Key takeaways
- A complete pallet concentrated on two rafters exceeds the permissible load and permanently deforms the roof.
- Delivery requires immediate unpacking and an even distribution of the bundles over the whole slope.
- The material hoist must rest on stable ground and have a secured reception area.
- Art. 17 OTConst requires concrete measures to prevent falling materials and collapses.
Preventing sagging of the rafters under the point weight of pallets
A pitched roof slope is designed to support a uniformly distributed load, comprising the self-weight of the elements, climatic snow loads and wind pressure. The most damaging handling error is to place an entire pallet of tiles directly on the rafters using a crane lorry. A standard pallet of clay or concrete tiles commonly weighs between 1000 and 1400 kg, concentrated on a floor area of about one square metre. Placed at mid-span, such a mass exceeds the elastic limit of timbers of common cross-section. The load causes immediate deflection of the rafters, damage to the sarking membrane and irreparable crushing of the ventilation counter-battens. This deformation distorts the roofing plane and compromises watertightness at the flashing junctions.
According to art. 17 OTConst, at workstations and walkways, measures must be taken so that workers are not endangered by the collapse of building elements or by falling objects and materials. The roofer must check the permissible load of the roof structure with site management or the timber engineer before any heavy lifting operation. If the structure has not been designed or propped to take such a concentrated load, storing an entire pallet on the slope is completely out of the question. Any delivery of material must be broken down into permissible loads distributed over all the structural supports.
| Type of roofing material | Indicative weight per square metre | Total weight of a pallet | Direct consequence of point placement |
|---|---|---|---|
| Clay plain tile | 45 to 65 kg/m² | 1100 to 1300 kg | Severe bending of rafters and local failure of battens |
| Interlocking machine-made tile | 40 to 50 kg/m² | 1000 to 1200 kg | Crushing of counter-battens and punching through of the sarking |
| Large-format concrete tile | 45 to 55 kg/m² | 1200 to 1400 kg | Permanent deformation of the slope and misalignment of courses |
Setting up the material hoist and organising distribution by bundles
Using an inclined material hoist is the reference technique for supplying a slope without locally overloading the roof structure. Installing the machine requires a stable base on the ground, on hardwood wedges or spreader plates, to prevent any settlement as the load increases. The foot of the ramp must never obstruct general circulation on the construction site. At the top, the drive head or the return pulley must be firmly anchored to the roof structure with compliant lashing straps or metal stirrups, and must never rest solely on a simple roofing batten. This anchoring absorbs the dynamic thrusts generated by the winch each time the carriage stops.
- Wedging and inclination of the mastErect the ladder sections at the angle recommended by the manufacturer and lock the eaves stops without placing any load on the gutter flashing.
- Setting up the reception landingCreate a secured reception platform on the slope, fitted with side guardrails and stable floors in accordance with SUVA guidelines.
- Handling in divided volumesCarry the tiles in loads of 40 to 80 kg per carriage in order to respect ergonomic limits and avoid any mechanical shock when unloading.
- Fan-pattern laying on the battensLay the tiles immediately in small bundles of 4 to 8 units, staggered on the battens, from the bottom to the top of the slope.
The SUVA guidelines applicable to winches and material hoists require a strictly delimited exclusion zone under the travel path of the carriage to protect personnel against falling objects. Once the bundles have been brought to the ridge or the working level, the team must immediately spread the tiles over the whole surface of the slope. This fan-pattern distribution ensures perfect spreading of the load over all the rafters. By avoiding any hard point or concentration of weight, the roofer preserves the break or hip line and works on a perfectly level substrate during final fixing.
Checking the permissible load and preventing deflection of the rafters
Unloading a complete pallet of tiles directly onto a roof structure is a major technical fault that may engage the company's liability. An industrial pallet of clay or concrete tiles has a mass of between 1000 and 1400 kg concentrated on a footprint of less than one square metre. Art. 17 OTConst requires that measures be taken at workstations and walkways so that workers are not endangered by the collapse of building elements or by falling materials. Pitched roof structures, designed for climatic and permanent loads distributed over all the slopes, have no reserve to support such a point load. Placing this massive weight next to the material hoist causes immediate plastic deformation of the rafters, tearing out of the counter-batten fixings, perforation of the sarking membrane and irreparable deflection of the intermediate purlins.
| Type of roofing | Unit weight | Weight of a bundle (5 to 8 tiles) | Indicative permissible point load per rafter |
|---|---|---|---|
| Clay plain tile | 1.1 to 1.4 kg | 8 to 11 kg | 100 to 120 kg max. (10 spaced bundles) |
| Interlocking machine-made tile | 3.2 to 4.2 kg | 16 to 25 kg | 120 to 140 kg max. (5 spaced bundles) |
| Large-format concrete tile | 4.3 to 5.0 kg | 22 to 25 kg | 120 to 140 kg max. (5 spaced bundles) |
Before starting to lift, the team leader carries out a visual check of the roof structure. He checks the rafter spacing, the absence of excessive sag, the integrity of the joints and the condition of the timber, particularly in renovation work where shrinkage cracks reduce bending resistance. If the span between purlins exceeds 1.50 m without propping, the tiles must absolutely be distributed bundle by bundle, without creating any settlement near the verges.
Paced handling at the material hoist and organisation of the reception
The smooth running of the supply depends on a strict balance between the output of the machine and the pace of distribution on the roof. In accordance with art. 82 LAA, the employer must take, to prevent occupational accidents and diseases, all measures that experience has shown to be necessary, that are feasible according to the state of the art and that are appropriate to the given conditions. Handling bundles from the inclined head of the material hoist requires precise ergonomic movements to prevent musculoskeletal disorders and loss of balance. Personnel stationed at the reception must never lean over the void to grab a load or force a poorly immobilised platform.
- Stopping and wedging the platformWait until the winch motor has come to a complete stop and the carriage is mechanically locked at the top of the ladders before handling the skip's retaining elements.
- Ergonomic load pick-upTake a single bundle while keeping the back straight and the feet braced on a stable support platform, without twisting the spine under load.
- Staggered distributionTake the bundle directly to its position on the battens, spacing the bundles every two or three rafters in a staggered pattern from bottom to top.
- Signalling and sending the cage back downFold down the skip's protective side rail before giving the lowering order to the operator stationed on the ground by radio or hand signal.
Permanent and unambiguous communication between the operator at the foot of the ladder and the receiving roofer on the roof prevents unintended starts and wrong manoeuvres. The operator systematically checks compliance with the maximum payload shown on the manufacturer's plate of the material hoist, deducting the self-weight of the platform or tile bin. He makes sure the bundles are properly wedged against the backrest to eliminate any risk of sliding during the ascent or when passing the angle knee joint, a critical articulation where dynamic jolts may destabilise poorly secured elements.
Emergency procedure: abnormal deformation of the slope or failure of the material hoist
On a roofing construction site, the appearance of abnormal deflection due to temporary storage or a mechanical jam of the material hoist calls for an immediate and methodical response. A complete pallet of clay or concrete tiles has a mass of between 1000 and 1400 kg. Concentrated on a small area, this point load frequently exceeds the permissible load of the rafters, risking brittle failure of the timber or permanent unevenness of the roofing plane.
- Stop the supplyAs soon as visible warping, a cracking noise from a roof structure element or a winch malfunction occurs, the team leader stops hoisting loads. In accordance with art. 82 LAA, the employer and his teams apply the prevention measures appropriate to the conditions of the construction site to counter the danger of collapse.
- Secure the area below and the access routesImmediately cordon off the area below the slope and prohibit passage under the material hoist. At workstations and walkways, provisions prevent personnel from being endangered according to art. 17 OTConst in the event of tiles sliding or the carriage coming loose.
- Relieve the slope by distributed unloadingNever remove tiles abruptly from a single support. The roofers manually remove the excess bundles, starting with the central areas of the slope, to transfer the weight to the load-bearing supports or the scaffolding, in compliance with the SUVA guidelines on load carrying.
- Check the load-bearing structureHave the carpenter assess the condition of the rafters, purlins and counter-battens before any resumption of laying. If residual deformation remains after unloading, structural reinforcement by sistering or the formal opinion of a timber engineer is required.
Frequently asked questions
How should you react immediately if a rafter bends while tiles are being placed?
Stop the supply via the material hoist and forbid access under the affected area of the roof structure. Immediately relieve the area by manually moving the tile bundles to the load-bearing purlins or wall plates. Continuing the roofing is out of the question until the carpenter has checked the mechanical integrity of the timber and confirmed that there is no fibre failure under load.
Can an entire pallet be winched directly onto the slope?
No. Placing a complete pallet on a roof slope creates a point load exceeding the permissible resistance of standard rafters. Unloading is always done in hand-portable bundles from the receiving carriage of the material hoist. The elements must be immediately spread out in small regular piles of three to six tiles over the whole of the battens to balance the loads.
What precautions apply when unloading in strong wind?
As soon as the wind compromises the stability of the bundles or deflects the path of the receiving carriage, suspend the hoisting of materials. The wind catching the box and the tiles creates unforeseen parasitic forces on the inclined ladders. Secure the head of the material hoist, lower the platform to the ground and fix the bundles already placed on the roof.
Who validates the permissible load before supplying an old roof?
The assessment is the responsibility of site management or a civil engineer specialised in timber structures. During a renovation, the roofer checks with the client that the existing roof structure can support the temporary mass of the grouped tiles. If there is visible doubt about the cross-section or the pest-damaged condition of the rafters, storage on the slope must be prohibited.
Texts and standards cited
- LAA art. 82general prevention rules: to prevent occupational accidents and diseases, the employer must take all measures that experience has shown to be necessary, that are feasible according to the state of the art and that are appropriate to the given conditions; the workers assist him
- OTConst art. 17protection against the collapse of building elements or the fall of objects and materials: at workstations and walkways, measures must be taken so that workers are not endangered
