🧱 CFC 224Sarking, ventilation and underlay membraneChapter 6 of 10 in the section

Condensation under a metal roof: why the metal drips and how to prevent it

After reading this chapter, you will be able to identify the physical causes of dripping under a cold metal roof, size the ventilation air gap according to the recognised rules of the trade, assess the effectiveness of a condensation-regulating felt and carry out a methodical diagnosis distinguishing rainwater infiltration from underside condensation.

Key takeaways

  • Night-time radiation cools the sheet below the outside temperature, causing condensation under the roof.
  • Continuous ventilation from eaves to ridge removes moisture before it reaches the dew point.
  • The regulating felt temporarily stores the condensation water but requires daytime drying by air flow.
  • A methodical diagnosis distinguishes rainwater infiltration from condensation by means of the weather and humidity readings.

Understanding the dew point and the role of the regulating felt

A cold metal roof has almost no thermal inertia and a very high emissivity towards the night sky. On clear nights, radiative undercooling lowers the temperature of the metal cladding several degrees below the ambient air temperature. As soon as the air beneath comes into contact with this cooled surface and reaches its saturation point, the water vapour changes phase: fine droplets form on the underside of the panels or profiled sheets.

Underside dew point
Critical temperature at which the humid air trapped or circulating beneath the metal roof reaches 100 % relative humidity, turning water vapour into liquid water directly against the steel or aluminium.

Without an absorbing device, this coalescing surface water forms drops that eventually fall by gravity, wetting the roof timbers, the underlay or the technical floor. To neutralise this localised dripping, a woven or non-woven regulating felt applied to the underside of the sheet provides temporary capillary retention capacity.

Comparative behaviour of metal undersides by type of build-up
Type of claddingWater management mechanismLimits of effectivenessTypical field of application
Bare sheet without feltImmediate run-off towards the eaves or falling dropsNot functional if the pitch is shallow or there is no free drip edgeOpen canopies, ventilated agricultural sheds
Integrated anti-condensation feltTemporary capillary absorption of liquid moistureCritical saturation if daytime air does not allow evaporationClosed uninsulated rooms, ventilated cold roofs
Ventilated underlay with screenDrained water carried away on a draining membraneRequires continuous counter-battens and nail sealingConverted attics, roofs insulated between rafters

Underside ventilation and method for diagnosing an apparent leak

The durability of the metal structure depends on continuous, unobstructed air circulation beneath the profiles. Thermal draught requires inlet sections at the eaves and outlet sections at the ridge that are rigorously proportioned, maintaining a flow that sweeps the entire length of the corrugations or bays. Any transverse obstacle in the air gap, such as an uncut massive purlin or over-compressed insulation, creates a dead zone conducive to moisture saturation.

When damage occurs in the form of dripping, the site manager must establish the exact physical cause without fail. A complaint about rainwater infiltration often conceals massive condensation caused by blocked ventilation or excessive permeability of the underlying envelope.

  1. Recording weather and ambient conditionsMeasure the surface temperature of the metal with an infrared thermometer and the relative humidity of the air under the roof, and note whether there was a clear night sky with no recent rain.
  2. Checking the ventilation openingsCheck that the eaves grilles are unobstructed, that the ventilated ridge opens freely and what the actual thickness of the air gap is along the counter-battens.
  3. Inspecting the wetting patternDistinguish a localised mark directly beneath a fixing or an overlap (suspected rain leak) from general, uniform wetting of the underside of the panels (confirmed condensation).
  4. Examining the screen and the vapour barrierMake sure the airtight membrane is continuous beneath the insulation, in order to rule out massive migration of indoor vapour into the void under the roof.

The rules of the trade for roofing require ventilation under a cold metal roof to be maintained permanently, in order to prevent damage caused by stagnant moisture.

Norme SIA 118

Design of ventilation cross-sections and sheet-metal details

To prevent moisture build-up under a cold metal roof (profiled sheets, steel panels or standing-seam roofing in zinc or copper), the effectiveness of the air flow depends directly on the batten height and the sizing of the inlet and outlet openings. The anti-condensation underlay or regulating felt can absorb the night-time droplets only if outside air circulates freely during the day to remove this water load by evaporation.

Minimum counter-batten heights and ventilation cross-sections for pitched roofs according to pitch
Roof pitchMinimum counter-batten heightContinuous air inlet at the eavesContinuous air outlet at the ridge
Shallow pitch (< 15° or 27 %)60 mm to 80 mm200 cm² per linear metre100 cm² per linear metre
Medium pitch (15° to 30°)50 mm150 cm² per linear metre80 cm² per linear metre
Steep pitch (> 30° or 58 %)40 mm to 50 mm100 cm² per linear metre50 cm² per linear metre

At the eaves, the ventilated eaves flashing or the perforated expanded-metal grille must provide a real free opening, after deducting the solid parts of the metal. A restriction caused by a badly fitted eaves board or a waterproofing flashing pressed against the metal profile blocks the thermal draught and instantly lowers the underside temperature towards the dew point.

At the ridge, the metal finishing caps require a calibrated ventilation profile that maintains continuous extraction without letting in powder snow. For double-pitched roofs, a perforated metal ventilated closure strip or a raised ridge on double battens provides the negative pressure needed for mechanical air draught.

Corrective measures in refurbishment and protocols after damage

When a ceiling or insulation drips outside periods of rain, condensation under the metal roof is confirmed. The remedy is not to apply sealing mastics blindly, which would worsen the confinement of vapour, but to restore the air flows and dry out the underroof build-up.

  1. Visual inspection and humidity readingMeasure the residual moisture content of the roof structure and the underlay with a pin probe. Examine the state of saturation of the regulating felt or bituminous underlay beneath the metal panels.
  2. Clearing the ventilation openingsCheck that there is no obstruction from blown insulation, mineral wool compacted against the sheets, or rodent nests at the eaves and along the hips.
  3. Creating local or continuous ventilationInstall sheet-metal vents suited to the roof profile, or replace the sealed ridge with a ventilated ridge strip on a timber riser.
  4. Checking the vapour barrier on the warm sideMake sure, by internal inspection, that the underroof is not subject to massive transfer of water vapour from a heated attic that is not airtight.

To restore a build-up without completely removing the roofing, the craftsman may recommend shifting some sheets in order to fit counter-batten risers, or adding roof ventilation skylights on the pitched roof. In the event of a non-compliant substrate or unsuitable instructions received by the contractor, art. 365 CO requires the sheet-metal worker to inform the client in writing immediately when circumstances endanger the proper performance of the roof against moisture-related defects.

During refurbishment work involving the cutting of sheets or the opening of ventilation hatches on steep roofs, art. 41 OTConst requires appropriate measures to prevent falls at the roof edge as soon as the fall height exceeds 2 m, by means of a roofer's catch scaffold or a perimeter guardrail suited to the slope.

Handling condensation damage and remedies on the construction site

The appearance of water drops under a ventilated metal roof frequently leads to disputes between the client, the sheet-metal worker and the other trades. Faced with water running inside, correctly characterising the damage is the first technical step to take before undertaking any destructive remedial work.

  1. Recording weather and thermo-hygrometric conditionsNote the exact time of the dripping, the indoor humidity, the ambient air temperature and the exposure of the slope to the night sky. A sharp night-time drop in temperature without precipitation points immediately to a dew-point phenomenon on the underside of the sheet.
  2. Checking the air passage cross-sectionsMeasure the real air inlet opening at the eaves and the outlet at the ridge or hip. Check that no badly folded eaves strip, bird's nest or compacted thermal insulation obstructs the continuous ventilation air gap.
  3. Checking the saturation state of the underlayCheck whether the factory-bonded regulating felt or the structured mat under the standing seam shows water saturation or areas torn away mechanically by friction on the boarding.

When the client reports leaks that he attributes to defective sheet-metal work, an adversarial inspection is required. Under CO, after delivery the client must inspect the work as soon as he can and notify the contractor of defects; for a building work he has 60 days to notify them. The company must respond with a factual analysis showing whether the water comes from a penetration or from an airflow design defect independent of its workmanship.

If the dispute over the origin of the damage persists, calling in a neutral expert from the trade makes it possible to decide between convective moisture rise and a lack of watertightness against precipitation. Art. 368 CO sets out the client's rights in the event of defects in the work, including repair, price reduction, rejection or damages. A drying protocol combined with reopening the ventilation openings is often enough to restore the physical balance without replacing the entire metal panel.

Frequently asked questions

How can you tell rainwater infiltration from condensation under the sheet?

Infiltration coincides with rainy spells or snowmelt and follows the roof penetrations such as dormers and vent pipes. Condensation occurs on clear, cold nights with an open sky and no rain at all, or at sunrise as the metal warms up. Condensation water is spread evenly over the underside of the panels and drips over the whole roof surface.

Can an anti-condensation felt be laid directly on close-boarded sheathing?

No. The non-woven regulating felt bonded under the metal profile requires permanent air circulation on the underside to evaporate the moisture absorbed during the night. If it lies directly against boards with no ventilated air gap, the fibres stay continuously saturated with water. This permanent moisture causes rapid rotting of the roof timber and triggers premature corrosion of the sheet through confinement.

What should be done when the anti-condensation felt starts to drip into the attic?

The felt has exceeded its maximum water absorption capacity. Urgent action is needed on the ventilation of the attic or of the air gap under the roofing. Check that the eaves grilles are not blocked and that the ridge closures let the air escape. Temporarily installing mobile air dehumidifiers and checking for non-airtight duct passages reduces the vapour input from the occupied floors.

What minimum ventilation cross-section must be provided under a cold metal roof?

The minimum height of the air gap depends on the length of the rafter run and the roof pitch, with a customary minimum of 40 millimetres for usual lengths. The air inlets at the bottom of the slope and the outlets at the ridge must provide free opening cross-sections of at least 200 square centimetres per linear metre, protected against wasps and rodents by a suitable perforated grille.

Texts and standards cited

  • COafter delivery, the client must inspect the work as soon as he can and notify the contractor of defects; for a building work he has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2)
  • COclient's rights in the event of defects in the work: rejection, price reduction, repair, damages; any clause agreed in advance that restricts or excludes the right to have defects remedied is void if the defect concerns a construction (para. 2bis, since 1 January 2026)