Rainwater drainage: gutters and downpipes: the execution reference
This section covers the sizing and fabrication of gutters and rainwater downpipes for pitched roofs. It is intended for foremen and site managers who must design or install watertight drainage systems, sized for 100-year rainfall, suited to frost and compliant with the drainage requirements of standard SIA 271 and standard SN EN 12056.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
5 mm/m
Recommended slope to ensure self-cleaning of the gutters
500 mm
Maximum spacing of gutter brackets in exposed areas
0.03 l/(s·m²)
Usual design rainfall intensity in Switzerland
6 m
Maximum distance between two expansion slides on zinc or copper gutters
Technical scope and rules of the trade in rainwater drainage
Rainwater drainage on pitched roofs (CFC 224) covers all the fabricated metal elements and pipework connecting the sloping roof covering to the collection network. This scope includes collection at the eaves (suspended or recessed gutters), expansion joints, emergency overflows, and the vertical run through exposed or concealed downpipes down to the base of the stack.
Every installation must prevent blockage and backflow towards the roof structure. In accordance with the general principles of the Code of Obligations (CO), the contractor must immediately notify the client of any defect found in the fixing supports or in the planned drainage capacities.
Installation sequence and linking of the ten chapters
Building a rainwater drainage system follows a strict logic, from the hydraulic design through to the watertightness check before acceptance of the construction site.
- Sizing and calculation of cross-sectionsDetermine the effective cross-section of the gutter and the diameter of the downpipes according to the projected area and the reference rainfall intensity (standards SIA 271 and SN EN 12056).
- Support and geometry of guttersAlign the gutter bottom with a minimum slope, set the spacing of the brackets to prevent any sagging and provide for the expansion of the metal.
- Protection against overflow of recessed guttersInstall overflows sized to discharge water to the outside before it can penetrate the structure in the event of a blockage.
- Installation of downpipes and connection at ground levelFix the downpipes with bayonet clips, incorporate expansion sleeves, fit the shoe at the base, then connect to the inspection chamber with a trap or separator.
- Protection, maintenance and inspectionFit the gutters with frost protection (heating cables) and leaf protection (leaf guards), then carry out the sprinkling test under controlled flow.
Gutters and their overflows must be sized to discharge the design rainfall without pressurisation or infiltration towards the sub-roof.
Norme SIA 271
📘 Chapters in this section 10
Sizing a gutter: collected area, rainfall intensity and effective cross-section
Calculate the exact cross-section of a gutter according to the collected area and 100-year rainfall in Switzerland.
Rainwater drainage: gutters and downpipesGutter slope and support: hook spacing, deflection and standing water
Set the slope and the bracket spacing to eliminate sagging and standing water.
Rainwater drainage: gutters and downpipesRecessed gutter: the overflow is not optional
Size and position the safety overflow to protect the roof structure from any infiltration.
Rainwater drainage: gutters and downpipesRainwater downpipe: brackets, expansion and cast-iron base shoe
Install rainwater downpipes with expansion collars and a reinforced shoe at the base of the run.
Rainwater drainage: gutters and downpipesConnecting to the network: manhole, trap and separation of waters required in Switzerland
Carry out the mandatory separation of waters and fit the inspection chamber with a removable trap.
Rainwater drainage: gutters and downpipesFrost in gutters: heating cable, installation and limits
Manage ice formation in the gutter using a self-regulating heating cable and a snow thermostat.
Rainwater drainage: gutters and downpipesLeaves and needles: leaf guards, grilles and cleaning intervals
Prevent blockage of the outlets by means of leaf guards and schedule a cleaning plan.
Rainwater drainage: gutters and downpipesSuspended gutter: overhang, position relative to the eaves line and splashback
Adjust the position of the suspended gutter below the eaves line to avoid backflow.
Rainwater drainage: gutters and downpipesRainwater harvesting: filter, overflow and separation from the drinking-water network
Connect a downpipe filter and connect a rainwater tank while preventing any backflow of water.
Rainwater drainage: gutters and downpipesWater test of drainage systems: method, flow rate and inspection record
Carry out the sprinkling test at continuous flow to validate the watertightness of the joints at acceptance.