Key takeaways
- The SIA 180 standard requires a continuous airtight layer to prevent destructive interstitial condensation.
- The service void beneath the membrane protects the vapour barrier from later penetrations by building services installations.
- Every duct or conduit passage requires an airtight penetration sleeve, mechanically bonded.
- The visual and joint inspection before the lining is fitted remains the final quality assurance step on the construction site.
Coordination of trades and creation of the service void under the pitched roof
The roof slope has the highest density of penetrating services in a building: ventilation pipes, electrical cable bundles, flues and aerial cables. According to SIA 180, the envelope must present a continuous barrier against the transfer of warm, humid air from heated rooms into the thermal insulation beneath a pitched roof. Any airtightness defect creates a concentrated convective flow capable of saturating the roof timbers and the insulation within a few winter cycles.
To protect the airtight layer, the classic mistake is to fix the interior finishing lining directly against the vapour control layer stapled to the rafters. In this configuration, every plasterboard screw, every recessed spotlight box and every electrical junction perforates the sheet. Creating a service void beneath the membrane is the essential construction rule. This technical plenum is formed by timber counter-battens or a suspended metal frame with a usable depth of at least 50 mm.
This physical separation clearly defines the technical responsibilities between the finishing work trades. Where a subcontractor must necessarily pass through the wall to the outside (mechanical extractor, chimney flue or solar sensor cable), this penetration must be planned and recorded before the insulation between the rafters is installed. Site coordination thus avoids uncontrolled cuts with a utility knife, which cannot be properly sealed once the services have been pulled through.
Treatment of individual penetrations and systematic inspection before closing up
The treatment of an individual penetration under a pitched roof strictly excludes makeshift fixes using cartridge sealant or general-purpose adhesive tape cut in a star shape. These stopgap solutions fail under the thermal expansion of the ducts and the creep of the materials. Using a prefabricated EPDM rubber penetration sleeve, fitted with a self-adhesive high-tack polyacrylate flange, ensures the elasticity required to cope with structural movement.
- Marking out and calibrated incisionLocate the axis of the duct and cut the membrane using a circular template with a diameter 20 % smaller than that of the pipe, so as to keep the film slightly under tension.
- Fitting the elastomer sleeveSlide the flexible ring of the sleeve over the duct until its peripheral flange lies perfectly flat against the airtight plane of the roof.
- Bonding and mechanical rollingRemove the protective strips from the acrylic adhesive and press the flange firmly onto the membrane with a rigid application roller, without forming any fold.
- Securing the collarPosition a suitable clamp or a specific stretch adhesive tape around the collar to seal the junction permanently onto the rigid pipe.
The inspection before the lining is fitted is the critical validation phase of the work. As soon as the plasterer starts, defects become invisible until mould appears or the final depressurisation test is carried out. A joint compliance inspection with the site manager checks the integrity of each sleeve, the continuity of the bonded joints against the masonry and the absence of accidental tears caused by the frame hangers.
| Item inspected | Technical requirement | Corrective action in case of defect |
|---|---|---|
| Electrical conduits passing through | Airtight multiple sleeve or airtight cable grommet | Replace the incision with a grouped flange |
| Sanitary vent pipes | EPDM sleeve with tightened retaining clamp | Fit an elastomer flange and roll it down |
| Rafter-membrane junctions | Mechanical pressure battens on resilient strip | Redo the bonding and fit a counter-batten |
| Surface tears | Certified adhesive tape applied to a clean substrate | Membrane patch overlapping by 100 mm, rolled down |
Design of the service void and connection of individual penetrations
The roof slope has the highest density of technical penetrations in the building envelope. The repeated crossing of the airtight layer by sanitary distribution, stack ventilation, photovoltaic panel cabling or aerial services is a major critical point. According to SIA 180, the continuity of the airtight plane must prevent interstitial moisture transfer by convection into the cold layers of the roof. To ensure this barrier without weakening it at each intervention, providing a service void beneath the membrane is an essential construction condition before any interior lining is fitted.
- Service void under the pitched roof
- Free space left between the airtight vapour control membrane and the finishing lining (plasterboard, panelling). Formed by mechanical battening or counter-battening, it accommodates electrical conduits, junction boxes and pipework without perforating the airtight envelope.
The vertical elements that must necessarily pass through the roof build-up cannot be treated with simple adhesive tapes applied directly onto the ducts. Using a prefabricated penetration sleeve made of EPDM rubber or flexible polyethylene provides the elasticity needed to absorb the differential movements of the timber structure. The following table summarises the airtightness provisions according to the type of element passing through the roof slope.
| Penetrating element | Means of connection to the vapour control layer | Point to watch during execution |
|---|---|---|
| Single electrical conduits or solar cables | EPDM sleeve with elastic cable grommet | Pierce the sleeve to a diameter 20 % smaller than that of the cable |
| Multiple bundles of conduits | Grouped airtight cable plate with flange | Strictly forbidden to wrap several conduits in a single piece of adhesive tape |
| Ventilation duct or stack vent (PVC/PE) | Flexible sleeve with integrated adhesive flange and clamp | Place a rigid backing behind the membrane for rolling down |
| Flue or metal chimney | Special high-temperature sleeve or airtight penetration box | Comply with safety distances to combustible materials |
Order of operations and inspection before closing up the lining
Successful airtightness under the pitched roof depends on strict sequencing between the structural work, roofing and technical finishing work trades. The membrane installer ensures the overall continuity of the airtight plane, but site coordination must prevent the electrician or the plumbing installer from cutting the vapour control layer afterwards without warning. Art. 365 CO para. 3 also reminds us that the contractor must notify the client of any circumstance jeopardising the proper execution of the work.
- Laying and fixing the vapour control layerRegular stapling to the rafters, 100 mm overlaps joined with certified adhesive and perimeter bonding against masonry with durable elastomeric sealant.
- Installing sleeves on heavy penetrationsFitting waste water and air duct penetrations, airtight connection of the flanges with roller pressing on a solid substrate.
- Installing the service void frameworkFixing battens or metal sections to create a service cavity at least 40 to 60 mm thick to receive the interior installations without contact with the film.
- Laying of secondary services by the technical tradesPulling of electrical circuits, communication networks and equipment contained within the cavity created, without any perforation of the membrane.
- Inspection before the lining is fittedExhaustive visual and tactile inspection of the entire pitched roof to validate the integrity of the film before it is covered with boards or panelling.
In the case of an airtightness test (measurement of overall air permeability according to SIA 180), the defects revealed under a pressure difference of 50 Pa almost always come from poorly sealed local penetrations. Drawing up a formal airtightness acceptance record between the carpenter-roofer and the plasterer ensures a clear transfer of responsibility before the plenum is finally concealed.
Managing non-conformities and acceptance of airtightness under the pitched roof
The roof slope has a critical density of technical penetrations: ventilation ducts, solar cable passages, chimney outlets and recessed boxes. When the order of operations of the trades is not respected or the service void beneath the membrane is insufficient, damage to the vapour barrier becomes common. Any unplanned penetration or defective connection compromises the permeability requirement defined by SIA 180 and exposes the roof structure to interstitial condensation.
- Finding and immediate stop of the liningAs soon as a tear or an uncontrolled penetration is identified, stop the fitting of the interior lining. If the work is concealed, the pressurisation test or smoke detection will reveal the leak, requiring destructive removal at the expense of the party responsible.
- Mechanical repair with a penetration sleeveFor each duct or conduit, open the insulation locally if necessary to slide on an EPDM penetration sleeve suited to the exact diameter. Connect its flange to the membrane with the recommended elastomer adhesive and roll it down carefully.
- Reinstating the service voidCheck that the battening provides a service void of at least 40 to 60 mm between the lining and the membrane, allowing the services to pass without straining or perforating the airtight sheet again.
- Inspection before the lining is fitted and recordCarry out a joint visual inspection with the site management. Note the conformity of the connections, sleeves and bonding on the load-bearing elements, recording the remedial work in the site diary.
In the event of a dispute between trades concerning damage to the membrane, the traceability of the execution steps protects the roofing company. The contractor notifies reservations in writing in accordance with SIA 118 to be released from liability as long as the compliant remedial work has not been accepted.
Frequently asked questions
How do you repair a vapour barrier sheet slashed by another trade?
Masking the cut with simple adhesive tape is out of the question. Cut a patch of the original membrane extending at least 100 mm around the slit. Remove dust from the substrate, apply a continuous bead of hybrid sealant-adhesive or bond the edges with an adhesive certified for vapour barriers. Roll the patch down without tension, then record the repair in writing with photos before the interior lining is fitted.
What minimum depth should be provided for the service void under the pitched roof?
The standard minimum height is 50 mm, formed by counter-battening mechanically fixed under the rafters or the load-bearing structure. This thickness allows spotlight recessed boxes, corrugated electrical conduits and services to be accommodated without touching or stretching the airtight membrane. Reducing this dimension considerably increases the risk of perforating the vapour barrier when the finishing linings are subsequently screwed on.
How do you treat the airtightness of a group of solar cables in a pitched roof?
Passing cables together under a single adhesive tape creates unavoidable leakage channels. You must install a prefabricated cable plate fitted with individual elastomer grommets suited to each diameter, or a dedicated airtight penetration sleeve. Each cable passes through its own opening ensuring an airtight fit. The flange of the plate is then bonded and bridged to the membrane in accordance with SIA 180.
Who is responsible for the compliance of the airtightness before the pitched roof is closed up?
The company that installed the airtight membrane guarantees its initial integrity. However, the site management must organise a formal acceptance of the substrates before the plasterers start work. This inspection before the lining is fitted validates the penetration sleeves and the perimeter bonding. Once the lining has been fitted without this joint inspection record, establishing responsibility in the event of a failed airtightness test becomes complex.
Texts and standards cited
- norme SIA 180Thermal insulation, moisture protection and indoor climate in buildings
- norme SIA 118General conditions for the execution of construction work