating work platform (para. 3)