Skip to content
Website
🧱 CFC 224Sarking, ventilation and underlay membraneChapter 10 of 10 in the section

Check the underlay before covering: the last chance to see

Once the tiles or slates are laid, the roof underlay becomes inaccessible. This chapter gives you the method for systematically inspecting the sheets, bonded joints and penetrations before covering. You will learn how to lock down every critical point according to the rules of the trade and how to compile a dated photographic record that serves as indisputable technical evidence.

Key takeaways

  • The visual and tactile check is always carried out before the first course of tiles.
  • Sheet overlaps and adhesive tapes require continuous rolling-down without creases.
  • Every individual penetration requires a watertight upstand and a functional diverter flashing.
  • The dated photographic record fixes the condition of the work before it is permanently and completely concealed.

Validate overlaps, bonded joints and penetrations before closing up

The roof underlay is the second line of defence against infiltration by powder snow, condensation water or water driven back up under the tiles. Once the covering battens are nailed and the first courses of tiles are laid, no correction is possible without heavy stripping. The foreman must walk over all the roof slopes to track down workmanship weaknesses. This systematic check is not limited to a quick glance: it requires a tactile examination of the bonded joints and a check of the membrane tension.

Technical checklist for the roof underlay before laying battens and tiles
Work itemSystematic check pointsTolerances and compliance criteria
Longitudinal overlapsOverlap width, direction of water flow, regular alignmentOverlap as per factory marking, no creases, straight alignment
Bonded joints and adhesive tapesAdhesion on a clean substrate, absence of dust, roller pressureContinuous rolling-down without bubbles or lifting at the edges
Ventilation counter-battensPresence of nail sealing strips under battens, mechanical fixingResilient strip compressed under each ventilation batten
Penetrations (chimneys, dormers)Vertical upstands, upslope diverter flashings, watertightness of cornersBonded upstand with watertight corner joint and free lateral drainage
Duct and pipe penetrationsStretchable EPDM sealing sleeves, peripheral sealing tapesSleeve fitted to the pipe diameter, clamp or continuous bonding
Eaves and gutterMetal connection strip, underlay discharging directly into the eaves overhangDrainage slope maintained, no counter-slope or water pocket

Individual details account for most subsequent damage claims. Upslope of every roof window or chimney flue, the membrane diverter flashing must direct residual water towards the adjacent bays without letting it stagnate behind the obstacle. Internal corners require reinforcement patches that are carefully rolled down. As regards fixing the counter-battens, a nail sealing strip under each ventilated batten is essential to neutralise the risk of infiltration through the nail perforations.

Compile the dated photographic record as proof of compliance

The roof underlay belongs to the category of concealed work. Once the roof is completed, the company remains bound by its contractual obligations regarding the quality of materials and of the work carried out. Art. 365 CO recalls the contractor's liability for the material supplied and the execution of the work. If a leak occurs several months after acceptance of the work, proving the perfect initial watertightness of the hidden joints is impossible without a rigorous visual record made before the underlay is finally covered by the tiles.

  1. Overview shots of the roof slopesPhotograph each roof slope from the scaffolding, capturing the overall flatness, the regularity of the underlay alignment and the general layout of the counter-battens.
  2. Tight framing on overlaps and jointsTake close-ups showing the continuous rolling-down of the adhesives, the continuity of the nail sealing strips under battens and the cleanliness of the junctions.
  3. Documentary focus on each penetrationSystematically photograph all four sides of each penetration: upslope diverter flashing, welded or bonded corners, ventilation sleeves and roof outlet.
  4. Details of the eaves and ridgeDocument the underlay lapping onto the metal eaves flashing as well as the treatment of the ventilation at the ridge purlin.
  5. Secure archiving and time-stampingFile the photos in the project file with verifiable time-stamp metadata and embedded geolocation data, before the self-inspection sheet is signed off.

This photographic record must be attached to the daily site report before the tiles are delivered onto the battens. In the event of a later dispute over infiltration, producing clear photos showing the correct treatment of a valley or the compliant execution of an upslope flashing immediately clears the installer of liability for any damage caused by third parties, such as solar panel installers or chimney sweeps.

Systematic roof underlay inspection protocol before battening

Checking the roof underlay is the decisive technical hold point on a pitched roof site. Once the counter-battening and covering battens are laid, direct visual access to the membrane, the sheet-metal flashings and the sealing bridging strips becomes impossible. Any defect hidden by the tiles or slates inevitably leads to slow infiltration into the insulation layer, often detected months after acceptance of the work under standard SIA 118.

The foreman or team leader applies a rigorous inspection method, slope by slope, from the eaves to the ridge. The mechanical anchor points, the tension of the sheet and the continuity of the sealing strip under each counter-batten must be inspected before the tiles are delivered onto the slopes.

Critical roof underlay check points before closing the slope
Inspected elementTechnical compliance criterionCommon defect to correct immediately
Overlaps and adhesive tapesLongitudinal and transverse overlap in line with the grid markings, bonded joints pressed down without creases or air bubblesAdhesive lifting off due to sawdust or residual moisture
Penetrations (ducts, ventilation)Flexible sealing sleeves bonded, collars folded down and water deflector sloping upslopeCreased adhesive tape creating stagnant water retention
Eaves line and drip edgeMembrane bonded to the metal drip edge without counter-slope, free drainage to the gutterWater pocket behind the drip edge due to the sheet sagging between rafters
Roof windowsConnection apron turned up onto the trimmer, corners reinforced with preformed corner piecesExposed staples not bridged in the splash zone
Counter-battens and perforationsContinuous sealing strip under the batten, centred nailing compressing the sealMisdirected nails that have torn the membrane outside the counter-batten

The contractor remains responsible for the quality of the materials he uses in accordance with art. 365 CO. Where a subcontractor installs the underlay, the cross-check formalised by a hold-point release avoids later shifting of responsibility in the event of a watertightness claim.

Compiling the evidential photographic record and clearing reservations

The photographic record is the only tangible memory of workmanship quality once the battening and covering are completed. In the event of a dispute over water damage, the client may invoke the statutory warranty for defects in the work under art. 371 CO. Producing time-stamped and geolocated photographs demonstrates scrupulous compliance with the rules of the trade by the roofing and sheet-metal company.

  1. Overview shots of the slopePhotograph the entire slope from the safety scaffolding or the roofer's working platform to show the overall flatness, the alignment of the counter-battens and the correct tension of the breathable membrane without pockets.
  2. Close-up details of individual pointsTake a sharp photo from less than one metre at each critical point: ventilation penetration, valley, hip, connection to the eaves drip edge and watertight junction against the gable wall.
  3. Checking bridging strips and repairsPhotograph every patch applied over an accidental perforation, with a compatible sleeve pressed down with a roller in accordance with the manufacturer's instructions.
  4. Secure archiving with complete metadataFile the photos in the site technical file under a standardised naming system (job number, date, South/North slope), keeping the original unmodified files that contain the time stamp.

Formal validation of the roof underlay is recorded in the daily site report before the order is given to the sheet-metal workers and roofers to install the eaves elements, flashings and bundles of tiles. This rigorous habit protects the company against unjustified claims when condensation later appears on the underside due to an internal airtightness defect.

Handling non-conformities and locking the acceptance file

Discovering a defect in the roof underlay before the covering operation requires a strict stop to the laying of tiles or slates on the affected area. Once the covering elements are fixed on the battening, watertightness or windtightness defects become invisible and cause damage whose destructive investigation is costly. Any fault found during the systematic check — membrane torn by a tool, creased adhesive tape, lifted ventilation sleeve or counter-batten nailed without a sealing strip under the ridge — must be recorded and dealt with before the covering battens are installed.

  • Immediately cordon off the non-conforming area and notify the foreman or team leader.
  • Cleanly cut out the damaged area with a cutter and fit a patch compliant with the sheet manufacturer's instructions, bonded or welded depending on the watertightness class.
  • Replace or bridge the failed adhesives on a dry, dust-free and degreased substrate, ensuring systematic rolling-down with a roller.
  • Redo the joints on technical ducts or dormers with the appropriate sealing sleeves and a continuous bead of elastomeric adhesive.

The site manager records this rework in the self-inspection protocol. Under art. 365 CO, if a circumstance jeopardises the proper or timely execution of the work, the contractor informs the client. Rigorous application of the duty to notify protects the company in the event of interference caused by another trade, in particular during late openings made by electricians or plumbing installers.

Final validation rests on an evidential photographic record. The photos must include clear visual references: digital time stamp, a wide shot including the roof slope and a close-up documenting the repair as well as the compliance of the verge, valley and ridge junctions. Under CO, acceptance of the work discharges the contractor, except for defects that could not be detected during the regular inspection or that he intentionally concealed. The countersigned self-inspection file guarantees full traceability before final concealment by the covering.

Frequently asked questions

How do you repair an accidental tear in the roof underlay sheet before battening?

The repair depends on the roof's load class. For a standard sheet, apply an original underlay patch extending beyond the tear by at least 150 mm in all directions. On a clean, dry substrate, bond this patch with the jointing adhesive recommended by the manufacturer or a technical adhesive certified for exterior use, then roll down firmly to eliminate air bubbles and ensure continuous watertightness.

What should you do if a plumber pierces the roof underlay after the acceptance check is finished?

Prohibit covering of the affected slope until the situation is rectified. Draw up a formal notice of damage with photos for the attention of the site management. Require the installation of a prefabricated EPDM rubber sealing sleeve suited to the exact diameter of the primary ventilation pipe. The connection to the roof underlay sheet must be carried out or approved by the sheet-metal roofer before tile laying resumes.

Which photographic views are essential to prove the compliance of valleys?

Take at least three photos per valley: an overview of the valley gutter showing the doubled sheet and its centring on the valley axis; a close-up showing the fixing of the battens set back at least 100 mm from the valley bottom; and a sharp close-up documenting the upper overlap or the welded connection at the eaves with a visible time stamp.

Is a simple smartphone photo enough to prove that the nail strip under the batten was installed?

Yes, provided a strict protocol is followed. The photograph must be sharp, unedited and retain its EXIF metadata (date, time, GPS geolocation). Take a close-up showing the sealing strip compressed under the counter-batten when nailing onto the rafter, together with a scale reference and a wider shot locating the roof frame axis being inspected.

Texts and standards cited

  • CO art. 365material and ground: the contractor is liable for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).
  • COacceptance of the work: the contractor is discharged, except for defects that could not be detected during the regular inspection or that he intentionally concealed.

In the same section