🧱 CFC 224Penetrations, dormers and special detailsChapter 2 of 10 in the section

Ventilation outlets: position on the roof slope, height and flashing

After reading this chapter, you will be able to determine the correct position of a ventilation outlet on a roof slope while avoiding critical water channels. You will master the projection heights required in relation to snow, the minimum clearance distances between penetrations, and the methodical execution of the watertight connection between the sheet-metal collar, the sarking membrane and the roof covering.

Key takeaways

  • The positioning must absolutely avoid valleys, hips and the immediate vicinity of the ventilated ridge.
  • A minimum horizontal spacing of fifty centimetres ensures unobstructed water flow between two neighbouring penetrations.
  • The height of the outlet above the roof covering plane prevents blockage by layers of snow.
  • The flashing requires a sleeve integrated into the sarking membrane and a metal apron dressed over the tile.

Position the ventilation outlet away from the drainage lines and observe the distances

The positioning of a ventilation outlet is not a simple matter of finding a passage between rafters. On a pitched roof, the penetration forms a direct obstacle to water run-off and to the sliding of the snow cover. Two areas are strictly prohibited on the slope: the channel of a valley and the top band beneath the ridge. Placing a cowl in a valley concentrates a massive volume of rainwater against the upslope collar, which is incompatible with the lateral drainage capacity of an apron. Conversely, a position too close to the ridge, within two rows of tiles or slates, compromises the overlap of the metal beneath the ventilated ridge capping and destroys the continuity of the counter-battening essential for ventilating the underside.

The geometric interaction between several protrusions determines the durability of the structure. Roof penetrations create zones where leaves, dust and silt are retained upslope. The space between two outlets, or between an outlet and a roof window frame, must allow regular cleaning and clean shaping of the side aprons without resorting to truncated joints or blindly brazed connections.

Safety distances for positioning a ventilation outlet on a pitched roof
Reference critical pointMinimum clear distanceTechnical constraint and associated risk
Axis of a recessed valley1,000 mmRisk of hydraulic blockage and backflow beneath the upslope apron.
Ridge line or break line500 mmPrevents fixing of the ventilated closure strip and weakens the top counter-battening.
Roof window or dormer600 mmWind eddies pushing odours back towards ventilation openings.
Other pipe or neighbouring protrusion500 mmImpossible to form the lateral water-shedding folds correctly.

In constructional terms, the permitted zone lies in the open field of the roof, centred between two load-bearing rafters. If the diameter of the duct exceeds the centre-to-centre spacing, a trimmer frame in the roof structure becomes mandatory, but this cut-out must on no account interrupt the continuous air circulation in the ventilation channel formed by the counter-battens.

Forming the collar, connecting the sarking membrane and setting the projection height

The treatment of a capped outlet is divided into two independent watertight barriers: the passage through the sarking layer and the sheet-metal work at the roof covering surface. The interruption of the sarking represents the point most vulnerable to residual infiltration of powder snow or condensate. At this level, the flexible membrane or sarking board must be cut diagonally or pierced to receive a prefabricated EPDM sealing sleeve or one formed with system adhesive tapes. This sleeve rises one hundred millimetres up the tubular shaft. Upslope of the opening, the counter-battening is slightly interrupted to insert a deflector drip that diverts laterally any streams of water running down the sarking.

  1. Fitting the base plate and upslope apronPosition a base sheet in copper, zinc or aluminium on the battens. Upslope, slide the plate beneath the roofing elements over two full courses, with a water-shedding fold raised by twenty millimetres.
  2. Joining the sleeve and the collarSolder or seam a rigid cylindrical sleeve perpendicular to the slope onto the plate. This vertical shaft passes through the roof covering without rigid contact with the roof structure, to tolerate slight differential expansion.
  3. Shaping the downslope apronDress the flexible pleated metal or lead apron over the profile of the tiles downslope. Hand shaping ensures continuous contact that prevents the wind from driving rain beneath the element.
  4. Fitting the cover ring and the cowlFit from above a cover ring with a conical collar dressed over the sleeve, completed by the rain-proof ventilation cowl fitted with an anti-bird grille.

The total height of the cowl outlet relative to the finished roof surface depends on the altitude of the construction site and on local snow loads. On the Swiss Plateau, a vertical projection of three hundred millimetres measured at the upslope side of the collar is generally sufficient for a soil stack vent. In the pre-Alpine or Alpine zone, this height must reach five hundred millimetres to prevent the cowl from being buried in the snow cover during thaw episodes, which would cancel the air draught and cause condensate to flow back into the insulated envelope.

Terminations and ventilation cowls: airflow, wind exposure and water seal

The termination of an exhaust duct on a pitched roof fulfils an inseparable dual function: guaranteeing the free passage of stale air, or the venting of stacks to the open air, without airflow resistance, while forming an impassable barrier to driving rain, powder snow and meltwater run-off. A poorly sized cowl or an undersized collar turns the penetration into a funnel, causing water to enter directly into the service shaft or beneath the waterproofing build-up.

The geometry of the cowl determines the discharge capacity. The free passage area under the cover must absolutely be greater than or equal to 1.5 times the nominal cross-section of the inner duct to prevent any overpressure at the terminal. For a wastewater stack of nominal diameter 100 mm, the peripheral air outlet must provide a net cross-section of at least 120 cm², after deducting the section blocked by the rodent- and bird-proof stainless steel mesh grille with 5 mm openings.

Characteristics of ventilation terminations according to use
Type of terminationAirflow profileResistance to wind and powder snowMain application on the slope
Classic conical cowl ("Chinese hat")Low pressure loss, direct static draughtVulnerable to backflow in grazing winds, risk of snow driftVenting of gravity soil stacks
Louvred deflector cover (louvre type)Medium pressure loss, built-in jet breakerExcellent protection against driving rain and bird nestsExhausts of controlled mechanical ventilation (CMV) and kitchen extractor hoods
Self-extracting terminal (static, suction type)Creates a dynamic negative pressure under the action of the windRobust against turbulence, greater vertical bulkVentilation of wet rooms by natural draught or exposed roofs
Directed ejection elbow with screened nozzleLinear discharge without rear obstructionSensitive to the direction of prevailing winds, not recommended directly upwindFresh-air intakes or horizontal exhausts under a ridge overhang

The fixing of the cowl to the protruding shaft must withstand the suction loads caused by storm winds as well as the mechanical thrust of a sliding snow cover. The cover is secured to the stub tube by telescopic fitting with an overlap of at least 60 mm, then locked by at least three stainless steel self-drilling screws fitted with neoprene sealing washers or by three watertight blind rivets, spaced at 120 degrees around the circumference. Any connection by simple friction or adhesive tape is prohibited.

Connection to the roof covering material and continuity of the sarking membrane

Integration on the slope requires absolute continuity of the drainage plane from the sarking layer to the visible surface of the roof covering. The sheet-metal plate, formed in titanium-zinc of 0.70 mm, copper of 0.60 mm or pre-coated aluminium, must have a seating proportionate to the pitch of the slope. Upslope of the shaft, the apron slides beneath the upper exposed course with a minimum overlap of 150 mm, finished with a water-stop fold of 10 to 15 mm directed upwards to prevent wind-driven backflow.

  1. Cutting and sleeving at sarking levelCut the sarking sheet in a diamond point at the pipe. Insert a flexible EPDM sealing sleeve cold-bonded to the sheet with the specific adhesive of the system manufacturer, then fold down a bevelled deflector upslope to drain accidental water towards the adjacent drainage channel.
  2. Adjusting the battens and transferring the loadsInterrupt the roof battens, leaving a peripheral gap of 20 mm around the insulated sleeve. Double the supporting battens upslope and downslope to take the self-weight of the adjacent roofing elements without deforming the metal plate.
  3. Fitting the base plate and forming the foldsEngage the metal plate on the slope. Downslope, the apron is dressed and formed onto the profile of the tiles using a wooden beater or a polymer mallet without tearing the metal. At the sides, form a lateral water-shedding roll or an upstand of at least 30 mm in height.
  4. Fitting the sealing collar and solderingLower the tapered collar onto the tubular shaft. Connect the collar to the plate by soft soldering with tin (minimum tin content 40%) for zinc and copper, or by seaming with a suitable sealing compound for metals that cannot be soldered on site.

On a clay tile roof, the tiles covering the lateral wings of the metal plate must be cut with a clear gap of 30 mm to avoid blockage by conifer needles and moss. Where the pipe exceeds an outside diameter of 160 mm, the upslope side of the collar must necessarily incorporate a saddle or a sheet-metal deflector with two inclined faces (pointing upslope) that splits the run-off flow and removes any risk of accumulation of debris or pockets of mud.

Handling positioning non-conformities and remedying penetrations

On the construction site, the sheet-metal roofer frequently discovers stack or mechanical extract stubs badly positioned by the finishing work trades. Where an opening comes out directly in the axis of a valley, less than fifty centimetres from a hip, or flush with the ridge without sufficient water seal, the work cannot guarantee long-term watertightness. Under art. 365 CO, the contractor must report to the client any circumstance compromising the proper execution of the work. On a pitched roof, the penetration must be diverted beneath the roof structure before any external cladding.

  1. Internal diversion of the ductHave the plumber or ventilation fitter rework the duct route in the roof space using two forty-five-degree elbows, so as to position the shaft on the clear slope, at mid-slope.
  2. Repair of the sarking sheetClose the erroneous opening in the rain barrier using a piece of compatible membrane extending at least fifteen centimetres beyond the perimeter, bonded with the dedicated adhesive bead, then insert a tensioned metal diversion deflector upslope.
  3. Reconstruction of the roof substrateReplace battens or sections of boarding cut by mistake, fixing reinforcing pieces nailed to the adjacent rafters to restore the mechanical strength beneath the tiles.
  4. Forming the final flashingFit the flexible sarking sleeve at the new outlet point, fit the rigid shaft, form the metal collar with a pleated lead apron or stretchable aluminium strip, and lock the weatherproof cowl.

Where the impossibility of diverting exceptionally forces an outlet in the immediate vicinity of the ridge, the sheet-metal worker must make a metal flashing wrapping around the ridge cap rather than a truncated collar. The upslope apron slid beneath the sub-ridge elements guarantees no water shedding without a diversion counter-slope and sufficient zinc development.

Frequently asked questions

Why is it prohibited to install a ventilation outlet directly in a valley?

The valley collects all the run-off water from two intersecting roof planes. Placing a penetration in this constriction forms an immediate hydraulic dam. During heavy downpours or in the presence of a spring ice plug, the water depth exceeds the effective height of the collar upstand. The water rushes beneath the roof covering, bypasses the metal fittings and saturates the boarding, causing rapid rotting of the valley rafters.

What minimum distance must be kept between a ventilation cowl and a roof window?

A minimum distance of one metre fifty to two metres must separate the axis of the ventilation outlet from the side or upper frame of the dormer or roof window. This clearance prevents stale odours, extractor hood grease or humid air from flowing back into the living spaces when the sash is opened, while also facilitating maintenance of the metal connections.

How is the watertightness at the sarking handled if the duct passes through the axis of a rafter?

Cutting through a rafter without reinforcing the roof structure is prohibited. The client must have a compliant trimmer frame installed. The sheet-metal roofer then cuts the sarking membrane in a star shape, fits an EPDM elastomer sleeve stretched over the shaft and ensures perimeter bonding. An inclined metal drip is fixed upslope to drain any infiltration water to the neighbouring bay.

What height above the tiles must the outlet of a wastewater ventilation respect?

The shaft of the soil stack must rise at least forty to fifty centimetres above the drainage plane of the roof covering. This minimum height prevents the opening from being blocked during heavy snowfall or the formation of drifts along the roof planes. In mountain zones, this clearance is increased according to the local snow load to preserve a permanent atmospheric draught.

Texts and standards cited

  • CO art. art. 365 COmaterial and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance compromises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).