🧱 CFC 224Tinsmithing: shaping, junctions and thermal expansionChapter 5 of 10 in the section

Metal valley: effective width, slope and overlap of the adjacent roof coverings

By the end of this chapter, you will be able to size accurately the developed width of a metal valley according to the roof areas draining into it, form its watertight upstands and set the flow channel. You will master the cutting and mechanical fixing of the adjacent tiles without piercing the metal, as well as the provisions that make maintenance easier against blockage by vegetation.

Key takeaways

  • The actual slope of the valley is always lower than that of the adjacent converging roof slopes.
  • Sizing the clear channel ensures that peak flows pass through without backing up sideways.
  • Tiles must always be cut outside the valley in order to preserve the integrity of the metal.
  • Sufficient free space between the tile courses prevents dead leaves from blocking the channel.

Hydraulic sizing, profiling of the sheet and overlaps under the roof covering

The valley forms a re-entrant break line where the water from two roof slopes converges. Geometrically, its gradient is markedly lower than the pitch of the adjacent slopes: for two slopes at 30° (approximately 58 %), the valley axis has an inclination of only about 22° (approximately 40 %). This reduction in slope slows the speed at which water is carried away even though the linear flow collected there is multiplied. An insufficient effective cross-section exposes the roof to direct lateral overflow beneath the covering, in particular during violent summer storms or intense snowmelt combined with overnight refreezing.

Indicative valley execution values according to the slope of the valley bottom
Valley slopeClear channel widthOverlap under tilesHeight of side upstand
Less than 15° (27 %)150 to 200 mm200 to 250 mm60 mm with water-stop edge
From 15° to 30° (27 to 58 %)100 to 150 mm150 to 180 mm50 mm with water-stop edge
More than 30° (58 %)80 to 120 mm120 to 150 mm40 mm with water-stop edge

The valley profile, formed in the workshop or on site, has a flat bottom or a central rib known as a water break. This central rib, 15 to 25 mm high depending on the size of the work, breaks the kinetic energy of the sheet of water coming from one slope and prevents the jet from rising up under the opposite tiles when the two slopes have asymmetrical areas or pitches. The side edges of the sheet receive a vertical fold extended by a seam or hem of at least 15 mm folded outwards. The sheet is held on the boarding exclusively by sliding clips nailed to the timber substrate, without any direct piercing of the waterproofing metal.

Cutting of covering elements, mechanical fixing and accessibility for maintenance

Fitting the tiles along the valley requires absolute geometric regularity in order to leave a straight channel with parallel edges. The cutting line is marked with a blue or red chalk line directly on the covering in place. Cutting with a power cutter on the metal valley is strictly prohibited: incandescent sparks burn the finishing layers of the titanium-zinc or the powder coating of the aluminium, while burrs and abrasive residues create severe starting points for oxidation. The tiles are marked, numbered, then cut on the ground or on a work table fitted with a water tray or a mineral-dust extraction device.

  1. Marking out and identificationPlace whole tiles overhanging the valley boarding, snap the chalk line keeping the specified setback from the axis, then mark the diagonal line on each exposed face.
  2. Cutting away from the valleyRemove each element and make the clean cut away from the sheet-metal area using a diamond blade, then slightly chamfer the lower edge to soften the contact.
  3. Anchoring of small piecesFix the cut tiles whose lug has been lost by drilling a blind hole in the back, then tie them with a copper or stainless steel tie wire secured to the upper battening.

The accumulation of dead leaves, conifer needles and moss is the recurring malfunction of metal valleys. When the clear channel is too narrow, plant debris packs against the bevelled points of the tiles and forms a compact organic dam. The water held back upstream of this obstruction builds up, passes over the side hems and seeps into the roof structure. For buildings at the edge of a forest or surrounded by deciduous trees, systematically widening the channel to at least 150 mm is essential to make natural sweeping by wind and rain flushes easier.

Access to the valleys for periodic inspection and manual cleaning must be built into the roof design from the outset. The operator must be able to check that the channel is clean at least once a year, preferably at the end of autumn. During these maintenance operations on the roof slope, art. 41 OTConst requires appropriate measures to prevent falls whenever the fall height exceeds 2 metres.

Hydraulic geometry and overlap under the adjacent coverings

The meeting of two roof slopes forms a re-entrant hip that channels all the rainwater received by the converging slopes. In terms of airflow and hydraulics, the valley is the most vulnerable point of the pitched envelope: its own slope is systematically lower than that of the slopes it connects. For two orthogonal slopes with the same pitch of 35° (70 %), the axial slope of the valley does not exceed 26° (48.8 %). This flattening slows the flow speed of the stream of water and increases the depth of the water sheet, particularly during high-intensity storm rainfall.

Indicative sizing of the metal valley according to the slope and the area collected
Minimum slope of roof slopesValley axial slopePlan area collectedEffective channel widthEdge upstand under tile
20° to 25° (36 to 47 %)14° to 18° (25 to 32 %)Up to 45 m²180 mm70 mm with continuous water fold
26° to 35° (48 to 70 %)19° to 26° (34 to 49 %)Up to 75 m²140 mm60 mm with double water fold
36° to 50° (71 to 119 %)27° to 39° (51 to 81 %)Up to 120 m²100 mm50 mm with single hem
Asymmetrical slopes (difference > 15°)Variable depending on dihedral angleAny area > 30 m²200 mm with central step80 mm on the gentler slope

The lateral overlap of the covering elements above the valley sheet requires rigorous attention to the dynamic pressure of the wind. Clay tiles, slates or fibre-cement sheets must overhang the metal sheet, leaving a drip space suspended above the bottom of the gutter. The outer edge of the metal piece never ends flat: it must have a raised water deflector, formed by an upstand of at least 50 mm bordered by a hem or a fold turned outwards (reinforcing and hooking hem). This profile prevents water driven sideways by gusts from reaching the supporting boarding.

Where the slopes have a marked asymmetry in pitch or area, the steeper slope sends its flow towards the gentler slope at a speed greater than the direct discharge capacity. Without an adequate constructional provision, the water crosses the valley axis and rises by inertia under the opposite tiles. Forming an axial stop fold in the shape of a projecting step (double-bed valley or valley with a flow breaker projecting at least 20 mm) splits the flows and guides each slope downstream without harmful turbulence.

Cutting of angled tiles, sediment retention and safe maintenance

The cutting of the tiles at the valley edge determines the durability of the work. The edges must be marked with a chalk line along a rigorously straight alignment, parallel to the re-entrant hip or slightly flared downstream to speed up the flow on approaching the gutter. No cut element must come down directly to the bottom of the metal profile: a free overhang of at least 40 to 50 mm relative to the vertical upstand fold is required, while keeping the 100 mm axial water passage clear of any obstruction.

Fixing the pieces of cut tiles is a mechanical challenge. The small end pieces, deprived of their hooking lug or lightened by the angled cut, must on no account be bonded with sealing mastic against the metal of the valley: this jointing blocks the discharge of condensation and retains abrasive dust. The elements must be drilled with a diamond core bit and then fixed individually with stainless steel screws or copper wire ties onto the counter-battening, beyond the immersion zone of the metal strip.

Art. 82 LAA requires the employer to take, in order to prevent occupational accidents and diseases, all the measures that experience has shown to be necessary, that the state of the art makes it possible to apply and that are suited to the given conditions. The design of the areas around a valley must therefore include periodic accessibility for sweeping and for the manual removal of vegetable sludge, by means of snow guards and certified individual anchor points allowing safe movement without crushing the zinc or copper upstands.

Managing defects, repairing faulty valleys and securing the work

When a metal valley overflows or backs up under the tiles during a violent storm, the cause almost always lies in a constricted flow channel or in massive blockage by plant debris. The accumulation of dead leaves and conifer needles in the bottleneck formed by tile cuts that are too tight creates a direct mechanical dam. The water builds up, passes over the side hems of the metal profile and seeps onto the boarding. The initial diagnosis on the roof requires checking the effective developed width against the area collected from the slopes, checking that the hems have not been crushed by the battens, and making sure that no through-fixing has pierced the sheet in the zone where the water surges.

To restore a faulty valley without replacing the entire roof slope, the crew removes the first two courses of adjacent tiles over the whole length of the junction. The angled cuts must be redone with a grinder fitted with a diamond blade in order to restore a minimum open-air opening of 100 to 150 mm, ensuring that sediment is discharged. If the developed width of the zinc, copper or aluminium sheet is insufficient to carry the peak flow, the sheet-metal work must be reformed with a widened flat-bottom profile, fitted with double side hems raised by at least 30 mm. Under the metal, the waterproof underlay strip must run up onto the trapezoidal tilting fillets so as to provide a second continuous line of defence in the event of accidental backing up.

Frequently asked questions

What width of open-air passage must be left between the tile cuts in a valley?

The free space between the cut tiles of the two slopes must measure between 100 and 150 mm. A space of less than 80 mm promotes immediate blocking by moss and dead leaves, causing lateral overflow. A spacing of more than 180 mm needlessly exposes the metal to ultraviolet rays and excessive thermal expansion. Marking a straight line with a chalk line ensures a clean, regular cut that makes hydraulic self-cleaning of the channel easier.

How can small pieces of cut tiles be held in place without piercing the metal valley profile?

It is strictly prohibited to nail or screw the tiles through the sheet-metal work, as this creates direct water paths. Small triangular edge cuts must be fixed mechanically using stainless steel valley hooks clamped onto the edge of the tile and connected to the upper battens by a copper wire, or bonded with a watertight polymer mastic to the whole tile underneath.

How should the metal valley be adapted where the slope of the roof is particularly low?

On slopes below 25 degrees, the flow speed decreases and the risk of capillary rise increases considerably under the effect of wind. The total developed width of the sheet should be increased to 500 to 670 mm, a central rib of at least 20 mm forming a flow breaker should be incorporated, and double raised side hems should be made. A welded bituminous or synthetic waterproofing membrane must always line the valley bottom beneath the sheet-metal work.

What accessibility must be provided to ensure that dead leaves can be cleared from the valley?

The valley concentrates all the plant debris drained by the roof slopes, requiring at least one inspection a year after the leaves have fallen. Access must be planned for from the time of installation by fitting safety hooks for a roof ladder or a compliant individual anchor point. The use of leaf-guard grilles in the valley gutter is not recommended, as they create a compact filtering mat that speeds up the overflow of rainwater.

Texts and standards cited

  • OTConst art. 41measures to be taken at roof edges: appropriate measures to prevent falls from a fall height of more than 2 m (roofer's platform and/or perimeter guardrail depending on the roof slope); on roofs with a slope of more than 60°, work only from scaffolding or a mobile elevating work platform (para. 3)
  • CO art. 365materials and land: the contractor is responsible for the good quality of the materials he supplies; if the materials supplied by the client or the land designated by him are found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3)