🧱 CFC 224Rainwater drainage: gutters and downpipesChapter 10 of 10 in the section

Water test of drainage systems: method, flow rate and inspection record

Before scaffolding is dismantled or the work is accepted, the water test validates the watertightness and gradient of rainwater drainage systems. This chapter details the targeted spraying method, the visual check of welds and expansion joints, and the verification of complete drainage. You will know how to draw up a dated joint inspection record that fixes the conformity of your sheet-metal work.

Key takeaways

  • Inject the water from the high points to simulate real rainfall along the gutters.
  • Inspect every weld, expansion joint and socket joint carefully under continuous, stabilised flow.
  • Confirm that there is no residual retention at all, to verify that the drainage gradient has been respected.
  • Draw up a dated joint record, countersigned, before any removal of the perimeter protection.

Inject water at the critical points and validate gravity flow

The flow test is the final functional check of the hanging gutters, box gutters, verges and external downpipes fabricated by the sheet-metal worker. Natural rainfall has a random intensity that masks incipient defects, local counter-slopes or slow seepage hidden behind the cornice fascias. Pouring a calibrated flow of water at the strategic injection points allows the conditions of continuous water flow to be recreated instantly. The operation is carried out with a garden hose connected to the construction site water supply, fitted with a flat-jet nozzle, or with a calibrated bucket, never with a high-pressure washer, whose violent spray would lift the flashings and distort the gravity drainage behaviour.

  1. Continuous supply upstream of the networkPour the water at the highest point of the structure, at the head of the gutter or at the junction of the metal valleys. Maintain a steady supply of about fifteen to twenty litres per minute for several minutes to saturate the run, stabilise the water sheet and check the absorption capacity of the outlets and stubs without any start of overflow around the perimeter.
  2. Tracking down seepage at joints and weldsDuring continuous spraying, carefully examine the underside of the profiles, the socket joints, the sliding pieces and every brazed or tin-soldered bead. The slightest hanging drop, moisture under a splice plate or flow down the façade indicates a watertightness defect, an open seam or a badly positioned expansion sleeve.
  3. Checking complete drainage and gradientsStop the injection abruptly to assess how the system drains. The water must drain completely towards the outlet sumps and downpipes without forming standing pools. After the flow has stopped, inspect the bottom of the channel: residual puddles reveal a sagging bracket or a counter-slope incompatible with the proper performance of the metal.
Visual checks and acceptance criteria during the water test
Sheet-metal componentCritical observation zoneAcceptance criterion
Hanging or box gutterWeld beads, seams and expansion jointsAbsolutely no seepage or drop on the underside
Outlet and conical stubConnection to the gutter and upstream socketSmooth drainage, no swirling or backflow
Rainwater downpipeSpigot-and-socket joints, bends and clamping ringsWatertight joints, flow strictly guided inside

Recording the results in a dated joint record

Carrying out a water test only has its full protective value if it is recorded in a joint inspection record drawn up on the spot, in the presence of site management or the client. Under art. 367 CO, after delivery, the client checks the state of the work as soon as it is able to and notifies the contractor of any defects. By organising this joint check before the final removal of the scaffolding or the sheet-metal worker's working platform, the foreman fixes the technical situation. Every defect found is recorded precisely, which allows the necessary rework on the welds or the adjustment of the gradient to be started immediately, without disproportionate subsequent access costs.

  • The exact identification of the construction site, the precise orientation of the façades and the clear marking of the roof slopes tested.
  • The date, the time of the test, the ambient weather conditions and the names of the persons present for the joint inspection.
  • The approximate flow injected and the spraying time applied to each gutter or downpipe section.
  • The explicit finding that the joints are watertight and that drainage is complete, with no residual standing-water pocket.
  • Any reservations, with a firm deadline for remedial work and the signatures of each party.

The signed record releases the following stages of the construction site, in particular the removal of the high-level access installations. If a leak is detected, the weld is redone or a gutter bracket is straightened within the hour, directly from the working platform. Conversely, a defect discovered several weeks after the sheet-metal workers have left means costly access equipment has to be brought back and exposes the company to complex disputes over the origin of the damage. The joint water test closes the sheet-metal service in accordance with the recognised rules of the trade among pitched-roof professionals.

The SIA 118 standard governs the procedure for joint verification and acceptance of the work between the client and the contractor, making it possible to formalise watertightness findings and any remedial work required.

norme SIA 118

Determining test flow rates and the paths of the injected flows

The spray test does not consist of blindly flooding the metal roof slopes. To simulate a heavy downpour without making the company liable for uncontrolled overflows, the sheet-metal worker calibrates the water supply using a nozzle fitted with a sub-meter or a calibrated outlet. The aim is to reproduce the theoretical flow of the roof area connected to the structure, applying the per-area flow rates in line with the professional rules of Swiss sheet-metal work.

Methodical injection must always begin at the high points of the drainage system: upstream ends of valleys, ventilated ridges and roof-window connections. The operator directs the water jet towards the upper part of the slope to test capillary rise under the seams, then sweeps sideways to observe the behaviour of the flashings, verge strips and apron flashings. This initial phase confirms that the water guided towards the gutter does not bypass the clips or seep under the drip edges.

Injection parameters and acceptance criteria during the dry-run test
Zone checkedTargeted injection pointVolume and spraying timeValidation criterion
Box valley in zinc or copperUpper edge, under the roof covering overlap50 to 80 l/min for 5 minutesNo seepage under the clips, straight flow towards the gutter
Half-round hanging gutterBottom of the channel at the high point opposite the outlet100 l/min continuously for 10 minutesContinuous gradient, no standing water deeper than the thickness of the sheet
Box gutter with expansion jointsImmediately upstream of the sleeves and neoprene bellows60 l/min directed at the joint for 8 minutesNo drop at all under the box gutter and on the sarking boards
Collector box and downpipe stubInside the stub, then overflow towards the sumpFree-flowing discharge, nominal flow of the pipeImmediate priming with no air backflow or splashing on the façade

During the build-up of flow, a second sheet-metal worker inspects the underside of the box gutters and the downpipe passages. Particular attention is paid to the tin-soldered joints, the seamed joints filled with sealant and the mechanical connections of the downpipes. Any trace of moisture appearing on the masonry or the roof timber indicates an immediate failure of the metal work.

Handling the defects found and clearing the joint reservations

As soon as the injection stops, the stopwatch runs to check complete drainage. A gutter that has been properly fabricated and laid to the usual gradients must not retain any pocket of standing water after ten minutes of draining. Residual puddles deeper than 2 mm reveal misaligned brackets, a sagging bottom board or poorly compensated expansion. In the long run these hollows lead to fouling by airborne dust and accelerate pitting corrosion under acidic sludge.

The findings are compared on the spot between the sheet-metal foreman and site management. Under art. 367 CO, after delivery, the client checks the state of the work as soon as it is able to and notifies the contractor of any defects. The dated joint inspection record summarises the zones tested, the ambient temperature during the test, the absence of infiltration on the façade cladding and the conformity of the water line up to the rainwater head or the downpipe foot connection.

  • Precise identification of the gutters, valleys and downpipes tested, with linear measurement
  • Record of the water pressures and flow rates applied during each sequence
  • Explicit statement that the mitre welds, bottoms and outlets are watertight
  • Written notification of any puddles, with their location in metres along the gutter
  • Joint setting of a deadline for reworking the fixings and raising the low points
  • Simultaneous signing by the company representative and site management

When the test reveals a leak at an expansion joint or a gutter misalignment, the repair is not improvised with an extra layer of silicone sealant. The sheet-metal worker removes the defective elements, straightens the fixing brackets or redoes the tin soldering on bright-stripped metal. A second spray test is carried out immediately on the corrected section, recorded in an addendum to the record in order to formalise acceptance of the rainwater drainage without reservation.

Handling non-conformities during the test and joint recording

The appearance of seepage under an expansion joint, residual water retention or an overflow at a connection sump immediately stops the validation procedure. The water test forgives no geometric defect: a gutter laid to a counter-slope or a badly fitted stub retains the water layer and compromises the durability of the underlying elements of the pitched roof.

  1. Locating the defect and stopping the flow immediatelyShut off the water supply as soon as the leak is detected to avoid soaking of the roof structure or the eaves fascia. Mark the exact location of the watertightness defect with a grease pencil, whether it is a leaking seam or a porous brazed joint.
  2. Drawing up the joint defect recordRecord on the test form the injection point that caused the problem, the height of the standing water measured with a rule and the nature of the anomaly. Site management and the foreman sign this document on the spot.
  3. Mechanical rework and repair of the workDry the area completely with a heat gun. Correct the bracket alignment to restore the continuous gradient towards the outlet, or redo the tin soldering after completely stripping the metal mechanically.
  4. Second joint testAfter the joints have cooled and hardened, inject the test flow again at the highest point for ten minutes. The final record is validated only after complete drainage and full drying of the bottom of the channel.

Under art. 367 CO, after delivery, the client checks the state of the work as soon as it is able to and notifies the contractor of any defects. If an anomaly persists and is not cleared during the retest, art. 368 CO governs the client's rights in the event of defects in the work, including rectification. A dated and countersigned joint inspection record is the only formal proof that the drainage works properly before the scaffolding is dismantled.

Frequently asked questions

How do you identify the exact source of an infiltration under a box gutter?

Work in isolated sections, from downstream to upstream. First inject the water at the connection sump of the downpipe. If no trace appears after five minutes, work gradually back up towards the expansion joints and intermediate welds, observing the metal underside. Using a non-staining biodegradable dye makes it possible to spot immediately the capillary path under the cladding elements.

What standing-water tolerance is acceptable after the injection has stopped?

No water retention is tolerated at the outlets and low points of the gutters. A residual puddle not exceeding two millimetres in depth over one linear metre may be tolerated at the bottom of the profile after the main flow has drained, provided that it evaporates naturally without causing premature fouling or galvanic corrosion under the effect of atmospheric deposits.

What should you do if site management refuses to sign the joint inspection record?

The foreman records the full course of the test in the daily report, stating the time, the flow injected, the checkpoints observed and the refusal to sign by the client's representative. Send this report the same day by registered post or formal e-mail, with time-stamped photographs of the complete flow, in accordance with the general rules of the SIA 118 standard.

Can the raw construction site water supply be used without a meter for the test?

Use of the temporary supply is permitted but requires the flow to be calibrated beforehand with a graduated bucket and a stopwatch. Make sure that the pressure remains stable and that the water contains no concrete-mixer rinse sludge or spoil. Injecting loaded water could block the leaf guards, distort the flow test and irreparably soil the new downpipes.

Texts and standards cited

  • CO art. 367after delivery, the client checks the state of the work as soon as it is able to and notifies the contractor of any defects; for a building work, it has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2)
  • CO art. 368client's rights in the event of defects in the work: refusal, price reduction, rectification, damages; any clause agreed in advance that restricts or excludes the right to have defects remedied is void if the defect concerns a construction (para. 2bis, since 1 January 2026)